CONFIGURATION DOCUMENTATION
Topic:BOM,WorkCenter & Routing
| Name | Target Completion Date | Actual Completion Date | StatusO/I/C* |
Config. template prepared by | 14/01/2013 | 14/01/2013 | C | |
Knowledge transfer to |
|
|
|
|
Actual set up by | 14/01/2013 | 14/01/2013 | C | |
Reviewed by |
|
|
|
|
*Status: O – Outstanding, I – In Progress, C – Completed
Transport request no. |
|
Client Dependent/Independent | Client Dependent |
I. Objective
- Set up Production related basic data
II. Configuration Template
Step 1.1: Define BOM Default Values
Step 1.1 | Goto t-code OS28 |
IMG Menu | Production > Basic Data > Bill of Material > Control Data for Bills of Material > Define Default Values |
Prerequisite |
|
Default base quantity: 1
Default BOM status: 1
Step 1.2Define BOM Usage
Step 1.2 | Goto t-code OS20 |
IMG Menu | Production > Basic Data > Bill of Material > General Data > BOM Usage > Define BOM Usage |
Prerequisite |
|
Defined BOM Usage:
1 – Production
R – Rework / Repair
Step 1.3Define Default Values for the Item Status
Step 1.3 | Goto t-code OS21 |
IMG Menu | Production > Basic Data > Bill of Material > General Data > BOM Usage > Define Default Values for the Item Status |
Prerequisite |
|
Defined Usage 1
Step 1.3Define Material Types Allowed in BOM Header
Step 1.3 | Goto t-code OS24 |
IMG Menu | Production > Basic Data > Bill of Material > General Data > Define Material Types Allowed for BOM Header |
Prerequisite | Material Type defined |
Define * for Material Type under BOM usage 1 is allowed as header material
Step 1.4: Define BOM Statuses
Step 1.4 | Goto t-code OS23 |
IMG Menu | Production > Basic Data > General Data > Define BOM Status |
Prerequisite |
|
Check no functionality for BOM Status 1
Check all functionalities for BOM Status 2
Step 1.5: Configure History Requirement for BOMs
Step 1.5 | Goto t-code OS25 |
IMG Menu | Production > Basic Data > General Data > Configure History Requirement for BOMs |
Prerequisite | BOM Status defined |
Check “History requirement” for BOM Usage 1, BOM Status 2
Step 1.6: Define Allowed Material Types for BOM Items
Step 1.6 | Goto t-code OS14 |
IMG Menu | Production > Basic Data > Item Data > Define Allowed Material Types for BOM Items |
Prerequisite | Material types defined |
Indicator “+” as allowed combination between header material type and BOM item material type and the BOM Usage indicator
Step 1.7: Define Order of Priority for BOM Usages
Step 1.7 | Goto t-code OS31 |
IMG Menu | Production > Basic Data > Alternative Determination > Define Order of Priority for BOM Usages |
Prerequisite |
|
Step 1.8: Define Applications
Step 1.8 | Goto t-code OS30 |
IMG Menu | Production > Basic Data > Item Data > Define Applications |
Prerequisite |
|
Check application PP01 with selection ID “01” check box “ExpMRP”, “PlndOr”, “RelCstg”, “RelWKSch”, “RelOrdr.” for production use
Check application PP99 with selection ID “Z1” and do NOT check any box for rework use
Step 1.9: Define Alternative Determination for Production
Step 1.9 | Goto t-code SPRO |
IMG Menu | Production > Basic Data > Bill of Material > Alternative Determination in Related Application Areas > Define Alternative Determination for Production |
Prerequisite | Production Order Type defined |
Define Order type “PPX1” to use application “PP01”
Define Order type “PPX2”, “PPX3” to use application “PP99”
Step 2.0: Define Alternative Determination for MRP
Step 2.0 | Goto t-code SPRO |
IMG Menu | Production > Basic Data > Bill of Material > Alternative Determination in Related Application Areas > Define Alternative Determination for MRP |
Prerequisite |
|
All plant use selection ID: 01
Step 2.1: Define Parameters - Standard Value (for Workcenter)
Step 2.1 | Goto t-code OP7B |
IMG Menu | Production > Basic Data >WorkCenter > General Data > Standard Value > Define parameters |
Prerequisite |
|
Step 2.2: Define standard value key - Standard Value (for Workcenter)
Step 2.2 | Goto t-code OP19 |
IMG Menu | Production > Basic Data >WorkCenter > General Data > Standard Value > Define standard value key |
Prerequisite |
|
Step 2.3: Define person responsible
Step 2.3 | Goto t-code SPRO |
IMG Menu | Production > Basic Data >WorkCenter > General Data > Define person responsible |
Prerequisite | Plant defined |
Step 2.4: Define Control Keys for Operations
Step 2.4 | Goto t-code OP00 |
IMG Menu | Production > Basic Data >WorkCenter > Routing Data > Define control key |
Prerequisite |
|
Step 2.5: Define Capacity Planner
Step 2.5 | Goto t-code SPRO |
IMG Menu | Production > Basic Data >WorkCenter > Capacity Planning > Define capacity planners |
Prerequisite |
|
Step 2.6: Define Material Type Assignments (Routing)
Step 2.6 | Goto t-code OP50 |
IMG Menu | Production > Basic Data > Routing > General Data > Define Material Type Assignments |
Prerequisite | Material Types defined |
Step 2.7: Define Routing Statuses
Step 2.7 | Goto t-code OP46 |
IMG Menu | Production > Basic Data > Routing Data > General Data > Define Routing Statuses |
Prerequisite |
|
Step 2.8: Define Routing Selection Automatically
Step 2.8 | Goto t-code OPEB |
IMG Menu | Production > Basic Data > Routing > Routing Selection > Select Automatically |
Prerequisite |
|