if someone added the component to the BOM with -ve quantity as requirement it gets issued as -ve component issue. You can also manually add to the material requirements (job's material requirement window) and then issue it to display this transaction(for push type). If that was added as an operation pull or assembly pull, then the move transaction/completion transaction automatically take care of this transaction respectively.
WIP Neg Comp Issue: the componenet is negative required for the job. so we need issue negative comp to the job. (equal: componenet return from the job to the subinventory.)
来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/15225049/viewspace-734624/,如需转载,请注明出处,否则将追究法律责任。
转载于:http://blog.itpub.net/15225049/viewspace-734624/