First create a reference op set ( ca11)
then create a trigger point( Ex fert)( co31)
Go to ops , choose operation(20) go to trigger point in edit menu and choose
trigger point.Include your created trigger point(fert) and tick in box
Now choose that line and goto menu trigger point overview and
tick the function create order with reference
enter the status as pcnf for op 20 ,activate once and + sign
place the cursor on create order with reference line and go to parameters
and enter the reference op set group and group counter no and order type and
save.
once you partially confirm the op 20 a rework order will be created
In c003 enter the number which is next to the actual prodn order no
Rework order will be seen.
If you assign ext number range to rework order the system will ask you the
rework order no with which you can easily indentify the rework order.
The trigger point that has been created should have the parameters as
CNF - + - tick mark - 1.
if the trigger point with the above parameters is set to the operation in the production order, while confirming the order it will ask if a trigger point has to be executed or not.
if 'No' is selected, the order will be confirmed without creating a rework order and if 'Yes' is selected, it will ask ' if a order has to be created with reference' and if 'yes' is selected again, a rework order is created.[@more@]
then create a trigger point( Ex fert)( co31)
Go to ops , choose operation(20) go to trigger point in edit menu and choose
trigger point.Include your created trigger point(fert) and tick in box
Now choose that line and goto menu trigger point overview and
tick the function create order with reference
enter the status as pcnf for op 20 ,activate once and + sign
place the cursor on create order with reference line and go to parameters
and enter the reference op set group and group counter no and order type and
save.
once you partially confirm the op 20 a rework order will be created
In c003 enter the number which is next to the actual prodn order no
Rework order will be seen.
If you assign ext number range to rework order the system will ask you the
rework order no with which you can easily indentify the rework order.
The trigger point that has been created should have the parameters as
CNF - + - tick mark - 1.
if the trigger point with the above parameters is set to the operation in the production order, while confirming the order it will ask if a trigger point has to be executed or not.
if 'No' is selected, the order will be confirmed without creating a rework order and if 'Yes' is selected, it will ask ' if a order has to be created with reference' and if 'yes' is selected again, a rework order is created.[@more@]