Know the Difference between Mitigation plan and Contingency Plan

Mitigation Plan

PMBOK®  Guide Fifth Edition defines risk mitigation “Risk mitigation is a risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.

It is important to understand that the aim of Risk Mitigation is to bring down the risk exposure within the acceptable threshold limits. The risk exposure is the function of the probability of occurrence of the risk and the impact of this risk on the project. Now, you need to understand, since, mitigation strategy is all about taking advance and proactive actions, the probability of occurrence of risk and its impact is identified and calculated at an early stage so as to prevent the foreseen damage to the project. In short, risk Mitigation follows ‘Prevention is better than cure” dictum.

Contingency Plans

Risk responses identified using contingent response strategy is called contingency plans.

PMBOK®  Guide Fifth Edition defines Contingent Response as “Some responses are designed for use only if certain events occur.

Contingency responses are the ones that get executed only when certain unwanted events occur. You do not execute contingency responses unless you see a warning sign that some risk is about to occur. Now, take note we only execute contingency responses when sufficient warning signs are given. It is mandatory to track and define the triggers of the contingency response.

It’s often observed that test takers consider these two risk plans as mutually exclusive, which however is not the case. At times, you may have to plan both the mitigation risk response and the contingency response alongside. In such urgent  situations, you have to make a proactive plan of actions to reduce the probability and impact of the risk and also stay prepared with the contingency plan and monitor triggers or warning signs in case the risk is inevitable.

You do not necessarily make both of these plans for all the identified risks. Instead the contingency plans are made for the risks which are under your threshold and flashes enough warning signs in advance.

Here is an  Examples to illustrate the case for both the risk responses:

Risk:

You are going to address a gathering of professionals, if the car tires get busted than it will result in delay of twenty minutes and you may miss your speaking slot.

The Mitigation Plan could be:

You take one car along, someone follows you, and in case there is any problem in the car you are traveling you change the car.

The Contingency Plan could be:

You keep some buffer time and if something happens to car tires, you change them and since you have timed buffer you still reach on time.

pmp-risk-contingency

Differences

Risk Mitigation Plan Risk Contingency Plan
You identify actions which you will take in advance irrespective of the occurrence of risk You plan actions, but you monitor certain warning signs. You take these actions only when you see the warning signs.
You spend time and money in advance for the given risk condition You do not spend time or money in advance, but you keep them ready, and invest them when needed
We are expected to mitigate the risks which are outside the risk threshold. By applying a mitigation plan, we reduce the probability of impact of the identified risk. By identifying the contingency plan, we do not change the probability or impact of the current risk, but we plan to control the impact as risk event looks like occurring.
This works as the first level of defense for the high exposure risks This works as a fallback plan for the high exposure risks.

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值