使用Excel Gantt图表进行简单的项目计划

本文介绍了如何使用Excel创建简单的项目计划,包括列出任务、计算任务开始日期和创建甘特图。通过WORKDAY函数处理节假日,调整图表以显示任务的时间线。提供了一个示例Excel Gantt图表文件供下载,并附有视频教程。
摘要由CSDN通过智能技术生成

If you're building a new city, or plotting world domination, you'll need a powerful project management tool, such as Microsoft Project. For smaller projects, you can list your tasks in Excel, and create a Gantt chart, to show the timeline. Here's how you can do simple project planning with Excel Gantt chart - watch the video and there are written steps too.

如果您要建造新城市或在世界上占主导地位,则需要强大的项目管理工具,例如Microsoft Project。 对于较小的项目,您可以在Excel中列出任务,并创建甘特图以显示时间轴。 这是使用Excel Gantt图表进行简单项目计划的方法-观看视频,并有书面步骤。

列出项目任务 (List the Project Tasks)

In this example, we're creating the company budget for next year. The first step is to list all the tasks on an Excel worksheet. The starting date for the first task is entered in column B, and the estimated days for each task is entered in column C.

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论

“相关推荐”对你有帮助么?

  • 非常没帮助
  • 没帮助
  • 一般
  • 有帮助
  • 非常有帮助
提交
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值