import java.util.*;
public class CriticalPath {
static class Graph {
int num; //顶点个数
Vertex[] vertices; //顶点数组
public Graph(int num) {
this.num = num;
vertices = new Vertex[num];
for (int i = 0; i < num; i++) {
//把每个顶点的入度初始化为0
//把每个顶点的最早开始时间初始化为0
//把每个顶点的最晚开始时间初始化为无穷大
vertices[i] = new Vertex(0, Integer.MAX_VALUE, 0, new ArrayList<>());
}
}
public void addEdge(String activityName, int u, int v, int weight) {
final Edge edge = new Edge(activityName, v, weight);
vertices[u].edges.add(edge);
vertices[v].inDegree++;
}
public Queue<Vertex> topologicalSort() {
Queue<Vertex> zero = new LinkedList<>(); //建立一个入度为0的顶点的队列
final Queue<Vertex> result = new LinkedList<>();
for (int i = 0; i < num; i++) {
if (vertices[i].inDegree == 0) {
zero.add(vertices[i]);
}
}
while (!zero.isEmpty()) {
final Vertex vertex = zero.poll(); //取出一个入度为0的顶点,遍历其边,将这些边的终点的入度减一
result.add(vertex);
for (Edge edge : vertex.edges) {
vertices[edge.vertex].inDegree--;
if (vertices[edge.vertex].inDegree == 0) zero.add(vertices[edge.vertex]);
}
}
return result;
}
public void criticalPath() {
//这个函数的主要工作分成4步。先得到一个图的拓朴排序;然后正向遍历这个排序来计算每个顶点的最早开始时间(etv);然后反向遍历这个排序来计算每个顶点的最晚开始时间(ltv);最后找到最早开始时间和最晚开始时间相同的路径输出。
final Queue<Vertex> sortedVertex = topologicalSort(); //得到图的一个拓朴排序序列
if (sortedVertex.isEmpty()) return;
calcEtv(sortedVertex);
calcLtv(sortedVertex);
//遍历拓朴排序后的节点,找出sTime==eTime的节点输出,即为关键路径节点,它们之间的边即为关键路径的活动
Vertex v = sortedVertex.poll();
traversal:
while (true) {
next:
for (Edge e : v.edges) {
//如果边指向的顶点的最早开始时间等于最晚开始时间,则这个顶点在关键路径上,输出这条边,并从下个顶点继续寻找
if (vertices[e.vertex].sTime == vertices[e.vertex].eTime) {
if (e.name != "") System.out.println(e.name);
v = vertices[e.vertex];
if (v.edges.size() == 0) break traversal; //如果这是最后一个顶点,直接跳出循环,程序结束
continue next; //换下个顶点继续寻找
}
}
}
}
//计算每个顶点的最早开始时间
private void calcEtv(final Queue<Vertex> sortedVertices) {
for (Vertex v : sortedVertices) {
//遍历顶点v所有的边,如果该边的终点e的最早开始时间小于顶点v的最早开始时间加上边的权重,则更新e的最早开始时间
for (Edge e : v.edges) {
if (vertices[e.vertex].sTime < v.sTime + e.weight) vertices[e.vertex].sTime = v.sTime + e.weight;
}
}
}
//计算每个顶点的最晚开始时间
private void calcLtv(final Queue<Vertex> sortedVertices) {
Vertex[] verticesArray = new Vertex[num];
verticesArray = sortedVertices.toArray(verticesArray);
verticesArray[num - 1].eTime = verticesArray[num - 1].sTime;
//逆序遍历拓朴排序后的节点
for (int i = 0; i < num; i++) {
//对于每个节点,从它的后驱节点来计算它的最晚开始时间,在所有结果中取得最小值,也就是最早的那个时间
for (Edge e : verticesArray[num - 1 - i].edges) {
if (verticesArray[num - 1 - i].eTime > vertices[e.vertex].eTime - e.weight)
verticesArray[num - 1 - i].eTime = vertices[e.vertex].eTime - e.weight;
}
}
}
}
static class Vertex {
int sTime; //事件最早开始时间
int eTime; //事件早晚开始时间
int inDegree; //事件的入度,即前驱节点数
List<Edge> edges; //相连的边表
public Vertex(int sTime, int eTime, int inDegree, List<Edge> edges) {
this.sTime = sTime;
this.eTime = eTime;
this.inDegree = inDegree;
this.edges = edges;
}
}
static class Edge {
String name; //边代表的活动的名称
int vertex; //边的终点的顶点
int weight; //边的权重,即活动所花费的时间
public Edge(String name, int vertex, int weight) {
this.name = name;
this.vertex = vertex;
this.weight = weight;
}
}
public static void main(String[] args) {
Graph graph = new Graph(10);
graph.addEdge("P1", 0, 1, 8);
graph.addEdge("P2", 0, 2, 5);
graph.addEdge("", 1, 3, 0);
graph.addEdge("", 2, 3, 0);
graph.addEdge("P7", 1, 6, 4);
graph.addEdge("P5", 2, 5, 7);
graph.addEdge("P3", 3, 4, 6);
graph.addEdge("P4", 4, 8, 4);
graph.addEdge("P8", 6, 7, 3);
graph.addEdge("", 8, 7, 0);
graph.addEdge("", 8, 5, 0);
graph.addEdge("P9", 7, 9, 4);
graph.addEdge("P6", 5, 9, 7);
graph.criticalPath();
}
}
有向图的拓朴排序及AOE网关键路径算法的Java语言实现