业务背景:将分解结构分配至成本中心
事务码: OKEW
SPRO路径:SPRO->控制->成本中心会计->实际过账->期末结算->作业分配->将分解结构分配至成本中心
第1步,SPRO路径进入
第2步,点击“更改”按钮,进入下一个界面
第3步,针对于成本中心进行分割结构的分配并保存
配置完成!
2021年12月26日 写于芜湖
2024年配置练习如下:
配置完成!
2024年1月22日 写于上海
2024 SAP CO module configuration practice recording as following:
Configuration Subject: Assign Splitting Structure to Cost Centers
SPRO Path: Controlling->Cost Center Accounting->Actual Postings->Period-End Closing->Activity Allocation->Splitting->Assign Splitting Structure to Cost Centers
There is one pop-up error since there is no cost center which has been created before. Now create cost center foreground throuhg T-Code: KS01 as following:
Take the cost center CN10880001 as an example and continue to do the configuration as following:
CSKS-Cost Center Master Record
Done.
Created on 31st March, 2024
CO模块目录(CO Module Catalogue): 0 CO配置-CO模块-成本控制-配置清单(CO Module SPRO Configuration List)
上一篇(Previous Article): 11 CO配置-控制-成本中心会计-定义分割结构(Define Splitting Structure)
下一篇(Next Article): 13 CO配置-控制-内部订单-定义内部订单类型(Define Order Types)