有向无环图的拓扑排序 关键路径

拓扑排序:在不违背先决条件的基础上将有向无环图排成线性序列

- 排序结果不唯一

- 用一维数组Indegree存储各顶点的入度

- 采用邻接表与队列

bool TopSort(LGraph Graph, Vertex TopOrder[])
{
    int Indegree[MaxVertexNum], cnt;
    Vertex V;
    PtrToAdjVNode W;
    Queue Q = CreateQueue(Graph->Nv);
    //初始化Indegree[]
    for (V = 0; V < Graph->Nv; V++)
        Indegree[V] = 0;
    //遍历邻接表得到Indegree[]
    for (V = 0; V < Graph->Nv; V++)
        for (W = Graph->G[V].FirstEdge; W; W = W->Next)
            Indegree[W->AdjV]++; //累计
    //将所有入度为0的顶点入队
    for (V = 0; V < Graph->Nv; V++)
        if(Indegree[V]==0)
            AddQ(Q,V);
    //拓扑排序
    cnt = 0;
    while(!IsEmpty(Q)) {
        V = DeleteQ(Q); //弹出一个入度为0的顶点
        TopOrder[cnt++] = V; //将之存为结果序列的下一个元素
        //对V的每一个邻接点W->AdjV
        for (W = Graph->G[V].FirstEdge; W; W = W->Next)
            if(--Indegree[W->AdjV] == 0) //若删除V使得W->AdjV入度为0
                AddQ(Q, W->AdjV); //则该顶点入列
    }
    if(cnt != Graph->Nv)
        return false; //图中有回路
    else
        return true;
}

拓扑排序的应用————关键路径问题

- AOE网络(边代表活动,权重代表活动所需时间),AOV网络是一种有向无环图

- 最早开始时间        Earliest[0] = 0;        Earliest[j] = max { Earliest[i] + C(i,j) }

- 最晚开始时间        Latest[Last] = Earliest[Last];        Latest[i] = min { Latest[j] - C(i,j) }

- 机动时间        D(i,j) = Latest[j] - Earliest[i] - C(i,j)

- 关键路径:由没有机动时间的活动组成的路径,缩短关键活动能提高整个工程的进度,而提前完成非关键活动不能加快工程的进度。 

例题:一个工程项目由下列A~L共12个活动构成,各活动的持续时间和前驱活动如下表所示

(1)画出AOE网 

(2)计算顶点最早最迟发生时间 

 (3)计算活动最早最迟发生时间,关键时间,以及所需总时间

  • 0
    点赞
  • 9
    收藏
    觉得还不错? 一键收藏
  • 打赏
    打赏
  • 0
    评论

“相关推荐”对你有帮助么?

  • 非常没帮助
  • 没帮助
  • 一般
  • 有帮助
  • 非常有帮助
提交
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包

打赏作者

Kentos(acoustic ver.)

你的鼓励将是我创作的最大动力

¥1 ¥2 ¥4 ¥6 ¥10 ¥20
扫码支付:¥1
获取中
扫码支付

您的余额不足,请更换扫码支付或充值

打赏作者

实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值