(456)Which of the following is true about job chains?
A. They consist of one or more Scheduler programs.
B. They are used to implement dependency scheduling.
C. They are used to implement time-based scheduling.
D. They are used to implement event-based scheduling.
E. None of the above.
答案:(B)
解析:
《Administrator’s Guide》 29.6 Creating and Managing Job Chains
Job chains是一个命名的一系列的任务,这些任务为了一个组合的目标而链接在一起.
chains是手段,通过它可以实现dependency based scheduling,即job的开始是依赖于之前的一个或多个job的输出.
来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/17013648/viewspace-1298712/,如需转载,请注明出处,否则将追究法律责任。
转载于:http://blog.itpub.net/17013648/viewspace-1298712/