Symptom: when user use VA01 to create SO order, she encounter Delivery Date postponing one day(2010-1-7), which the order is create on 2010-1-6. So the Delivery Date should be 2010-1-6. Why it postpone one day?
[@more@]Symptom: when user use VA01 to create SO order, she encounter Delivery Date postponing one day(2010-1-7), which the order is create on 2010-1-6. So the Delivery Date should be 2010-1-6. Why it postpone one day? Below picture for reference.
Root course: In SAP, there is “Standard Calendar” and “Country Calendar”. Standard calendar is based on Germany calendar. The problem is that setting is follow Standard calendar. And 2010-1-6 is epiphany day(a holiday), so system will skip that day and setting req. Deliv. Date on 2010-1-7.
Solution: manual change the Delivery Date to 2010-1-6.