MRP:所有例外状况类别汇总

Planning Exceptions

通过MRP例外信息,可以使计划调整计划参数设置,计划环境,产能负荷方面信息,同时使MRP运行出来的数据更合理和更准确。

1.Items allocated across projects: items whose supply for one project has been allocated to the demand of a different project

2.Items below safety stock: items for which demand, less supply, brings the projected quantity on hand to a negative level or below safety stock

3.Items that are over–committed: items for which ATP is negative or below safety stock

4.Items with a shortage(短缺物料): items whose quantity on hand is less than the sum of the requirements plus safety stock, within the exception time fence defined by the item’s planning exception set(在手量少于(总需求量+安全库存量)被视为短缺物料,在例外集定义)

5.Items with a shortage in a project(一个项目中无论短缺物料): items whose demand exceeds supply with a project/task for an item(在一个项目中,需求大于供给的短缺物料)

6.Items with excess inventory(超出库存料件): items whose quantity on hand exceeds the total requirements against the item, within the exception time fence defined by the item’s planning exception set(当前库存超出总需求数量,在例外集设定值之上的料件)

7.Items with excess inventory in a project(在一个项目中超出库存料件): items whose supply exceeds demand with a project/task for an item(在一个项目中,一个料件供给超出需求)

8.Items with expired lot(过期料件): lots that expire within the planning horizon(在水平展望期内批量过期)

9.Items with negative starting on hand(在手量开始为负库存料件): items with a negative onhand beginning balance(在手量开始为负库存料件)

10.Items with no activity(不具有活动的物料): items with no demand or supply in the current plan(在当前MRP中没有参与运算的料件)

11.Items with repetitive variance: items with suggested aggregate schedules that differ from current aggregate schedules by more than a user–defined repetitive variance percentage, up to the exception date defined by the item’s planning exception set

12.Late order due to resource shortage(由于瓶颈资源导致order推后): items that will cause a late order because a resource required to manufacture the item is overloaded

13.Late supply pegged to forecast(最迟供给反查预测): items with shortages that prevent forecast demand from being met, caused by component shortages (短缺物料导致预测延迟满足)

14.Late supply pegged to sales order(最迟供给反查订单): items with shortages that prevent sales order demand from being met, caused by component shortages(短缺物料导致订单延迟满足)

15.Orders to be cancelled(要取消的订单): items with orders that the planning process recommends be cancelled MRP建议取消工单,采购单)

16.Orders to be rescheduled in(重新计划提前的单): items with orders that the planning process recommends be rescheduled to an earlier dateMRP建议提前工单,采购单)

17.Orders to be rescheduled out(重新计划延期的单): items with orders that the planning process recommends be rescheduled to a later dateMRP建议推后工单,采购单)

18.Orders with compression days(具有压缩天数的订单): items with planned orders, discrete jobs and purchase orders that have compression days and need to be expedited(对计划订单,工单,采购订单需要压缩时间来加速完成)

19.Past due forecast(过期预测): items with a forecast demand due date earlier than the plan start date(料件预测日期早于计划起始日期)

20.Past due orders(过期订单): items with planned orders, discrete jobs and purchase orders that are past due(指过期的计划订单,工单,采购单)

21.Past due sales orders(过期销售订单): items with a sales order due date earlier than the plan start date(销售订单日期早于计划起始日期)

22.Resource Overloaded(资源超载): a resource is overloaded, as defined by the load ratio entered in the exception set(资源超载是定义在例外集里面)

23.Resource Underloaded(资源欠载): a resource is underloaded resources, as defined in load ratio entered in the exception set(资源欠载是定义在例外集里面)

来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/14573622/viewspace-732663/,如需转载,请注明出处,否则将追究法律责任。

转载于:http://blog.itpub.net/14573622/viewspace-732663/

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值