在做货物移动时,跳出如下错误:
Internal error in LMLCCS_UPDATEF02 LCL_DB method get_normvector position A with RC 1
这个内部错误,比较吓人,也比较少见。原因是在ML已经生产启动后,再次修改成本组件分割配置造成的。
我碰到这个问题,所幸的是,在SDN中找到了解决方法,摘录如下:
Re: Error During MB1C with MVT type 531 Posted: Oct 15, 2008 7:35 AM in response to: Kevin Dai
Hi Greetings
The error reported may be because of the fact that you have activated the actual cost component split in Customizing after the production startup.
Please refer the OSS notes
" Note 639675 - Initialization of the actual cost component split".
May be helpful.
Gobinathan G
Re: Error During MB1C with MVT type 531 Posted: Oct 15, 2008 8:14 AM in response to: Gobinathan Govi...
Hi Gobinathan
Notes 639675 is exact what we want! The problem resolved after we run reports MLCCS_RESET and MLCCS_STARTUP in sequence . Thaks for you helpful reply
BR
Kevin
来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/494216/viewspace-613676/,如需转载,请注明出处,否则将追究法律责任。
转载于:http://blog.itpub.net/494216/viewspace-613676/