通过MRP例外信息,可以使计划调整计划参数设置,计划环境,产能负荷方面信息,同时使MRP运行出来的数据更合理和更准确。
目前公司用到10, 15,16,17,18,20,21
[@more@]1.Items allocated across projects: items whose supply for one project has been allocated to the demand of a different project
2.Items below safety stock: items for which demand, less supply, brings the projected quantity on hand to a negative level or below safety stock
3.Items that are over–committed: items for which ATP is negative or below safety stock
4.Items with a shortage(短缺物料): items whose quantity on hand is less than the sum of the requirements plus safety stock, within the exception time fence defined by the item’s planning exception set(在手量少于(总需求量+安全库存量)被视为短缺物料,在例外集定义)
5.Items with a shortage in a project(一个项目中无论短缺物料): items whose demand exceeds supply with a project/task for an item(在一个项目中,需求大于供给的短缺物料)
6.Items with excess inventory(超出库存料件): items whose quantity on hand exceeds the total requirements against the item, within the exception time fence defined by the item’s planning exception set(当前库存超出总需求数量,在例外集设定值之上的料件)
7.Items with excess inventory in a project(在一个项目中超出库存料件): items whose supply exceeds demand with a project/task for an item(在一个项目中,一个料件供给超出需求)
8.Items with expired lot(过期料件): lots that expire within the planning horizon(在水平展望期内批量过期)
9.Items with negative starting on hand(在手量开始为负库存料件): items with a negative onhand beginning balance(在手量开始为负库存料件)
10.Items with no activity(不具有活动的物料): items with no demand or supply in the current plan(在当前MRP中没有参与运算的料件)
11.Items with repetitive variance: items with suggested aggregate schedules that differ from current aggregate schedules by more than a user–defined repetitive variance percentage, up to the exception date defined by the item’s planning exception set
12.Late order due to resource shortage(由于瓶颈资源导致order推后): items that will cause a late order because a resource required to manufacture the item is overloaded
13.Late supply pegged to forecast(最迟供给反查预测): items with shortages that prevent forecast demand from being met, caused by component shortages (短缺物料导致预测延迟满足)
14.Late supply pegged to sales order(最迟供给反查订单): items with shortages that prevent sales order demand from being met, caused by component shortages(短缺物料导致订单延迟满足)
15.Orders to be cancelled(要取消的订单): items with orders that the planning process recommends be cancelled (MRP建议取消工单,采购单)
16.Orders to be rescheduled in(重新计划提前的单): items with orders that the planning process recommends be rescheduled to an earlier date(MRP建议提前工单,采购单)
17.Orders to be rescheduled out(重新计划延期的单): items with orders that the planning process recommends be rescheduled to a later date(MRP建议推后工单,采购单)
18.Orders with compression days(具有压缩天数的订单): items with planned orders, discrete jobs and purchase orders that have compression days and need to be expedited(对计划订单,工单,采购订单需要压缩时间来加速完成)
19.Past due forecast(过期预测): items with a forecast demand due date earlier than the plan start date(料件预测日期早于计划起始日期)
20.Past due orders(过期订单): items with planned orders, discrete jobs and purchase orders that are past due(指过期的计划订单,工单,采购单)
21.Past due sales orders(过期销售订单): items with a sales order due date earlier than the plan start date(销售订单日期早于计划起始日期)
22.Resource Overloaded(资源超载): a resource is overloaded, as defined by the load ratio entered in the exception set(资源超载是定义在例外集里面)
23.Resource Underloaded(资源欠载): a resource is underloaded resources, as defined in load ratio entered in the exception set(资源欠载是定义在例外集里面)
来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/41594/viewspace-1004837/,如需转载,请注明出处,否则将追究法律责任。
转载于:http://blog.itpub.net/41594/viewspace-1004837/