EEET 3050 - Renewable Energy Systems Practical 2 – DFIG Feeding Power to a Grid through a Transforme

Java Python EEET 3050 - Renewable Energy Systems

Practical 2 - DFIG Feeding Power to a Grid through a Transformer and a Line

Aim:                    The aim of this practical is to evaluate the characteristics of a DFIG based wind power

plant connected to the grid through a transformer and a distribution line using standard MATLAB/SIMULINK blocks given in Simscape.

Objectives:        Familiarise with modification/extension of MATLAB Simulink models

Develop the model of a realistic wind power plant feeding power to a grid Investigate the system responses to change in wind speed

Background:      Background and theory related to this practical have been covered in Practical - 1. In

this practical,you will be modifying the Simulink model developed in Practical - 1 to represent a more realistic model of a wind generating system.

Description:

Fig.1 illustrates the single line diagram of the wind power plant and the utility grid considered for this practical. Fig. 2 illustrates the corresponding Simulink model block diagram. The procedure for developing the block diagram (or modifying the diagram of practical 1) is given in the following.

Instructions:

1.    Open MATLAB from ‘Start’ menu.

2.    Select ‘Open’ →  Open the Simulink model saved from Practical 01.

3.    Select ‘File’ → Save as → Save the Simulink file with a different name.

4.    Click ‘Simulink Library’ icon  in the toolbar to get the window of the Simulink library.

5.    Search for the following blocks and drag & drop them into your Simulink file.

•    Three-phase PI section line, Three-phase transformer (two winding), Three-phase V-I measurement, scope, Abs, Step, Sum

6.    Delete only the  lines connecting the ‘Three-Phase Source’ and the ‘Three-Phase Series RLC load’ . Insert the new elements and connect all as in Fig.2. Right click on Three-phase V-I measurement block and select ‘flip’ to get required configuration.

7.    Choose the solver: Click on the ‘Variable step auto’ (bottom right corner)  → Settings → Solver → ode 45 (Dormand-Prince).

8.    Double click on the ‘Three-phase Source’ and enter the following parameters:

•    Phase-to-phase rms voltage -11 kV, Frequency - 60Hz, Phase angle - 0, 3-phase short circuit level - 100 MVA, X/R ratio – 7, Base voltage – 11 kV.

9.    Double click on the ‘Three-phase PI section line’ and enter the following parameters:

•    Line length  - 10 km

 

Resistance( Ohm/km)

Inductance (mH/km)

Capacitance (nF/km)

Positive seq.

0.01273

0.9337

12.74

Zero seq.

0.3864

4.1264

7.751

10.  Double click on the ‘ Transformer’ and enter the following parameters:

•    In the ‘Configuration’ tab → winding 1 ‘Yg’ and winding 2 ‘Delta (D1) ‘

•    In the ‘Parameters’ tab  → Nominal  power - 2.0 MVA, frequency - 60 Hz, Winding 1 parameters  -   [11e3,  0.002,  0.08],  Winding  2  parameters  -   [575,  0.002,  0.08], Magnetizing resistance - 500, Magnetizing inductance - 500

11.  Double click on the ‘Three-phase load’ block and enter the following parameters :

•    In the ‘Parameters’ tab → Nominal phase-to-phase voltage - 575 V, configuration - Y (grounded), frequency  -  60  Hz,  active  power  -    100  kW,  Inductive  and  capacitive reactive power - 0

•    In the ‘Load flow’ tab → load type ‘Constant Z’

12.  Double click on the ‘Wind Turbine’ model and enter the following parameters:

•    Select  the  ‘Generator’  option  →  Nominal  power,  line-to-line  voltage,  frequency&nbs EEET 3050 - Renewable Energy Systems Practical 2 – DFIG Feeding Power to a Grid through a Transformer and a LineMatlab p; - [1.5e6/0.9  575  60], Stator  -  [  0.00706  0.171],  rotor  -  [  0.005  0.156],  Magnetizing inductance - 2.9, Inertia constant, friction factor, and pairs of poles - [5.04 0.01 3], Initial conditions - [0.2 0 0 0 0 0]

•    Select the ‘Turbine’ option → Nominal wind turbine mechanical output power - 1.5e6, Tracking characteristic speeds- [0.7 0.71 1.2 1.21], Power at point C - 0.73,Wind speed at point C - 12, Pitch angle controller gain - 500, Maximum pitch angle - 45, Maximum rate of change of pitch angle -2

•    Click  on  the   ‘Display  wind  turbine  characteristics’  and  obtain  the  wind  turbine characteristics.

•    Save the figure.

13.  Remove the ‘Step’ block connected to the ‘Wind’ input of the DFIG model. Connect the ‘Sum’ block and other ‘Step’ blocks as in Fig. 2.

14.  Double click on the ‘Sum’ block and in the ‘ List of signs’ enter  |++++

15.  In order to obtain the step variation of wind speed connect four different step blocks to the summation block as illustrated in Fig. 2 and enter the following parameters:

Block

Step time

Initial value

Final value

Step 1

100

8

10

Step 2

200

0

2

Step 3

300

0

2

Step 4

400

0

2

 

16.  Right click the ‘Bus creator’ → Block parameter → Set no. of inputs to ‘7’ .

17.  Right click on the ‘Bus selector’ → Block parameter → Select P (pu), Q (pu), pitch angle, Tm, wr→ Click ‘OK’ . Connect the signals from the ‘ Bus selector’ to the ‘Bus creator’

18.  Double click on the scope and click the ‘Parameter’ icon  on the toolbar of the scope → Select the ‘Logging’ tab → untick the box for ‘Limit data points to last’ →Click ‘OK’ . Do this change on all the scopes.

19. Set the ‘Simulation Stop Time’ in the tool bar to ‘500‘ as follows:

                               

20.  Run the simulation by clicking on the ‘Run’ icon in the tool bar.

21.  Double click on all the scopes and observe the parameter variations. Click the ‘Auto scale’ icon  on the scope toolbar to view the full simulation.

22. To open the Workspace browser if it is not currently visible, do either of the following:

•    Type workspace at the Command Window prompt.

•    The variables you selected from the DFIG in the previous section (P (pu), Q (pu), pitch angle, Tm, wr) are saved in the ‘simout’ matrix.

23. Type  the following command in the command window and press ‘Enter’:

•    plot(out.simout( :,1),out.simout(:, 2))

The x-axis of the graph denotes the time variable while they-axis represents the second output coming from the wind generator model.

In order to add labels to the x-axis andy-axis and a title, select ‘Insert’ in the graph and select the appropriate labels and title. Then type the label names and the title. Alternatively, double click on ‘arrow’ of figure toolbar and edit the axis by double clicking on any of the axis. Save the  plot  or  use  ‘Copy  Figure’  option  from  Edit  menu  and  paste  the  figure  in  the  word document.

24. Similarly, plot the following outputs from the wind generator in separate figures and save all the figure files. Submit the graphs in a report.

•    Time vs Active  power, Time vs Reactive power, Time vs Wind speed, Time vs Pitch angle, Time vs Rotor speed, Time vs Mechanical Torque

Report:

The report should include a brief introduction, all plots of step 24 with critical analysis and discussion, and a conclusion. The report should be approximately 600 words long, excluding figures, diagrams, and tables         

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值