PS Material 漫谈 四: Exploding the Bill of Material

使用:

用户可以将带有bill of material (BOM), sales order BOM, or WBS BOM的物料分配给activity, 可以在network下一级级或完全(多级)展开BOM

以下情况需要展开BOM:

  • You want to maintain subordinate components in the BOM
  • The header material is not planned using MRP, but you want to trigger MRP for subordinate components
  • You want to change the structure of the bill of material as used in the current network.

For more information, see BOM Explosion

 

在BOM展开前,如果物料已经分配给了activity, 用户有以下选择:

  • You select the component and proceed as below. When you do this, the "header" material is assigned the item category T (text item) which means that no requirements will be generated for it, just for the subordinate items.
  • If you do not select the component, but enter it manually in the dialog box, it remains allocated to the network with the original item category. You can delete this component or define it as an assembly item, by giving it a negative requirements quantity.

 

操作:

选中要展开的物料

image

 

Expload the BOM

image

BOM Selection

image

Copy all the items

Caution: If you explode the BOM all at once, requirements could be generated both in the network and in MRP, depending on control of the BOM items. Since MRP always explodes the complete BOM, this could lead to multiple requirements for the same component.

image

Material Overview

image

转载于:https://www.cnblogs.com/lazymango520/archive/2011/01/06/1958758.html

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值