Demeolition
Outlines
the rationale for demolition 拆除的理由;
stakeholders and responsibilities 利益相关与责任;
procurement of demolition works 拆卸工作的采购;
demolition techniques and technology 拆卸技术;
risk management 风险管理;
environmental management 环境管理;
Why demolish
several factors influence the decision to demolition:
- structural condition of the faclity;
- durability issues;
- end of intended life of built facility; typically<=120 yrs;
- energy/carbon effciency,eg. tower blocks;
- urban regeneration;
regeneration has knocked-on dffects-including housing and other amenities;
increasingly,construction projects are designed to fit into the existing built environment
Demolish or refurbish
- Decisions based on performance, besides safety are complex due to
social & economic trade-offs ; - The whole building stock approach supports policy based on age,
condition and tenure & SAP rating(整个建筑存量方法支持政策,根据年龄,状况和任期及SAP评级); - Individual building approach – based on CBA of demolish or refurbish
now or in future by (个体建造方法–基于CBA,现在或将来拆除或翻新); - considering:
capital expenditure(CAPEX)(基本建设费用);
operational expenditure(OPEX)(操作费用);
investment appraisal(投资评估)
Stakeholders in demolition
the CDM sets out the responsibilities
Client:(客户)
- Appoint competent designer(设计师), contractor(承建商) and principal designer;
- Allow sufficient time and resources for planning, mobilization and
execution
Principal designer(首席设计师) - Identify risks and ensure mitigating measures;
- Ensure that designers/contractors do their work;
Designer(设计师) - ensure the designs can be safely built, maintained and demolished;
- where risks cannot be eliminated from designs, give adequate
information to those who may be affected;
principal contractor(承包商)
develop the construction phase plan(施工阶段计划);
ensure operatives(操作人员) are adequately resourced;
excute the works to agreed method statement(计划好的施工方案);
Procurement
Pre-contract planning
初步计划(招标前的准备)
- sufficient information about structure to tenderers(投标人):
*details about existing utilities(现有应用工具) and services;
*previous use/s of structure–likely contaminations(污染物);
*asbestos survey(石棉检测);
*site environment–adjoining properties, ecology; - procurement: specialist contractors(专业承包人)-sufficient technical and practical experience;
Invitation to tebder
(招标)
the invitation usually has 4 main components:
- instruction for tendering(招标说明书)
- Clarifications and submission;
- Guarantees and warrantees;
- Evaluation, award criteria and payment terms;
- description of the works
- the site, vacancy of premises;
- scope of the works;
- programme;
- form/ conditions of contract(合约形式)–NEC or JCT clauses;
- tender response form;
some demolition terminologies(术语)
- Decommissioning: Process of making potentially contaminated structure
safe for dismantling(使可能被污染的结构安全拆除的过程); - Partial demolition: Also selective demolition or taking down – involves removal of non structural, elements and may precede full demolition(选择性拆除);
- Safe demolition: Is one which has procedures and resources to ensure the occupational health and safety(职业健康和安全) of operatives and the general public;
-Environmentally-friendly demolition: One which addresses the impact of all activities – includes techniques, pollution and waste disposal;
The demolition process
the demolish contractor’s task
(承包商的责任)
- inspect the facility and obtain inventory(详细目录) of all materials;
- demolition plan detailing method, safety and pretreatment before disposal-CDM requirement;
- implement the demolition plan utilising resources(利用资源实施拆除计划) which lead to safe and environmentally-friendiy demolition;
- collaborative approach- contractors vs. client with transparent substance account of materials;
Refurbishment & Demolition survey
(翻新和拆卸测量)
structural refurbishment(结构性翻新)
- a detailed survey to identify all hazardous materials(有害物质) in the
facility. can be intrusive; - the commonest contaiminants are asbestos containing materials(含石棉材料)
and lead based paints(铅基油漆); - ACMs may be notifiable to the HSE(health,safety,environment) – licensed contractors to remove &
dispose; - Survey identifies areas suspected of ACMs but limited to accessible
areas; - CAR 2012 requires training & further testing for employees likely to
be exposed to hazard;
Demolition plan
(拆卸计划)
for small projects, a single A-4 sized page containing:
- project information e.g. details of stake-holders site location,
dates etc; - method statement & programme of works;
- risk assessment;
for large projects,the elaborate method statements: - description of operations;
- sequence works;
- hazards and risk assessments;
- waste management plan etc;
Implementing the demolition plan
(实施拆卸工程计划)
case study(案例分析): RC frame multi-storey block(钢筋混凝土框架多层砌块);
- decontamination(清除污物) e.g. remove asbestos - if any;
- disconnect services;
- typically, lift shaft to be used as rubbish chute–remove lift cars
and cables, prepare shaft base; - soft strip(软剥离): take down non structural items-fitting(配件),
cladding(覆层), ceiling(天花板), tiles(瓷砖) etc; - A bottom-to-top approach desirable for fire safety;
- demolition can proceed once decontamination and soft-stripping(软剥离)
completed - may need temporary scaffold(临时支架) and propping(支撑);
- demolition choice is influenced by structure, site location,
materials, time, budge and expertise:- hand demolition
- mechancal demotion from ground or sequential;
- deliberate collapse;
- wrecking balls - drop, swing or slewing jib;
- wire rope pilling;
- demolition explosives;
Demolition tool
hand demolition tools
- useful in structural refurbishment;
- top down approach;
- slow and hazardous;
- wastes via chute or skip;
mechanical demolition rig
extensive demolition(大量拆卸);
crawler mounted base machine(履带式座底机);
top down approach;
building height to be reduced if above the arm;
**mechanical demolition rig(mini) for sequential
swquential demolition will be in the reverse order of construction(拆除顺序和施工顺序相反);
remove controlled mini rigs offer a safe option;
-
environmentally friendly-dust, noise;
-
lower risk to operatives;
-
slower than ground controlled;
-
external power required;
controlled demolition using bursters(爆破)
bursters apply pressure mechanically or chemically in confined spaces to induce cracks(裂纹) and hence damage;
-
where noise, vibration and dust are to be eliminated alogetther;
-
bursters inserted into pre- drilled openings;
-
pressure applied to exceed trnsile strength of concrete-cracks form;
Safe working space & Exclusion zones
-
for the safety of operatives and public, demolition must be provided
with exclusion zones; -
safe working space: working locations within the excl zone; safe for operatives but with protection;
-
Excl.zone is the designed area around the works unsafe for non
enssential activities & comprises of:- plan area–of structure or parts being demolished;
- drop area–principal mass of structure will drop;
- predicted debris(碎片) area–extent which debris may travel and com to rest;
- buffer(缓冲) zone–area to allow for unpredicted harzard;
-
where operatives need to be in this zine, they must be in
safe working
space but no nearer to the works than the*buffer zone
; -
the exclusion zone is to be reviewed in the course of the works particularly restricted sites;
-
the exclusion zone is to be reviewed in the course of the works particularly restricted sites;
-
site machinery(现场机械) also require exclusion zones;
Pollution during demolition
- pollution arising from demolition include noise, dust, waste;
- it is important to establish threshold levels(阈值水平) and monitor(监测)
them during the works; - dust control by spraying water at the source;
Delimotion waste management
waste from construction and delimotion~30% of waste in the EU(欧盟);
in UK, BRE reports:
- concrete~59%;
- inter material~21%;
- metals~10%;
- timber~7%;
- miscellaneous~3%;
The opportunities for technology
- efficient use of space–adaptable space;
- demolition techniques–robotics, equipment;
- environment impact of demolition–emphasis on pollution control;