目录
了解本文内容前,可以先读之前的关于patch的文章,希望可以给你带来帮助
Oracle Primavera P6 & Unifier等产品 Patch 补丁介绍_Oracle Primavera P6 & Unifier 项目(协同)管理-CSDN博客常有一些P6,PU用户向我咨询关于产品的功能问题,有些是本身的缺陷,经过了解得发现大多数这些用户安装的这些产品版本都是初始版,也就是从未打过补丁或更新的0版,典型如18.8.0.0,19.12.0.0,20.12.0.0,21.12.0.0https://campin.blog.csdn.net/article/details/123149918以下内容纯干货,全部摘自于ORACLE服务支持网站 Oracle Support, 涉及的内容也全为原版英文,需要的朋友可以找工具翻译,内容不包含对应的具体patch(补丁更新)文件
Patch 20.12.13.0
Component | Bug ID | Title |
WEB | 33812477 | CANNOT EDIT FUTURE PERIOD SPREADSHEET BUCKETS FOR PLANNED UNITS AND EARLY REMAINING UNITS IN P6 EPPM (RESOURCES TAB > ASSIGNMENTS PAGE) |
33792578 | APPROVALS > STATUS UPDATES PAGE EXECUTING INEFFICIENT/INCORRECT TASKACTV/UDFVALUE STATEMENTS | |
33783284 | WHY ARE THE PRIVILEGES REQUIREMENTS DIFFERENT BETWEEN CLIENT AND WEB WITH REGARD TO COPYING A READ-ONLY PROJECT? | |
33774152 | GLOBAL SEARCH AND REPLACE FAILS - THE CONVERSION OF THE DATA TYPE VARCHAR TO DATETIME PRODUCED AN OUT-OF-RANGE VALUE. | |
33767857 | DIFFERENT RESOURCE MANAGER CAN APPROVE TIMESHEET BY SWITCHING VIEWS IN APPROVAL PAGE | |
33733128 | 20 BP - HIERARCHICAL ASSIGNMENT CODE VALUES NOT RETAINED AFTER SAVE IF APPLIED VIA FILL DOWN | |
33706449 | FP COULD NOT FIND THE CONTEXT WBS FOR SECURITY CHECKING. {1} MIGHT NOT EXIST. | |
33701461 | 20 BP - UPGRADE LOG4J JAR TO 2.17.1 | |
33676475 | PROJECT CODES ARE NOT GROUPING PROPERLY IN SCORECARDS | |
33643447 | PORTUGUESE LANGUAGE TRANSLATION NOT 100% ON PROJECTS TAB, EPS PAGE AND ACTIONS MENU ITEMS | |
33643026 | DUPLICATE PROJECT CODES WHILE IMPORTING XML USING NEW NAME FEATURE IN IMPORT TEMPLATE | |
33641091 | RECENT USER ACTIVITY VIEW DOES NOT POPULATE ALL THE COLUMN DATA | |
33640485 | ACTIVITY PAGE GRIDDATA/LOAD STATEMENT LOADING PROJECTS WITH TWO TASK TABLE SUBQUERIES CAUSING PERFORMANCE DEGRADATION | |
33633440 | RISK RESPONSE PLAN WILL NOT STAY ACTIVE | |
33630721 | DELETED RELATIONSHIPS REAPPEAR AFTER RELATIONSHIP CHANGES SAVED | |
33612641 | MSP PROJECTS IMPORT INTO P6 WITH PERCENT COMPLETE TYPE SET TO PHYSICAL EVEN THOUGH IT IS SET TO DURATION ( % COMPLETE) IN MSP | |
33416712 | SQL SERVER: BUG 33368214 - FULLPATHNAME IN RESOURCEHIERARCHY IS NOT CORRECT | |
33416686 | PRE2012: THE FULL PATH NAME OF LAST 2 LEVELS FOR ANY CHILD IS SAME IN RESOURCEHIERARCHY TABLE . | |
33217532 | INVALID PATH WAS REQUESTED WHEN OPENING BUBBLE CHART WITH LABOR UNITS MORE THEN 999 HOURS | |
32842965 | CANNOT CLEAR REJECTED STATUS UPDATE | |
33809255 | ONLINE INDEX BUILD FAILS WITH ORA-00439: FEATURE NOT ENABLED | |
33654575 | UNEXPECTED RESULTS IN THE WBSHIERARCHY TABLE IN REFERENCE TO THE PARENTLEVELSBELOWROOT AND CHILDDLEVELSBELOWROOT COLUMNS | |
TM | 33655221 | BASELINE DATES DON'T SHOW IN TIMESHEETS FOR ACTIVITIES THAT WERE AUTOMATICALLY ADDED |
33507961 | FP - TIMESHEET SUBMISSION ERROR - TOTAL HOURS CANNOT EXCEED 24 HOURS PER DAY | |
SRVS | 33654866 | CUSTOMER WIPED PAUDITX BUT WHEN AUDIT DATA IS REPUBLISHED IT ONLY TOOK AUDIT DATA FROM THE DAY OF THE REPUBLISH |
33667063 | AFTER UPGRADING TO 20.12.9 P6 WS FAILS WITH ERROR THE MESSAGE CANNOT BE PROCESSED BECAUSE IT HAS EXPIRED | |
P6PRO | 33643306 | COPY/PASTE A BIG PROJECT IS SLOW IN PPM - SQL DATABASE |
33531556 | APPLICATION GENERATE ERROR VQCCR-2757-D WHEN GROUP USER BY GLOBAL SECURITY PROFILE | |
33449343 | UNEXPECTED CENTURY DATE DISPLAYED WHEN USING 2-DIGIT YEARS IN THE FUTURE FOR CONSTRAINTS DATE DIALOG BOX | |
33155621 | CONFLICTING SCHEDULE OPTIONS PROMPT AFTER ENABLING/DISABLING THE LOG TO FILE PARAMETER THEN SCHEDULING MULTIPLE OPEN PROJECTS | |
33760224 | UNABLE TO DEFINE CRITICAL ACTIVITIES IN VISUALIZER | |
33714783 | MSP TEMPLATE CREATES INVALID NOTES TAG FOR MSP XML EXPORT THAT CAUSES FILE CORRUPTION | |
33674499 | ENABLE PUBLICATION SETTING IS DISABLED AFTER MERGING REFLECTION PROJECT INTO SOURCE PROJECT | |
33664490 | ERROR EXPORT PROJECT XML | |
33615178 | PUBLISH PROJECT WEBSITE IS SLOW - BACKPORT IN 20.12 | |
33596914 | P6 PROFESSIONAL LINK TO UNIFIER THROWS ERROR 'NF(-'-3940-8 NOT FOUND (404) | |
33546964 | GROUPING ACTIVITIES BY START DATE WITH DAY INTERVAL IN P6 PROFESSIONAL SHOWS INCORRECT DATE FORMAT | |
33466700 | EMPTY WBS NODE BECOMES AN ACTIVITY WHEN EXPORTED TO MSP XML | |
33433490 | THE 'ACTIVITY RESOURCE ASSIGNMENTS' STAGE OF AN XER IMPORT TAKES ABOUT 80% OF THE TOTAL IMPORT TIME. | |
DBCONFIG | 33458464 | FP - UNABLE TO CONNECT DATABASELOGINS TOOL TO SQL SERVER WITH ENCRYPTED CONNECTION |
Patch 20.12.12.0
Component | Bug ID | Title |
WEB | 33648691 | RESOURCE USAGE PAGE NOT LOADING |
33637402 | DOWNLOAD FILE FROM NOTIFICATION WINDOW DOES NOT WORK WHEN ATTEMPTING TO DOWNLOAD A REPORT | |
33620576 | CHANGES FOR NULL CHECKS AND MINOR OPTIMIZATION IN STATUS UPDATES PAGE | |
33493661 | UNNECESSARY SERVER SIDE LOGGING WHEN SELECT ACTIVITY THAT DOESNOT HAVE RESOURCE ASSIGNMENT. | |
33596425 | USING FILL DOWN IN P6 WEB TO UNCHECK ENABLE SUMMARIZATION PRODUCES SEVERAL POPUPS | |
33586021 | PORTFOLIO VIEW SCORECARD PORTLETS FAILING TO LOAD WITH JAVA.LANG.NULLPOINTEREXCEPTION POST UPGRADE FROM 19.12.X | |
33557148 | MODIFY 20.12.10 P6.EAR TO NOT CONTAIN PASSWORD ENCRYPTED FILES SO CUSTOMER'S SECURITY SCANS WILL PASS | |
33546654 | GLOBAL SEARCH AND REPLACE ONLY USES FIRST VALUE IN THE COMMA SEPARATED VALUES | |
33513139 | RESOURCE ASSIGNMENTS VIEW NOT GROUPING BY HIERARCHY IN P6 WEB | |
33512897 | INCORRECT TIME IN MANAGE USER SESSIONS LAST ACTIVE TIME | |
33503584 | TIMESHEET TOTALS IN P6 WEB NOT SHOWING TOTALS FOR FIRST OR LAST DAY OF TIMESHEET PERIOD | |
33463110 | IN P6 WEB ACTIVITIES MULTIPLE ISSUES AFTER COPY AND PASTE EXISTING USER VIEW, AND AFTER ADDING FOOTER, PRINTING, AND RETURNING TO ACTIVITIES VIEW ERROR APPEARS | |
33388704 | NULL FOR FINISHDATE IN P6BLPROJECT, NULL FOR STARTDATE AND FINISHDATE IN P6BLWBS | |
32959927 | EXPORT LANGUAGE IS DIFFERENT THAN LANGUAGE SELECTED DURING LOGIN. | |
33236650 | RESOURCE ASSIGNMENT SPREADS (NOT PERIOD ACTUALS) FOR BASELINES ARE NOT AVAILABLE | |
TM | 33577050 | FP USERNAME WITH Ü IN THE NAME CAUSES AUTHENTICATION FAILURE |
33526581 | FP TEAM MEMBER MANAGED SERVER(S) JVM PROCESS CONSUMING HIGH CPU AND MEMORY - CLEARENTITYMANAGER CHANGES | |
33517120 | TEAM MEMBER LOGIN EXCEPTION ACCESSOR OR ITS CONNECTION HAS BEEN SET TO NULL. | |
33497408 | STATUS UPDATES FOR REMAINING DURATION AND PERCENT COMPLETE RESETS ORIGINAL DURATION | |
P6PRO | 33605141 | AFTER THE UPGRADE USER CAN'T SELECT OPTION FROM PAGE SETUP. |
33562945 | VERTICAL SIGHT LINES ARE PLACED BETWEEN WEDNESDAY AND THURSDAY AFTER SETTING SHOW MAJOR LINES EVERY TO 7 DAYS | |
33559255 | ACTIVITY USAGE SPREADSHEET PASTED INTO EXCEL DISPLAYS DATES BACK TO 00 | |
33531488 | INCORRECT RELATIONSHIPS BETWEEN TASK DEPENDENT AND FINISH MILESTONE | |
33576330 | PERIOD DATA AT ACTIVITY LEVEL LOST WHEN COPY/PASTING PROJECT | |
33571422 | IMPORT EXCEL XLSX FAILS WHEN UPDATING MILESTONES RELATIONSHIPS | |
33559964 | CSTR_DATE: INVALID VALUE OR DATA TYPE MISMATCH ERROR WHEN TRYING TO IMPORT XLSX FILES IN P6 PROFESSIONAL | |
33555301 | IMPORT / EXPORT REMAINING LAG FROM XLS DOESN'T WORK | |
33540032 | TIME DISPLAYED IN FOOTER REVISION BOX EVEN WHEN TIME IS DISABLED IN USER PREFERENCES | |
33530312 | INCORRECT NAME OF ACTIVITY TYPE = LEVEL OF EFFORT IN RUSSIAN | |
33433490 | THE 'ACTIVITY RESOURCE ASSIGNMENTS' STAGE OF AN XER IMPORT TAKES ABOUT 80% OF THE TOTAL IMPORT TIME. | |
33332097 | XML IMPORT IS VERY SLOW | |
32906183 | BUDGETED COST IS NOT CORRECTLY CALCULATED FOR SMALL VALUES FOR BUDGETED UNITS/TIME SEV 1 SR | |
INTG | 33623073 | P6 WEB SERVICES READACTIVITIES FAILS WHEN INCLUDING BASELINE FIELDS |
33585154 | TEMPLATEWBSOBJECTID PARAMETER FROM PROJECTSERVICE > COPYWBSFROMTEMPLATE OPERATION ALLOWS A WBS_ID VALUE FOR AN EPS | |
33572823 | INTERNAL-BP:P6 WS RESOURCE ASSIGNMENT SPREAD HAS INVALID DATA IN THE LAST BUCKET | |
33474369 | PROJECT LASTUPDATEDATE HAS DIFFERENT VALUES BETWEEN P6 WEB SERVICES AND PDS / PX. | |
DB | 33390934 | GETTING ERROR WHILE UPGRADE DATABASE FROM 16 TO 20 |
ADMIN | 33640462 | UPGRADE SCRIPT MISSING LOGIC TO CREATE NDX_PROJWBS_1 AS A LOCAL INDEX IF PARTITIONING ENABLED |
Patch 20.12.11.0
Component | Bug ID | Title |
WEB | 33516332 | 20 BP - REG: MY PREFERENCES THROWS ERROR AN INVALID VALUE WAS DETECTED FOR 'RETURNTOPAGE'. CLICK THE BROWSER'S BACK BUTTON TO RETURN TO THE PREVIOUS PAGE. |
33492851 | 20 BP - UPDATE DATE FIELDS IN ACTIVITY/EPS TAB DISPLAYS ERROR THIS VALUE IS NOT FORMATTED CORRECTLY | |
33488474 | 20 FP - P6WEB EPS VIEW DOES NOT SHOW EMPTY EPS NODES WHEN FILTER IS APPLIED | |
33486140 | THE DEBUG MESSAGES NOT CAPTURED IN P6WEBACCESSLOG WHEN SEVERITY LEVEL SET TO DEBUG | |
33462569 | 20 BP - ASSIGNMENT CODES VALUES DOES NOT RETAIN FILL DOWN AFTER SAVE | |
33451589 | ACTIVITY CODE COLUMN SORTING BLANKS NOT AS EXPECTED | |
33444480 | ADJUST HARD CODED EMAIL LOGGER LEVEL FROM INFO TO ERROR | |
33441303 | ERROR 'UNABLE TO LOAD UDF DEFS' WHEN ATTEMPTING TO SET A FILTER IN RESOURCES/ASSIGNMENTS WITH A UDF CONDITION | |
33425581 | OPTIMIZE ITERATIVE CODE FOR APPROVALS STATUS UPDATES PAGE FOR NON ADMIN USER | |
33358582 | VIEW MIGRATION UTILITY MIGRATES ONLY SOME VIEWS AND FILTERS AND THOSE THAT ARE MIGRATED ARE NOT VISIBLE | |
33250906 | ERROR 'PROBLEM POPULATING DATA INTO GTT PKLIST TABLE' WHEN ACCESSING ACTIVITIES VIEW IN P6 WEB | |
33043465 | DASHBOARD PORTLETS DO NOT ALWAYS DISPLAY DATA | |
SRVS | 33545791 | CANNOT ADD NEW PROJECTS THAT ARE COPIED FROM TEMPLATE VIA WEB SERVICES |
33488696 | 20 BP - P6 EPPM WEB SERVICE EXPORT SERVICE DOES EXPORT XML FILE WITH CORRECT ENCODING | |
TM | 33379784 | TEAM MEMBER MY ACTIVITIES TAB SLOW TO LOAD DATA WHEN USING WORK DISTRIBUTION FILTERS FROM USER ACCESS PAGE |
P6PRO | 33447744 | XSLX EXPORT TEMPLATE DOES NOT HONOR SELECTED COLUMN ORDER |
33411012 | DATABASE UPGRADE DOESN'T KEEP THE ROW HEIGHT CHANGE TO GLOBAL ACTIVITY LAYOUT | |
32996852 | TOTAL ACTIVITY COUNT IN WBS VIEW NOT UPDATED CORRECTLY | |
32416108 | P6 LAYOUT PRODUCES A PREVIEW THAT IS 8 PAGES WHEN THE DATA IS ONLY 7 PAGES | |
33477352 | EXTREMELY POOR PERFORMANCE WHEN EXECUTING GLOBAL CHANGE | |
33419559 | XML IMPORT FAILS WITH: JAVA.LANG.NULLPOINTEREXCEPTION | |
33378212 | IN P6 PROFESSIONAL ACTIVITIES LAYOUT IF GROUP AND SORT IS PRIMARY RESOURCE ANY COLLAPSED NODES ARE UNEXPECTEDLY EXPANDED AFTER LAYOUT SAVE OR SAVE AS | |
32790428 | IN P6 20.12.1 P6 PRO USER UNABLE TO SEE SUCCESSOR OR PREDECESSOR ASSIGN DIALOG AFTER CLICKING ASSIGN BUTTON |
Patch 20.12.10.0
Component | Bug ID | Title |
WEB | 33432605 | TIMESHEET APPROVAL PAGE IN P6 NOT DISPLAYING DETAILED HOURS FROM A P6 MOBILE SUBMITTED TIMESHEET |
33421276 | FP - P6 EXPORT TO P6 XML CAUSES SIGNIFICANT LOB GROWTH | |
33394996 | HIERARCHICAL QUERIES CAUSE PERFORMANCE ISSUE WHILE LOADING EPS PAGE WHEN GROUPING INTERVAL IS ONE | |
33368214 | FULLPATHNAME IN RESOURCEHIERARCHY IS NOT CORRECT | |
33326156 | TIMSHEET APPROVAL PAGE FAILS TO LOAD WITH: UNABLE TO LOAD DATA | |
33313441 | RESOURCE ANALYSIS PAGE LOADING CAN FAIL WHEN MULTIPLE USERS ARE SIMULTANEOUSLY LOADING DATA | |
33305090 | P6 WEB RESOURCES TAB ANALYSIS PAGE AND AREA CHART HOVER POPUP ONLY DISPLAYS PROEJCT ID AND MEASURED VALUE (UNIT OR COST) | |
33303561 | PROJECT PUBLICATION LOG AND AUTOMATED FAILED PUBLICATION EMAIL USES P6 INTERNAL DB PROJ_ID NUMBER AND NOT P6 UI PROJECT ID VALUE | |
31767676 | P6 RESOURCE ASSIGNMENTS PAGE ERROR UNABLE TO LOAD DATA. AN UNKNOWN ERROR HAS OCCURED | |
TM | 33335276 | ERROR GETSINGLERESULT() DID NOT RETRIEVE ANY ENTITIES AFTER CLICKING LOGIN WITH USING SSO WITH THE ALLOW ALTERNATE LOGIN ATTRIBUTE ENABLED |
SRVS | 33390540 | 20 BP - NOTEBOOK TOPICS WHICH INCLUDE SINGLE SET OF DOUBLE-QUOTATION MARKS IN HTML TAG ATTRIBUTES ARE PUBLISHED AS NULL TO WBSMEMOX.RAWTEXTNOTE |
33181947 | P6 WS READJOBLOG DOES NOT RETURN XML LOG | |
P6PRO | 33436349 | ABILITY TO DELETE THE GLOBAL DEFAULT CALENDAR WITHIN P6 PROFESSIONAL WHILE ATTEMPTING TO DELETE UNASSIGNED PROJECT LEVEL CALENDAR |
33373733 | FULL GLOBAL OR EPS ACTIVITY CODE HIERARCHY DOES NOT DISPLAY WHEN ASSIGNING A CODE VALUE AT LEVEL 3 OR HIGHER USING CURRENT PROJECT DATA ONLY STARTUP FILTERS | |
33215951 | P6 PROFESSIONAL WBS PAGE LOADS SLOW FOR ONE PROJECT WITH LARGE WBS STRUCTURE | |
33192233 | XER EXPORT IMPORT OR BATCH RPT CMDLINE WITH LAUNCHER DOES NOT CREATE LOG FILES WITH PRIMAVERA.CACHESERVICE.EXE | |
33388765 | FP - P6 EXPORT TO MS PROJECT XML PERFORMANCE AND SIGNIFICANT LOB GROWTH ISSUE | |
33357812 | /PASSFILE DOES NOT WORK FOR PRIMAVERA.CACHESERVICE.EXE | |
33286344 | GROUP BY OPTIONS SHOULD BE GREYED OUT WHEN SELECTING SHOW GRAND TOTALS IN GROUP AND SORT | |
32825167 | RESOURCE FILTER IN P6 PROFESSIONAL ONLY RETURNS VALUES WHEN SEARCHING FOR NAME AND NOT SURNAME |
Patch 20.12.9.0
Component | Bug ID | Title |
WEB | 33330802 | SCORECARD PORTFOLIO VIEW PROJECT NAME HYPERLINKS DO NOT OPEN THE PROJECT BEFORE REDIRECTING TO THE ACTIVITIES PAGE |
33319506 | FP UPDATE USERS FROM LDAP WITH SELECT ALL USERS - RETURNS NO RESULT | |
33290833 | FP - ERROR: ORA-01795: MAXIMUM NUMBER OF EXPRESSIONS IN A LIST IS 1000 WHEN COPY/PASTE PROJECTS | |
33277306 | P6 WEB APPROVALS TAB TAKES MINUTES TO LOAD | |
33251166 | SORT BY ACTIVITY CODE COLUMN NOT WORKING | |
33251021 | SEARCH FOR ACTIVITY CODE VALUES NOT WORKING IN ACTIVITIES VIEW | |
33225658 | STACKED HISTOGRAM IN RESOURCE ANALYSIS IS NOT SORTING ALPHABETICALLY | |
33210278 | TYPE AHEAD SEARCH IN PROJECT CODE FIELD IN GRID VIEW OF EPS DOES NOT RECOGNIZE CHILD PROJECT CODE VALUES | |
33197195 | FP DURATION DOES NOT CHANGE WHEN DRAGGING ACTIVITY START ON GANTT CHART | |
33180166 | HIERARCHICAL QUERIES CAUSE PERFORMANCE ISSUE WHILE LOADING EPS PAGE WHEN GROUPING INTERVAL IS ONE | |
33270003 | FP - WHEN LOADING ACTIVITES USING P6 API ALL TASKRSRC FOR THE PROJECTS ARE LOADED DURING EACH BATCH | |
33273500 | FP PRIMAVERA WEB SERVICES SYNCHRONIZATION ERROR | |
33294152 | BP- INVALID OBJECT LISTED FOR 20.12.5 NEW INSTALL OR UPGRADE IN 12.1.0.2 ORACLE DB | |
33173548 | 20 BP - P6 (WEB) AND P6 PROFESSIONAL USE DIFFERENT RESOURCE CALENDAR WORKTIME WHEN CALENDAR HAS NULL CALENDAR.CLNDR_DATA BLOB FIELD | |
33279324 | BP-CANNOT DOWNLOAD EXCEL XLSX FROM GLOBAL AND PROJECT SECURITY PROFILE PAGES | |
TM | 33279132 | [OCI MIGRATION ISSUE] ERRONEOUS EMAIL DETAILS FROM TEAM MEMBER VIEWER EMAIL SENDING FUNCTIONALITY |
SRVS | 33246025 | JAVA.LANG.ARRAYINDEXOUTOFBOUNDSEXCEPTION OR JAVA.LANG.NULLPOINTEREXCEPTION SUMMARIZING PROJECT WHICH USES DIFFERENT FINANCIAL PERIOD CALENDAR THAN PROJECT BASELINE |
33214484 | ERROR IN PARSING THE DATE SELECTING UPDATE HISTORY ON ACTIVITIES VIEW FOR MULTIPLE USERS AND PROJECTS | |
32883218 | SOME P6 PROJECT NOTEBOOK TOPICS PUBLISHING AS 'SPAN>' | |
P6PRO | 33219586 | IMPORT XLSX FAILS FOR SPECIFIC PROJECT |
33159081 | TIME DEFAULTS TO 00:00 WHEN DISABLING DISPLAY TIME IN USER PREFERENCES | |
33155553 | SCHEDULE LOG LOCATION POINTING TO NETWORK DRIVE CAN DEGRADE OVERALL PERFORMANCE WITH SCHEDULING OPERATION | |
33067059 | FS RELATIONSHIPS ARE CREATED WHEN ATTEMPTING TO CREATE SS, SF OR FF RELATIONSHIPS IN THE GANTT CHART | |
33244525 | XML IMPORT – ADVANCED OPTIONS - MISSING OPTION TO “MOVE TO PROJECT†CALENDARS/CODES UNDER ACTION. | |
33231679 | FP - SUMMARIZE PROJECT FAILED | |
33220683 | IN P6 PROFESSIONAL PAGE SETUP > OPTION TAB WHEN BREAK PAGE EVERY GROUP IS SELECTED BUT DISABLED RESULTS IN PAGE BREAKS AFTER EACH ACTIVITY ROW | |
33219973 | ACTIVITIES ARE NOT IMPORTED WHEN IMPORTING PRIMAVERA XML FILE | |
33210351 | LAYOUT REORGANIZES EVEN WITH DISABLE AUTO-REORGANIZATION ENABLED | |
33173377 | SHOW GRAND TOTALS PREVENTS EMPTY EPS NODES FROM BEING DISPLAYED | |
33121448 | EVENT CODE: AVAA0-0396-F CHANGING THE FILTER ON THE PROJECT VIEW FROM CURRENTLY OPEN TO ALL | |
33037753 | WBS ELEMENTS ARE NOT COPYING WPS & DOCS WITH ACTIVITES BETWEEN PROJECTS WHEN THAT OPTION IS SELECTED |
Patch 20.12.8.0
Component | Bug ID | Title |
WEB | 33149547 | INTERNAL-FP:[SQL SERVER] SELECTING A PARENT CODE VALUE ONLY LOADS RESOURCE DATA FOR IMMEDIATE CHILD CODES VALUES ON THE RESOURCE > ANALYSIS PAGE GROUPED BY RESOURCE CODE |
33146020 | VIEW SERVICE STATUS IMPORT JOB PROJECTS COLUMN SHOWING IMPORTING EPS NAME RATHER THAN THE IMPORTED PROJECTS NAME. | |
33141555 | RESOURCE ASSIGNMENTS VIEW DOES NOT LOAD | |
33123131 | FP - [SQL SERVER] RESOURCE > ASSIGNMENTS PAGE INCORRECT EXECUTES SECOND TASKRSRC STATEMENT WHEN FIRST STATEMENT MATCHES OR EXCEEDS DATA LIMIT AND VIEW CONTAINS UDF OR CODE | |
33085632 | ERROR INVALID PATH WAS REQUEST WAS RECEIVED WHEN TRYIN TO LOGIN IN P6 WEB | |
33036441 | GLOBAL CALENDARS ARE NOT SORTING PROPERLY IN ENTERPRISE DATA | |
33164010 | FP - P6 RESOURCEASSIGNMENT SERVICE ALWAYS RETURNS PRICEPERUNIT AS NULL VALUE FOR A ROLE | |
33124852 | ERROR: JAVA.LANG.NUMBERFORMATEXCEPTION: NULL WHEN LOADING RELATIONSHIPS USING ACTIVITY CLASS. | |
32999690 | EPS IS UNDER FILTER FOR PORTFOLIOS CAUSES AN ERROR | |
32671449 | FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES | |
32559858 | RESOURCE ANALYSIS PAGE TAKES OVER 1 MINUTE TO LOAD | |
33066149 | CHANGE ERROR RETURNED WHEN SUMMARIZING PROJECT WITH NO CALENDAR ASSIGNED | |
33167149 | IN P6 WEB IF A USER IS ASSIGNED A UIV THAT DOES NOT ALLOW ACTIVITY UDF EDITING THE UIV USER IS STILL ABLE TO EDIT THE UDF ON THE LOWER UDF TAB | |
33130147 | SERVICE STATUS PAGE IN P6 IS UNABLE TO LOAD - GETTING AN ERROR | |
TM | 33160145 | AFTER UPGRADE TEAM MEMBER IS TAKING THREE MINUTES TO OPEN THE PAGE |
CLOUDCONN | 32986124 | CLOUDCONNECT DOES NOT SYNCHRONIZE DATA |
P6PRO | 33102367 | CURTAINS ATTACHMENT NOT PRINTING OVERLAP IN PDF OR PRINT PREVIEW |
32818318 | P6 SHOWS NOT RESPONDING FOR 8-12 MINUTES WHEN ASSIGNING BASELINES | |
33124349 | IN P6 PRO DURING XER IMPORT IF A NON-DEFAULT IMPORT TEMPLATE IS SELECTED TO USE IT'S SELECTION IS NOT SAVED OFF. | |
33105897 | IN P6 PROFESSIONAL 'STATUS' VALUE IS MISSING FROM THE GROUP BY PICKLIST AND DOES NOT PRE POPULATE THE 1ST GROUP BY ROW WHEN CHOSEN | |
33104535 | P6 VISUALIZER SCHEDULE COMPARISON IS NOT WORKING | |
33103928 | ERROR: EVENT CODE: RRAGC-0089-9 WHEN LEVELING PROJECT | |
32779443 | CORRUPTED BASELINES CREATED INTERMITTENTLY | |
32617682 | FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES | |
31704565 | UNABLE TO LOCK PROJECT AT REQUESTED ACCESS LEVEL WHEN IMPORTING MSP XML FILE TO UPDATE AN EXISTING PROJECT | |
33202099 | SCHEDULE PROJECT SLOW PERFORMANCE IN 20.12.7 | |
32955489 | XML IMPORT FAILS TO IMPORT TO SQL SERVER PPM DATABASE | |
33028808 | WEBSERVICE FILTER LASTPUBLISHEDON |
Patch 20.12.7.0
Component | Bug ID | Title |
WEB | 33053293 | OAS :REPORT GENERATION ARE GETTING FAILED |
33041114 | THE PROJECT ARBITER FAILS AT 3:00 AM DAILY | |
33029042 | BP-ON DELETING CODES/UDF/STEPS NOT DELETED FOR PUBLISED X TABLES | |
32988267 | MISSING CAPTION IN APPLICATION SETTINGS FOR AUDITING | |
32982399 | CLASSIC VIEW MIGRATION FAILED WITH ERRORS | |
32963106 | DATA GETS PUBLISHED IN TO CHGMEMOX TABLE FOR ALL THE PROJECTS THOUGH ONLY SINGLE PROJECT IS PUBLISHED. | |
32958239 | THE USER LOGIN REPORT SHOWS DIFFERENT VALUES UNDER APP_NAME SINCE UPGRADING TO V20.12.4 | |
32936422 | WHEN SWITCHING BETWEEN SECURITY PROFILES THE LOWER PERMISSIONS PANE ALSO CHANGES | |
32877925 | 20 FP - SQLSERVER: FILTER CRITERIA NOT DISPLAYING PROJECTS WHEN THE NUMBER OF EPS/PROJECTS EXCEEDS MAX SETTING | |
32876372 | WHEN CREATING A NEW GLOBAL DASHBOARD FILTER,USERS RECEIVE THE ERROR: AN ERROR OCCURRED WHILE PROCESSING YOUR REQUEST. | |
31721941 | VIEW SERVICE STATUS IMPORT JOB PROJECTS COLUMN SHOWING IMPORTING EPS NAME | |
32973049 | P6 WEB SERVICES XML EXPORT FAILS WITH: FIELD FINANCIALPERIODTEMPLATEID HAS NOT BEEN LOADED OR SET. | |
32983183 | ACTUALTHISPERIODCOST SET TO LARGE NEGATIVE VALUE WHEN CREATING NEW RESOURCEASSIGNMENTS | |
33012838 | PRIMAVERA P6 IN AZURE - EXPORT PROJECT TO MICROSOFT PROJECT XML IS SLOW | |
32894598 | VALIDATE.BAT, DATABASELOGIN.BAT & DBSETUP.BAT USING SSL PORT GOT ERROR : SQLRECOVERABLEEXCEPTION: IO ERROR: NO APPROPRIATE PROTOCOL ( PROTOCOL IS DISABLED OR CIPHER SUITES ARE INAPPROPRIATE), AUTHENTICATION LAPSE 0 MS | |
33001533 | NEED TO REMOVE DROP SCRIPT IN GET_TASK_CODE_FOR_COPYWBS MSSQL PROCEDURE | |
32967352 | AFTER EPPM UPGRADE FROM V.18.8 TO 20.12 USERS CANNOT COPY WBS COPY WBS FROM TEMPLATE WHEN PROJECT STATUS IS INACTIVE | |
32929634 | COPY WBS FAILED WHEN COPYING A WBS FROM ANY PROJECT OR PROJECT TEMPLATE | |
P6PRO | 33038664 | P6 HANGS FOR MINUTES WHEN REFRESHING AFTER SUMMARIZING A PROJECT |
32996852 | TOTAL ACTIVITY COUNT IN WBS VIEW NOT UPDATED CORRECTLY | |
32976471 | WHILE SWITCHING FROM THE ACTIVITIES VIEW TO WBS VIEW, THE WBS SELECTED IN WBS VIEW IS NOT UPDATED | |
32801608 | IMPORT XML PROCESS COMPLETED SUCCESSFULLY BUT NO PROJECT AND ERROR IN LOG | |
31514547 | IN VISUALIZER TSLD LAYOUT FINISH DATE FILTERS ARE NOT WORKING AS EXPECTED | |
33030789 | LOADING DATA SUMMARY AFTER MANUAL SUMMARIZATION IS TAKING A LONG TIME | |
32988936 | PLANNED VALUE COST DIFFERS IN THE ACTIVITY USAGE SPREADSHEET AND THE ACTIVITY TABLE | |
32739773 | ??INCORRECTRESULTSIZEEXPECTED1ACTUAL0?? INCORRECT RESULT SIZE: EXPECTED 1, ACTUAL 0 WHEN ATTEMPTING TO SAVE A COPY OF THE CURRENT SCHEDULE AS A NEW BASELINE | |
30505276 | THE DATE ADDED IS TODAY'S DATE AND ADDED BY IS SYMON(BG) | |
32975530 | BP - STORED IMAGES CANNOT LOAD AFTER MIGRATING DATABASE |
Patch 20.12.6.0
Component | Bug ID | Title |
WEB | 32934025 | BP - ALLOCATION NOT CORRECT IN OPEN REQUEST FOR RESOURCES PORTLET |
32928082 | BP - REMOVING CURRENT VIEW COLUMNS AND SAVE CHANGES NOT REFLECTED | |
32911837 | 20FP - SWITCHING FROM DEUTSCH TO ENGLISH WILL MAKE COLUMN NAMES BE DISPLAYED IN DEUTSCH | |
32902698 | APPEARS POSSIBLE TO DELETE A PROJECT VIA P6 WEB EVEN IF SOMEONE ELSE HAS SAME PROJECT OPEN | |
32900793 | INTERNAL-BP:PRE213- PERIOD ACTUAL UNITS ARE INCORRECTLY CALCULATED FOR A SCENARIO IN PROJ ASSIGNMENTS PAGE | |
32900405 | INTERNAL-BP:PROJECT LEVEL COST DISCREPANCY BETWEEN ANALYTICS AND P6 | |
32895781 | DOCS: UNABLE TO ADD DOCUMENTS TO DOC FOLDERS FROM ACTIVITIES PAGE . | |
32871052 | AUTO-NUMBERING NOT USED WHEN PASTING ACTIVITIES FROM ANOTHER PROJECT | |
32866172 | DELETEPUBLISHDATA -DOESN'T DELETE THE RECORDS FROM CHGUDFVALUEX TABLE. | |
32841953 | FP P6 WEB CALENDAR DISPLAYED INCORRECTLY FOR 24X7 CALENDAR. | |
32970015 | STRANGE DATA ROW IS GENERATED IN TABLE RESOURCEASSIGNMENTSPREAD | |
32833853 | DATA MISSING IN COLUMNS WHEN EPS VIEW IS LOADED | |
32798853 | PRE- PORTFOLIO FILTERS ARE NOT SAVING WHEN A DATE FIELD WITH EQUALS OPERATOR IS APPLIED | |
32769012 | WHEN ACCESSING THE WEB. ALL PAGES GIVE ERROR, PAGE UNRESPONSIVE | |
31954320 | ASSIGN ROLE/RESOURCE DISABLED IN ACTIVITY DETAILS BUT NOT DISABLED IN CONTEXT MENU | |
TM | 32946250 | 20 BP - TIMESHEETS NOTES SHOW WRONG TIME - MISSING TIMEZONE IN DATE |
SRVS | 32846495 | 20FP - BASELINE1 SPREAD DATA FOR P6 WEB SERVICES ACTIVITYSPREAD IS INCORRECT |
32845663 | DISSOLVE ACTIVITY WEB SERVICE IS NOT WORKING GENERAL ERROR | |
32818373 | DISSOLVE ACTIVITY WEB SERVICE IS NOT WORKING IN SOME CASES | |
32855762 | IMPORTSERVICE-> UPDATEEXISTING IS FAILING FOR PROJECT WITH BASELINES. | |
32841625 | FP - BUG 32775117 - P6 WEB SERVICES XML IMPORT UPDATE EXISTING ERROR: PHYSICALPERCENTCOMPLETE: ACTIVITY PERCENT COMPLETE IS BASED ON ACTIVITY STEPS AND THEREFORE CANNOT BE MODIFIED | |
32946197 | BP - PROGRAMMATICALLY HANDLE INSERT OF PROJECT ARBITER JOBSVC ROW IF PUBLICATION IS ENABLED BUT SOMEONE IMPROPERLY REMOVES ROW FROM JOBSVC | |
P6PRO | 32775987 | IMPORT XER: CALENDAR INSERT NEW IS NOT INCREMENTED PER THE EXISTING GLOBAL CALENDAR |
32966465 | ACTIVITIES NOT GROUPED CORRECTLY | |
32964462 | GROUP SORT FUNCTION DOES NOT WORK AFTER UPGRADE | |
32811556 | IN P6 RESOURCE ASSIGNMENTS VIEW, WHEN ADDING A FILTER WITH CRITERIA ACTUAL MATERIAL UNITS WILL RESULTS IN AN ERROR - '[QT_HOUR=###]' IS NOT A VALID FLOATING POINT VALUE' | |
32722565 | PRIMARY CONSTRAINT HOUR FIELD NOT CHANGING IN ACTIVITY DETAILS LAYOUT |
Patch 20.12.5.0
Component | Bug ID | Title |
WEB | 32832036 | THE SCHEDULER PROCESS REQUIRES ADDITIONAL TIME TO COMPLETE - WHEN VIEW LOG FOR FAILED SCHEDULED SERVICE |
32830051 | RESOURCE PRICE/UNIT VALUE IS CHANGED WHEN THE DISPLAY CURRENCY SYMBOL IS CHANGED | |
32815639 | IN P6 WEB APPROVALS TAB HANGS WHEN SELECTED SINCE UPGRADING FROM 20.12.2 TO 21.2 | |
32773561 | RESOURCE NOTES TEXT COLOR APPLIED IN PROFESSIONAL NOT DISPLAYED IN EPPM | |
32773456 | DOWNLOAD LINK FROM P6 WEB CLIENT DOES NOT UPDATE AFTER EXPORT JOB COMPLETES SUCESSFULLY. | |
32759304 | THE FINANCIAL PERIOD VALUE DOES NOT ADVANCE AFTER STORED PERIOD PERFORMANCE IS EXECUTED. | |
32757685 | SETTING TIME TO SHOW AS PERCENTAGE DOES NOT WORK, STILL SHOWING DATA AS SHOW AS UNIT/DURATION | |
32739004 | FP PORTFOLIO FILTERS NOT SAVING FOR IS UNDER AND NOT EQUAL TO CONDITION | |
32737850 | EDIT FILTER TAB IS CLOSING IN EPS VIEW | |
32734514 | CANNOT ASSIGN RESOURCE ASSIGNMENT CODE TO A RESOURCE ASSIGNMENT | |
32723412 | THE APPLICATION DOES NOT DISPLAY THE INFORMATION CORRECTLY IN THE FIELDS PROJECT STATUS FROM COLUMNS AND FROM GENERAL TAB | |
32618959 | PRIVILEGE REQUIRED FOR UDF ASSIGNMENT.AND EDIT UDF VALUE IN UDF DETAILED TAB | |
32756878 | SERVICE LOG FILES SHOW IN UNFORMATTED XML WHEN INITIATED FROM P6 WEB BUT VIEWED FROM P6 PROFESSIONAL | |
32765759 | DBENGINE.EXECUTESTATEMENT FOR {CALL PV_LOGIN(?, ?, ?, ?)} FAILED: NUMERIC OVERFLOW | |
32814362 | Bug 32814362 - UNABLE TO UPGRADE 19.12.12 PMDB TO 20.12.0 -ALTER TABLE STATEMENTS FAILING | |
32828234 | [ORACLE ONLY] INCLUDE PDS TRIGGER FILTER IN UPGRADE SCRIPT LOGIC THAT RE-ENABLES ALL TRIGGERS OWNED BY THE P6 EPPM SCHEMA | |
31577521 | COPIED PROJECT RETAINING PROJECT ACTIVITY CODE FROM ORIGINAL CAUSING KEY NOT FOUND ERROR ALERT BOX TO DISPLAY | |
32677970 | NO LOCATION FOUND WHEN ENTERING THE GEO COORDINATES | |
32738574 | SR 3-25024826451: SPREAD DATA VALUES IS NOT COMING IN WEBSERVICE IN STAGE 20.12/BUG 32418691 - SPREAD DATA VALUES IS NOT COMING IN WEBSERVICE IN STAGE 20.12 | |
32671449 | FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES | |
32422137 | REVOKING A USER'S TIMESHEET MODULE ACCESS WILL CLEAR OUT 'USES TIMESHEET' AND 'TIMESHEET APPROVAL MANAGER' CAUSING INCORRECT APPLY ACTUALS | |
TM | 32800103 | UPDATES TO ACTIVITY UDF FIELDS IN TEAM MEMBER ARE NOT PUBLISHED TO THE EXTENDED SCHEMA |
32377728 | FOR CERTAIN TEAM MEMBER USERS AFTER LOGIN THEIR MY ACTIVITIES PAGE NEVER LOADS AND KEEPS SHOWING 3 SPINNING DOTS | |
SRVS | 32768018 | 20BP - ACTIVITYSPREAD SHOWS INCORRECT VALUES WHEN INCLUDING BASELINES |
32713519 | FP RISKS ARE NOT COPIED WHEN USING P6 WEB SERVICES COPYPROJECT | |
32808919 | BUG 31136153 - P6 RESOURCEASSIGNMENT SERVICE ALWAYS RETURNS PRICEPERUNIT AS NULL VALUE | |
P6PRO | 32787953 | USER WITHOUT UPDATE PRIVILEGE OF TEMPLATE CAN CHANGE TEMPLATE AFTER RENAME IT |
32757624 | PERFORMANCE DEGRADATION WITH ACTVCODE STATEMENT WHEN USING 'VIEW ALL DATA' STARTUP FILTER OR DISPLAYING ALL VALUES WITHIN ACTIVITY CODE WINDOW | |
32749704 | SLOW PERFORMANCE OF EXPORTING SPREADSHEET XLSX | |
32731637 | XLSX IMPORT PERFORMANCE IMPROVEMENT | |
32787985 | THE SEQ_NUM ON TWO DIFFERENT CHILD WBS RECORDS, UNDER THE SAME PARENT WBS, IS DUPLICATED | |
32751789 | GLOBAL CHANGE UPDATING UDF DATE TO NULL INSTEAD OF DELETING ROW | |
32750482 | P6 PROFESSIONAL HANGS ON RELATIONSHIPS TO EXTERNAL PROJECTS IMPORTING LARGE XER FILE | |
32554709 | ASSIGN GLOBAL ACTIVITY CODES IN P6 PRO TO ACTIVITIES - NOT RESPONDING |
Patch 20.12.4.0
Component | Bug ID | Title |
WEB | 32698883 | FP - VIEW GROUPING DIFFERENT BETWEEN VERSION 19 AND VIEW FROM VERSION 16 |
32693847 | INCOMPLETE URL REFER TO YOUR WELCOME EMAIL FOR THE URL IN DASHBOARD-RISKS TAB | |
32673711 | 20FP - IN P6 WEB IF THE USER EDITS THE DURATION FORMAT FROM DAY TO HOUR THIS CHANGES THE ASSIGNMENT'S PRICE / UNIT ($8.00/D) TO $1.00/H | |
32643657 | 20 BP - ACTIVITY AND EPS VIEW THEME SETTINGS DO NOT SAVE (CUSTOM COLORS) | |
32642689 | DASHBOARD PORTFOLIO VIEW SCORECARD PORTLET PERFORMANCE PERCENT COMPLETE NOT SUMMARIZING AS EXPECTED | |
32641922 | REPETITIVE SQL EXECUTED ONE TIME PER PORTFOLIO DEGRADING OVERALL PERFORMANCE LOADING 'MANAGE PORTFOLIO' WINDOW | |
32636719 | FP - TIMESHEET APPROVAL TAKES TOO LONG TO LOAD AND BECOME UNRESPONSIVE | |
32630562 | FP DIFFERENT BEHAVIOR IN PRO CLIENT / WEB WHEN CHANGING START DATE ON ACTIVITY | |
32622727 | FP - ADD/EDIT/DELETE RESOURCE ASSIGNMENTS FOR RESOURCE PLANNING STILL DISPLAYS IN ASSIGNED PRIVILEGES COLUMN AFTER UPGRADE | |
32612956 | OUTPUT FORMAT DROPDOWN IS BLANK IN P6 FOR SPECIFIC REPORT TEMPLATE | |
32607435 | COPY PROJECT TO CREATE NEW PROJECT- DOES NOT USE PROJECT PLANNED START DATE FOR NEW PROJECT | |
32603405 | RESOURCE SEARCH DOES NOT WORK FROM OPEN REQUESTS FOR RESOURCES PORTLET IN DASHBOARD | |
32591330 | FP - P6 EPPM MIGRATE.BAT LOGFILE - LOG LEVEL | |
32576631 | FILTER CRITERIA CHANGING UNDER MANAGE PORTFOLIOS | |
32487403 | FP - MIGRATING LARGE DATABASE - MIGRATE TOOL HANGS - DOES NOT LAUNCH | |
TM | 32654823 | GROUPING ACTIVITIES BY WBS IN TEAM MEMBER NOT CORRECTLY DONE |
32642884 | ERROR DATE OR UNIT FORMAT SPECIFIED WAS INVALID OR MISSING WHEN TRYING TO UPDATE ACTIVITY STATUS USING EAMIL STATUSING SERVICE | |
SRVS | 32712018 | FP PROJECT CODE/UDF ASSIGNMENTS GET MISSING AFTER IMPORTING XML FILE |
32622550 | 20FP - P6 SERVICES SCHEDULING LOGIC CAN SET WBS SUMMARY ACTIVITIES TO AN IN-PROGRESS STATUS WITHOUT AN ACTUAL START DATE | |
32564695 | FP- TASK_COPY_PKG.TASKPRED_COPY PACKAGE PROCEDURE CAN RUN SLOWLY WHEN OPTIMIZER USES HASH JOIN | |
32574050 | STATUS REVIEWER IN PROJECT SERVICE CANNOT BE SET | |
INTG | 32647746 | FP - PRIMAVERA GATEWAY RESOURCE ASSIGNMENT UPDATE ISSUE |
32694830 | FP - ERROR ILLEGAL CHARACTER ((CTRL-CHAR, CODE ##)) INVOKING THE IMPORTSERVICE USING ZIP FORMAT WHEN PROJECT DATA INCLUDES CERTAIN UNICODE DASH CHARACTERS | |
32635938 | FP FOR BUG 32469119 - ERROR ILLEGAL CHARACTER ((CTRL-CHAR, CODE ##)) INVOKING THE IMPORTSERVICE USING ZIP FORMAT WHEN PROJECT DATA INCLUDES CERTAIN UNICODE CHARACTERS | |
P6PRO | 32662702 | CHANGING ACTIVITY CALENDAR TO A CALENDAR WITH NON-WORK TIME CAUSES RESOURCE ASSIGNMENT DURATION TO SET TO 0 |
32650039 | THE CONVERSION OF A VARCHAR DATA TYPE TO A DATETIME DATA TYPE RESULTED IN AN OUT-OF-RANGE VALUE | |
32606566 | ACTIVITIES ARE MOVED TO AN EPS FROM ITS ORIGINAL WBS NODE AFTER MODIFYING THE ACTIVITY RELATIONSHIP | |
32606334 | WHEN ASSIGNING RELATIONSHIPS, FOCUS MOVES TO ASSIGNED ACTIVITY | |
32605057 | CHOOSING CUSTOM DATE FOR PAGE SETUP TIMESCALE DIRECTS TO YEAR 1899 | |
32598730 | P6 CLIENT LOGIN FAILING WITH ERROR 'UNABLE TO CONNECT DATABASE' | |
32565894 | NOTEBOOK TOPIC DISPLAYS TEXT AFTER APPLYING FILTER, THEN OPENING UP A DIFFERENT PROJECT | |
32648631 | RESOURCE ASSIGNMENT LAYOUT SHOWS DASHES INSTEAD OF NUMBERS AT SUMMARY LEVEL WHEN PRINTING | |
32618834 | INDICATOR ICON IN COLUMN NOT DISPLAYING CORRECTLY | |
32617682 | FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES | |
32591422 | P6 PRO AND P6 WEB INVALID RELATIONSHIP TYPES | |
32586297 | ERROR SAVING MODIFIED UN/CEFACT XML TEMPLATE <DATE>T<TIME> IS NOT A VALID DATE/TIME VALUE | |
32532931 | UNABLE TO RUN P6 PROFESSIONAL REPORTS IN PRODUCTION | |
32517551 | ACTIVITY CODE ASSIGNMENT/REMOVAL ISSUE | |
32108186 | P6 PROFESSIONAL VIA CLOUDCONNECT: UNABLE TO CONNECT TO THE DATABASE. PLEASE RUN THE DATABASE CONFIGURATION TOOL OR CONTACT YOUR ADMINISTRATOR. | |
32652945 | IMPORTING XER FILE TRUNCATES FRONT OF NAME | |
32604136 | EXPORT LAYOUT FROM VISUAIZER FAILS WHEN THE LAYOUT NAME CONTAINS A FORWARD OR BACKWARD SLASH |
Patch 20.12.3.0
Component | Bug ID | Title |
WEB | 32581820 | SR 3-25330538341: [DEV/UAT] ALL NON-ADMIN SUPERUSERS RECEIVE ERROR INVALID REQUEST ACCESSING P6 WEB ACTIVITIES PAGE |
32566751 | FILL-DOWN VALUES NOT POPULATED UNTIL AFTER PAGE IS SAVED | |
32566022 | INTERNAL-FP: RESOURCE OVERALLOCATION VIEW VS TEAM USAGE SHOWING DIFFERENT VALUES FOR THE SAME RESOURCES. | |
32542925 | IN RISKS PAGE - ON UPDATING UDF FIELDS LAST MODIFIED BY FIELD IS NOT BEHAVING AS EXPECTED | |
32530717 | P6 WEB ACTIVITIES PAGE DOES NOT LOAD FOLLOWING UPGRADE FROM V19.12.10 TO V20.12.1 | |
32519870 | USERS CANNOT RESET VIEWS IN P6 WEB MY PREFERENCES VIEW TAB AFTER UPGRADE TO V20.12.1 | |
32518923 | SUMMARY DATA COLUMN IS BLANK WHEN USE FORMULA IS SELECTED | |
32509859 | 20FP - SCREEN TAKES 5 MINUTES TO POPULATE WHEN TRYING TO ASSIGN PRIMARY RESOURCE | |
32508076 | IN P6 EPPM WHEN CLICKING ADD BUTTON THE WEB PAGE FAILS TO LOAD AND IS DOES NOT RESPONDING. | |
32507336 | 20 FP - COLUMN ORDER WHEN EDITING SCORECARD IS NOTE SAVED | |
32500507 | EXTRA CHARACTERS ARE ADDED WHEN OPENING A DOCUMENT LINK IN P6 WEB IN THE ACTIVITY SECTION. | |
32483721 | MODIFIED DATA LIMITS IN ADMINISTRATION TAB SET BACK TO DEFAULTS AFTER UPGRADE TO V20.12.1 | |
32481667 | WHEN A P6 USER IS DELETED THEIR DISCUSSION NAME IS REMOVED IN P6 WEB FROM THE UI IN THE ACTIVITIES VIEW, DISCUSSION TAB | |
32495800 | BP - IMPROVEMENT IN RESOUCE ANALYSIS PAGE FOR ENTIRE DATE RANGE | |
32471699 | JAVA.LANG.ILLEGALARGUMENTEXCEPTION: INVALID FIELD UDF_### FOR PROJWBS EXCEPTION OCCURS WHEN ADDING FORMULA UDF COLUMN TO VIEW | |
32461558 | FILE NOT FOUND IN THE SERVER. PLEASE CONTACT YOUR ADMINISTRATOR. CLICKING DOWNLOAD FILE LINK FROM VIEW NOTIFICATIONS PAGE OVER SSL & HTTP/2 PROTOCOL | |
32461428 | IN P6 WEB V20.12.1 WHILE LOADING ENTERPRISE DATA > ACTIVITIES > ACTIVITY CODE - GLOBAL PAGE THE ERROR PAGE NOT IMPLEMENTED RESULTS | |
32312694 | STATUS UPDATES PAGE DOES NOT LOAD | |
TM | 32498405 | TEAM MEMBER PROJECT FILTER DISPLAYS ACTIVITIES FROM ONE PROJECT WHEN PROJECTS HAVE SAME PROJECT NAME |
SRVS | 32531817 | PROJECT SUMMARIZATION PERFORMANCE DEGRADATION WITH BASELINE COMPARISION SQL |
P6PRO | 32523211 | FINANCIAL PERIODS END DATE IS 12:00 AM |
32464541 | AVAA0 EXCEPTION WHEN OPENING A PROJECT AND LOADING ACTIVITY PAGE USING A LAYOUT WHICH CONTAINS ACTIVITY CODE HIERARCHICAL GROUPING | |
32439933 | RESOURCES LISTED UNDER DATA TYPE: PROJECT WHEN MODIFYING IMPORT CONFIGURATION | |
32434311 | ACTIVITY CODES IN JAPANESE LOST AND CHARACTERS GARBLE AFTER UPGRADING FROM R15.1 TO R19.12 SEV 1 SR | |
32415673 | STREAM READ ERROR DESELECTING THE ENABLE SUMMARIZATION CHECKBOX | |
32566047 | P6 PROFESSIONAL REPORTS RUNNING VERY SLOW OR STUCK WITH OUT ANY PROGRESS | |
32506643 | ERROR SCHEDULING PROJECT ERROR SSFII-0822-6 | |
32501284 | IN P6 PROFESSIONAL WHEN A NOTEBOOK IS DISPLAYED IN GANTT VIEW AS A BAR LABEL THE ACTUAL ROW HEIGHT IS MUCH GREATER THAN THE VALUE ENTERED | |
32501197 | IN P6 PROFESSION (19.12.9 AND 20.12) APPLYING TABLE AND FONT ROW HEIGHT VALUE IS ALSO RESIZING GROUP BY BANDS (INCORRECTLY) | |
32500997 | WRONG ENCODING IN E-MAIL | |
32494669 | ACTIVITIES VIEW ROW HEIGHT CHANGES ARE NOT BEING RETAINED AND REVERTS BACK TO DEFAULT ROW SIZE AFTER SAVING LAYOUT | |
32482461 | PRIMAVERA XML EXPORT/IMPORT TAKES MUCH LONGER IN R19.12.X THAN IT DID IN 17.12.X | |
32463346 | 32333789 - TRACE LOGIC SLOW TO LOAD | |
32462080 | PRINT PREVIEW IN P6 PROFESSIONAL 19.12.10 SHOWS LARGER FONT SIZES UNTIL ZOOMED IN | |
32459491 | EURO SYMBOL IS NOT ACCEPTED WHEN CREATING A NEW SQLITE DB IN CURRENCY SYMBOL BOX | |
32434490 | AVAA0 ERROR WHEN CREATING CUSTOM TOOLBAR | |
32434415 | CUTTING A GLOBAL ACTIVITY CODE AND PASTING INTO GLOBAL ACTIVITY CODE CAUSES THE CODE TO GO MISSING | |
32469681 | P6 PPM MSP XML WITH MANDATORY CONSTRAINTS GENERATES ERRORS WHEN IMPORTING IN MICROSOFT PROJECT | |
32569080 | PROJECT LOAD SLOW AFTER MIGRATION | |
32459410 | MISSING DATA IN RISKS |
Patch 20.12.2.0
Component | Bug ID | Title |
WEB | 32479634 | SELECTED COLUMNS NOT DISPLAYED IN SAVED VIEWS AND ISSUES WITH PINNED COLUMNS |
32450875 | FP - THE NEW TIME PERIOD ABBREVIATION IS NOT TAKEN INTO ACCOUNT IN RISKS | |
32444227 | BP - REG:ORA-00918: COLUMN AMBIGUOUSLY DEFINED WHILE COPY PASTING ISSUE SECURE CODE | |
32436988 | ERROR PASTING ACTIVITY WHEN NEGATIVE BASELINE DATE AND/OR DURATION VARIANCE COLUMN(S) IN VIEW | |
32428945 | FP FOR BUG 32374238 - GLOBAL SEARCH & REPLACE - PROJECT NAME NOT APPEARING FOR ACTIVITY LEVEL CRITERIA | |
32420317 | 20.12FP-USERS.USER_NAME CHANGES AFTER ADJUSTING USER ACCESS ON A NEW MULTI-USER VIEW CREATED AS A COPY OF AN EXISTING MULTI-USER VIEW | |
32413229 | 20 FP - PROJECT STATISTICS CAN'T DISPLAY ANY INFORMATION IN TRADITIONAL CHINESE ENVIRONMENT | |
32405996 | NO LOCATIONS FOUND WHEN ATTEMPTING TO ADD LOCATION WITH ADDRESS IN OCI ENVIRONMENT | |
32371923 | TEAM USAGE PAGE DOES NOT LOAD ON SDTEST ENVIRONMENT | |
32328874 | 20 BP - PRE211: TITLE CONTAINS /:*?<>| SPECIAL CHARACTERS, ERROR IS NOT DISPLAYING FOR WP&DOCS | |
32283946 | SPECIFIC REPORT ADDED TO A FOLDER IN BIP CAUSES OTHER REPORTS TO NOT DISPLAY IN P6 WEB | |
32267379 | PORTFOLIO FILTER NOT UPDATING IN DASHBOARD | |
32221097 | PROJECT NAME DISPLAYED IN PORTOFOLIO TAB IS NOT THE SAME AS THE OPENED PROJECT | |
TM | 32450660 | FP - ONLY TEAM MEMBER CAN NOT BEEN STARTED ONCE DATABASE SSL ENABLED |
32438831 | TEAM MEMBER MODULE CREATING USESSION.DB_ENGINE_TYPE='INT_API' ROWS | |
31618353 | ACTION REQUIRED TAB SHOULD BE HIDDEN, WHEN THERE IS ONLY INACTIVE PROJECTS DATA AVAILABLE | |
SRVS | 32435540 | ACTIVITYSPREAD'S REMAINING COSTS DO NOT MATCH THE ACTIVITY'S REMAINING TOTAL COST |
32378970 | PROJECT SUMMARIZATION PERFORMANCE DEGRADATION | |
32344607 | 20 FP - SQLSERVER -BUG 32123798 - ASSIGNMENT SPREAD DATA IS NOT KEPT UP TO DATE WITH LATEST START AND FINISH DATES OF ASSIGNMENT | |
32324986 | PERFORMANCE IMPROVEMENT - ENHANCE PROJECT COPY/PASTE WITH BASELINE FROM USING PROJECT_COPY_BASELINE TO DBCRUD CODE | |
INTG | 32379622 | COPYWBSFROMTEMPLATE RETURNS THE PARENT UNIQUE IDENTIFIER OF THE NEW WBS |
P6PRO | 32451963 | SELECTING FINISH ON A STARTED ACTIVITY THEN MOVING THE FINISH DATE AHEAD CAUSES THE HH:MM TIME VALUE (16:00) TO REVERT TO MIDNIGHT (00:00) |
32400883 | EXPORTING PROJECT FILE SHOWS INVALID FORMAT. | |
32382534 | CANNOT OPEN EXCEL FILE AFTER IMPORTED INTO P6 |
Patch 20.12.1.0
Component | Bug ID | Title |
WEB | 32321014 | FILE NOT FOUND IN THE SERVER. PLEASE CONTACT YOUR ADMINISTRATOR.CLICKING DOWNLOAD FILE LINK FOR XML EXPORT JOB FROM PROJECT SCHEDULED SERVICE PAGE OVER SSL & HTTP/2 PROTOCOL |
32312676 | SEARCH CRITERIA CLEARED OUT WHEN ASSIGNING RESOURCE CODE VALUE | |
32312030 | IN P6 WEB FROM ADMINISTRATION TAB PSS UNABLE TO DOWNLOAD EXPORT XML FILE LINK, HITTING CRITICAL ERROR FILE NOT FOUND IN THE SERVER | |
32310780 | 20FP - BUG 32064358 - LOSS OF FUNCTIONALITY IN P6 WEB ACTIVITY ID FILTER PARAMETER (CLASSIC VIEW) NO LONGER EXISTS IN V19.12.X (STANDARD VIEW) AND REPLACED WITH ID/CODE PARAMETER | |
32309814 | 20 FP - UNABLE TO SELECT THE WBSCODES FROM THE 'SEARCH' PICKER IN THE GLOBALSEARCHAND REPLACE WBS SEARCH CRITERIA | |
32288106 | USERS NEED TO SELECT INDIVIDUAL ACTIVITY IDS WHEN FILTERING WITH MULTIPLE PROJECTS OPEN | |
32261087 | FP FOR BUG 32177958 - IN P6 WEB (V19.12.11) PROJECTS/EPS GLOBAL SEARCH AND REPLACE FAILING WITH PROJECT CODES | |
32257557 | FP BUG 32168434 - USER PREFERENCES FOR RESOURCE USE CURRENT ASSIGNMENT'S UNITS/TIME NOT CONSISTENTLY APPLIED | |
32254238 | SEARCH NOT WORKING WITH PROJECT CODE FILTER WITH MULTIPLE NOT EQUAL TO VALUES | |
32245284 | FP - DATA IN PROJECT UDF AND CODES COLUMNS APPEARING AS BLANK IN EPS VIEWS | |
32244775 | 20 FP - DOCUMENT CANNOT BE SAVED WHEN URL CONTAINS CHAR BEHIND CHAR | |
32240624 | FP - ON P6 WEB RISKS COST COLUMN SHOWS INCORRECT DECIMAL AND DIGIT GROUPING SYMBOL | |
32240612 | FP - DATABASE MIGRATION PRODUCES ERROR THIS IS AN UNSUPPORTED FEATURE: GETBYTES | |
32240429 | FP - UNABLE TO DELETE PUBLISHED PROJECT TEMPLATE DATA | |
32229684 | JAVA.LANG.INDEXOUTOFBOUNDSEXCEPTION LOADING EPS VIEW THAT CONTAINS HIERARCHICAL GROUPING AT SPECIFIC GROUPING LEVEL WHEN UDF ADDED AS COLUMN AND THE GROUPING LEVEL IS STORED AS STRING | |
32228857 | FORMULA UDF NOT CALCULATING AFTER UPGRADE TO 20.10.0.2 | |
32224844 | JAVA.LANG.ILLEGALARGUMENTEXCEPTION: INVALID FIELD FOR PROJWBS LOGGED ONE TIME PER PROJECT WHEN REMOVING GROUPING BAND ON EPS PAGE POTENTIALLY CAUSING GRIDDATA REST CALL TO FAIL | |
32221665 | 20 FP - IN P6 WEB (19.12.11) GLOBAL SEARCH AND REPLACE ALLOWS A BLANK 'IS A REQUIRED FIELD' VALUE | |
32214489 | OBS HIERARCHY SHOWING DIFFERENT ORDER WHEN ASSIGNING RESPONSIBLE MANAGER TO PROJECTS | |
32213593 | STAGE - ACTIVITIES PAGE IS SLOW TO LOAD | |
32213319 | PARTICULAR ACTIVITY VIEW CAUSES THE ACTIVITIES TAB TO HANG | |
32211049 | FP BASIC DASHBOARD PORTLETS ARE NOT WORKING ANY MORE | |
32188658 | USERS NOT SEEING ALL PROJECTS IN EPS VIEW | |
32084450 | FP OF BUG 31896759 - IN P6 WEB PROJECTS TAB /EPS PAGE GLOBAL SEARCH AND REPLACE FAILING WHEN PROJECT CODES ARE USED | |
31887131 | IN P6 WEB STAGE 20.8 UNABLE TO IMPORT ACTIVITY VIEWS EXPORTED FROM PROD 19.12.3 WITH THE ERROR UNEXPECTED ERROR. UNABLE TO IMPORT VIEWS | |
TM | 32309449 | 20 BP - TIMESHEETS NOTES SHOW WRONG TIME |
32303084 | TEAM MEMBER FUNCTIONALITY WITH 508 COMPLIANCE - JAWS READER (MY TASKS VIEW) | |
SRVS | 32281525 | BP - LARGE PROJECT LEVEL RESOURCE ASSIGNMENT SPREADS CAUSING EPS ROLLUP SUMMARIZATION JOB TO CONSUME LARGE VOLUME OF MEMORY BY JVM RUNNING P6 SERVICES |
32252205 | 20 FP - ASSIGNMENT SPREAD DATA IS NOT KEPT UP TO DATE WITH LATEST START AND FINISH DATES OF ASSIGNMENT | |
32333029 | PRIMAVERA EXPORT PROJECTS FAILED FROM REMS P6WEBSERVICES (SOAP-ENV:FAULT XMLNS:SOAP-ENV) | |
P6PRO | 32310049 | MSP XML IMPORT ERROR - VALUE FOR FIELD HOURSPERYEAR IN CALENDAR MAY NOT BE SET TO GREATER THAN 8784 |
31341023 | P6 PROFESSIONAL CONNECTION FAILURE THROUGH AUTHENTICATED PROXY USING CLOUD CONNECT |