1.[单选题]【中项2022年5月】试题71

71、A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in ().

A.risk plan process

B.risk control process

C.risk response process

D.risk analysis process

答案:D

1.[单选题]【中项2022年5月】试题72

72、Machine leanning a fundamental concept of () research since the field ´s inception,is the study of computer algorithms that improve automatically throgh experience.

A. date center

B.artificial intelligence

C.edge computimg

D.lnternet Protocol Version 6

答案:B

1.[单选题]【中项2022年5月】试题73

73、The project () processes include: develop project charter, develop project management plan,direct and manage project work,manage project knowledge,monitor and control project work,perform integrated change control and close project or phase.

A.integration management

B.scope management

C.schedule management

D.resource management

答案:A

1.[单选题]【中项2022年5月】试题74

74、(  )includes the process for incorporating the organization's quality policy regarding planning managing and controlling project and product quality rquirements in order to meet stakeholders’objectives.

A.Project risk management

B.Project communication management

C.Project stakeholder management

D.Project quality management

答案:D

1.[单选题]【中项2022年5月】试题75

75、(  )is the process of monitoring the status of the project to update the projects costs and managing changes to the cost baseline.

A.Control costs

B.Costs udates

C.Validate scope

D.Monitor comnunications

答案:A

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论

“相关推荐”对你有帮助么?

  • 非常没帮助
  • 没帮助
  • 一般
  • 有帮助
  • 非常有帮助
提交
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值