拓扑排序:在不违背先决条件的基础上将有向无环图排成线性序列
- 排序结果不唯一
- 用一维数组Indegree存储各顶点的入度
- 采用邻接表与队列
bool TopSort(LGraph Graph, Vertex TopOrder[])
{
int Indegree[MaxVertexNum], cnt;
Vertex V;
PtrToAdjVNode W;
Queue Q = CreateQueue(Graph->Nv);
//初始化Indegree[]
for (V = 0; V < Graph->Nv; V++)
Indegree[V] = 0;
//遍历邻接表得到Indegree[]
for (V = 0; V < Graph->Nv; V++)
for (W = Graph->G[V].FirstEdge; W; W = W->Next)
Indegree[W->AdjV]++; //累计
//将所有入度为0的顶点入队
for (V = 0; V < Graph->Nv; V++)
if(Indegree[V]==0)
AddQ(Q,V);
//拓扑排序
cnt = 0;
while(!IsEmpty(Q)) {
V = DeleteQ(Q); //弹出一个入度为0的顶点
TopOrder[cnt++] = V; //将之存为结果序列的下一个元素
//对V的每一个邻接点W->AdjV
for (W = Graph->G[V].FirstEdge; W; W = W->Next)
if(--Indegree[W->AdjV] == 0) //若删除V使得W->AdjV入度为0
AddQ(Q, W->AdjV); //则该顶点入列
}
if(cnt != Graph->Nv)
return false; //图中有回路
else
return true;
}
拓扑排序的应用————关键路径问题
- AOE网络(边代表活动,权重代表活动所需时间),AOV网络是一种有向无环图
- 最早开始时间 Earliest[0] = 0; Earliest[j] = max { Earliest[i] + C(i,j) }
- 最晚开始时间 Latest[Last] = Earliest[Last]; Latest[i] = min { Latest[j] - C(i,j) }
- 机动时间 D(i,j) = Latest[j] - Earliest[i] - C(i,j)
- 关键路径:由没有机动时间的活动组成的路径,缩短关键活动能提高整个工程的进度,而提前完成非关键活动不能加快工程的进度。
例题:一个工程项目由下列A~L共12个活动构成,各活动的持续时间和前驱活动如下表所示
(1)画出AOE网
(2)计算顶点最早最迟发生时间
(3)计算活动最早最迟发生时间,关键时间,以及所需总时间