第一步:
创建一个表格holiday用于灵活存放节假日日期(周末除外),如果和周末日期重复,则无需添加到该表格中:
Sql代码
create table HOLIDAY (
ID VARCHAR2(45) not null,
HL_DATE DATE,
HL_DESC VARCHAR2(500),
REMARK VARCHAR2(500),
constraint PK_HOLIDAY primary key (ID)
); www.2cto.com
comment on table HOLIDAY is
'节假日日期表(不含周末)';
comment on column HOLIDAY.ID is
'节假日编号';
comment on column HOLIDAY.HL_DATE is
'节假日期';
comment on column HOLIDAY.HL_DESC is
'假日说明';
comment on column HOLIDAY.REMARK is
'备注';
第二步:写个函数用以获取两个日期之间的周末天数,如下:
Sql代码
create or replace function weekend_count(startdate date,enddate date)
return number
/**返回两个时间段内的周末天数,开始日期不计算在内*/
is
weekend_num number:=0;
tempdate date;
begin
tempdate:=startdate+1;
while tempdate<=enddate loop
weekend_num:=weekend_num+(case when to_char(tempdate,'day') in('星期六','星期日') then 1 else 0 end);
tempdate:=tempdate+1;
end loop;
return weekend_num;
end;
select nvl(count(1),0) into holiday_num from holiday a where a.hl_date is not null and a.hl_date > startdate and a.hl_date <= enddate;
第三步:编写函数用以获取指定日期延迟特定工作日以后的具体日期,如下:
Sql代码
create or replace function getDeferDate(startdate date,deferDay number)
return date
/**返回延期后的日期*/
is
enddate date :=startdate+deferDay;--延期后的日期
holiday_num number:=0;--节假日天数
weekend_num number:=0;--周末天数
nonework_num number :=0;--非工作日天数
begin
--获取周末天数
weekend_num:=weekend_count(startdate,enddate);
--获取节假日天数
nonework_num:=weekend_num+holiday_num;
if nonework_num !=0 then
enddate :=getDeferDate(enddate,nonework_num);
end if;
return enddate;
end;
第四步:实际应用,如下:
Sql代码
select getdeferdate(sysdate,5) deferdate from dual;
结果如下:
DEFERDATE
1 2012-9-4 16:12:53