Answer: The following priority sequence applies to the determination of the quantity structure.
Priority 1:If you assign a quantity structure on the initial screen of the cost estimate, the system uses it in any case.
Priority 1:If you assign a quantity structure on the initial screen of the cost estimate, the system uses it in any case.
Priority 2:The system determines the quantity structure data that you have entered in the cost estimate view of the material.
Priority 3:Via the selection method indicator in Materials Planning view 4 in the material master, you can control whether the quantity structure occurs according to validity (lot size, period) or according to production version.
Priority 4:The quantity structure is determined via the settings in the quantity structure control (Transaction OKK5).