Demeolition

Outlines

the rationale for demolition 拆除的理由;
stakeholders and responsibilities 利益相关与责任;
procurement of demolition works 拆卸工作的采购;
demolition techniques and technology 拆卸技术;
risk management 风险管理;
environmental management 环境管理;

Why demolish

several factors influence the decision to demolition:

  • structural condition of the faclity;
  • durability issues;
  • end of intended life of built facility; typically<=120 yrs;
  • energy/carbon effciency,eg. tower blocks;
  • urban regeneration;
    regeneration has knocked-on dffects-including housing and other amenities;
    increasingly,construction projects are designed to fit into the existing built environment

Demolish or refurbish

  • Decisions based on performance, besides safety are complex due to
    social & economic trade-offs ;
  • The whole building stock approach supports policy based on age,
    condition and tenure & SAP rating(整个建筑存量方法支持政策,根据年龄,状况和任期及SAP评级);
  • Individual building approach – based on CBA of demolish or refurbish
    now or in future by (个体建造方法–基于CBA,现在或将来拆除或翻新);
  • considering:
    capital expenditure(CAPEX)(基本建设费用);
    operational expenditure(OPEX)(操作费用);
    investment appraisal(投资评估)

Stakeholders in demolition

the CDM sets out the responsibilities

Client:(客户)

  • Appoint competent designer(设计师), contractor(承建商) and principal designer;
  • Allow sufficient time and resources for planning, mobilization and
    execution
    Principal designer(首席设计师)
  • Identify risks and ensure mitigating measures;
  • Ensure that designers/contractors do their work;
    Designer(设计师)
  • ensure the designs can be safely built, maintained and demolished;
  • where risks cannot be eliminated from designs, give adequate
    information to those who may be affected;
    principal contractor(承包商)
    develop the construction phase plan(施工阶段计划);
    ensure operatives(操作人员) are adequately resourced;
    excute the works to agreed method statement(计划好的施工方案);

Procurement

Pre-contract planning

初步计划(招标前的准备)

  • sufficient information about structure to tenderers(投标人):
    *details about existing utilities(现有应用工具) and services;
    *previous use/s of structure–likely contaminations(污染物);
    *asbestos survey(石棉检测);
    *site environment–adjoining properties, ecology;
  • procurement: specialist contractors(专业承包人)-sufficient technical and practical experience;

Invitation to tebder

(招标)
the invitation usually has 4 main components:

  • instruction for tendering(招标说明书)
    • Clarifications and submission;
    • Guarantees and warrantees;
    • Evaluation, award criteria and payment terms;
  • description of the works
    • the site, vacancy of premises;
    • scope of the works;
    • programme;
  • form/ conditions of contract(合约形式)–NEC or JCT clauses;
  • tender response form;

some demolition terminologies(术语)

  • Decommissioning: Process of making potentially contaminated structure
    safe for dismantling(使可能被污染的结构安全拆除的过程);
  • Partial demolition: Also selective demolition or taking down – involves removal of non structural, elements and may precede full demolition(选择性拆除);
  • Safe demolition: Is one which has procedures and resources to ensure the occupational health and safety(职业健康和安全) of operatives and the general public;
    -Environmentally-friendly demolition: One which addresses the impact of all activities – includes techniques, pollution and waste disposal;

The demolition process

the demolish contractor’s task

(承包商的责任)

  • inspect the facility and obtain inventory(详细目录) of all materials;
  • demolition plan detailing method, safety and pretreatment before disposal-CDM requirement;
  • implement the demolition plan utilising resources(利用资源实施拆除计划) which lead to safe and environmentally-friendiy demolition;
  • collaborative approach- contractors vs. client with transparent substance account of materials;

Refurbishment & Demolition survey

翻新和拆卸测量
structural refurbishment(结构性翻新)
在这里插入图片描述

  • a detailed survey to identify all hazardous materials(有害物质) in the
    facility. can be intrusive;
  • the commonest contaiminants are asbestos containing materials(含石棉材料)
    and lead based paints(铅基油漆);
  • ACMs may be notifiable to the HSE(health,safety,environment) – licensed contractors to remove &
    dispose;
  • Survey identifies areas suspected of ACMs but limited to accessible
    areas;
  • CAR 2012 requires training & further testing for employees likely to
    be exposed to hazard;

Demolition plan

(拆卸计划)
for small projects, a single A-4 sized page containing:

  • project information e.g. details of stake-holders site location,
    dates etc;
  • method statement & programme of works;
  • risk assessment;
    for large projects,the elaborate method statements:
  • description of operations;
  • sequence works;
  • hazards and risk assessments;
  • waste management plan etc;

Implementing the demolition plan

(实施拆卸工程计划)
case study(案例分析): RC frame multi-storey block(钢筋混凝土框架多层砌块);

  1. decontamination(清除污物) e.g. remove asbestos - if any;
  2. disconnect services;
  3. typically, lift shaft to be used as rubbish chute–remove lift cars
    and cables, prepare shaft base;
  4. soft strip(软剥离): take down non structural items-fitting(配件),
    cladding(覆层), ceiling(天花板), tiles(瓷砖) etc;
  5. A bottom-to-top approach desirable for fire safety;
  6. demolition can proceed once decontamination and soft-stripping(软剥离)
    completed
  7. may need temporary scaffold(临时支架) and propping(支撑);
  8. demolition choice is influenced by structure, site location,
    materials, time, budge and expertise:
    • hand demolition
    • mechancal demotion from ground or sequential;
    • deliberate collapse;
    • wrecking balls - drop, swing or slewing jib;
    • wire rope pilling;
    • demolition explosives;

Demolition tool

hand demolition tools
在这里插入图片描述

  • useful in structural refurbishment;
  • top down approach;
  • slow and hazardous;
  • wastes via chute or skip;

mechanical demolition rig
在这里插入图片描述
extensive demolition(大量拆卸);
crawler mounted base machine(履带式座底机);
top down approach;
building height to be reduced if above the arm;

**mechanical demolition rig(mini) for sequential
在这里插入图片描述
swquential demolition will be in the reverse order of construction(拆除顺序和施工顺序相反);
remove controlled mini rigs offer a safe option;

  • environmentally friendly-dust, noise;

  • lower risk to operatives;

  • slower than ground controlled;

  • external power required;
    controlled demolition using bursters(爆破)
    bursters apply pressure mechanically or chemically in confined spaces to induce cracks(裂纹) and hence damage;
    在这里插入图片描述

  • where noise, vibration and dust are to be eliminated alogetther;

  • bursters inserted into pre- drilled openings;

  • pressure applied to exceed trnsile strength of concrete-cracks form;

Safe working space & Exclusion zones

  • for the safety of operatives and public, demolition must be provided
    with exclusion zones;

  • safe working space: working locations within the excl zone; safe for operatives but with protection;

  • Excl.zone is the designed area around the works unsafe for non
    enssential activities & comprises of:

    • plan area–of structure or parts being demolished;
    • drop area–principal mass of structure will drop;
    • predicted debris(碎片) area–extent which debris may travel and com to rest;
    • buffer(缓冲) zone–area to allow for unpredicted harzard;
      在这里插入图片描述
  • where operatives need to be in this zine, they must be in safe working space but no nearer to the works than the* buffer zone;

  • the exclusion zone is to be reviewed in the course of the works particularly restricted sites;

  • the exclusion zone is to be reviewed in the course of the works particularly restricted sites;

  • site machinery(现场机械) also require exclusion zones;

Pollution during demolition

  • pollution arising from demolition include noise, dust, waste;
  • it is important to establish threshold levels(阈值水平) and monitor(监测)
    them during the works;
  • dust control by spraying water at the source;

Delimotion waste management

waste from construction and delimotion~30% of waste in the EU(欧盟);
in UK, BRE reports:

  • concrete~59%;
  • inter material~21%;
  • metals~10%;
  • timber~7%;
  • miscellaneous~3%;

The opportunities for technology

  • efficient use of space–adaptable space;
  • demolition techniques–robotics, equipment;
  • environment impact of demolition–emphasis on pollution control;
以下是对提供的参考资料的总结,按照要求结构化多个要点分条输出: 4G/5G无线网络优化与网规案例分析: NSA站点下终端掉4G问题:部分用户反馈NSA终端频繁掉4G,主要因终端主动发起SCGfail导致。分析显示,在信号较好的环境下,终端可能因节能、过热保护等原因主动释放连接。解决方案建议终端侧进行分析处理,尝试关闭节电开关等。 RSSI算法识别天馈遮挡:通过计算RSSI平均值及差值识别天馈遮挡,差值大于3dB则认定有遮挡。不同设备分组规则不同,如64T和32T。此方法可有效帮助现场人员识别因环境变化引起的网络问题。 5G 160M组网小区CA不生效:某5G站点开启100M+60M CA功能后,测试发现UE无法正常使用CA功能。问题原因在于CA频点集标识配置错误,修正后测试正常。 5G网络优化与策略: CCE映射方式优化:针对诺基亚站点覆盖农村区域,通过优化CCE资源映射方式(交织、非交织),提升RRC连接建立成功率和无线接通率。非交织方式相比交织方式有显著提升。 5G AAU两扇区组网:与三扇区组网相比,AAU两扇区组网在RSRP、SINR、下载速率和上传速率上表现不同,需根据具体场景选择适合的组网方式。 5G语音解决方案:包括沿用4G语音解决方案、EPS Fallback方案和VoNR方案。不同方案适用于不同的5G组网策略,如NSA和SA,并影响语音连续性和网络覆盖。 4G网络优化与资源利用: 4G室分设备利旧:面对4G网络投资压减与资源需求矛盾,提出利旧多维度调优策略,包括资源整合、统筹调配既有资源,以满足新增需求和提质增效。 宏站RRU设备1托N射灯:针对5G深度覆盖需求,研究使用宏站AAU结合1托N射灯方案,快速便捷地开通5G站点,提升深度覆盖能力。 基站与流程管理: 爱立信LTE基站邻区添加流程:未提供具体内容,但通常涉及邻区规划、参数配置、测试验证等步骤,以确保基站间顺畅切换和覆盖连续性。 网络规划与策略: 新高铁跨海大桥覆盖方案试点:虽未提供详细内容,但可推测涉及高铁跨海大桥区域的4G/5G网络覆盖规划,需考虑信号穿透、移动性管理、网络容量等因素。 总结: 提供的参考资料涵盖了4G/5G无线网络优化、网规案例分析、网络优化策略、资源利用、基站管理等多个方面。 通过具体案例分析,展示了无线网络优化中的常见问题及解决方案,如NSA终端掉4G、RSSI识别天馈遮挡、CA不生效等。 强调了5G网络优化与策略的重要性,包括CCE映射方式优化、5G语音解决方案、AAU扇区组网选择等。 提出了4G网络优化与资源利用的策略,如室分设备利旧、宏站RRU设备1托N射灯等。 基站与流程管理方面,提到了爱立信LTE基站邻区添加流程,但未给出具体细节。 新高铁跨海大桥覆盖方案试点展示了特殊场景下的网络规划需求。
以下是对提供的参考资料的总结,按照要求结构化多个要点分条输出: 4G/5G无线网络优化与网规案例分析: NSA站点下终端掉4G问题:部分用户反馈NSA终端频繁掉4G,主要因终端主动发起SCGfail导致。分析显示,在信号较好的环境下,终端可能因节能、过热保护等原因主动释放连接。解决方案建议终端侧进行分析处理,尝试关闭节电开关等。 RSSI算法识别天馈遮挡:通过计算RSSI平均值及差值识别天馈遮挡,差值大于3dB则认定有遮挡。不同设备分组规则不同,如64T和32T。此方法可有效帮助现场人员识别因环境变化引起的网络问题。 5G 160M组网小区CA不生效:某5G站点开启100M+60M CA功能后,测试发现UE无法正常使用CA功能。问题原因在于CA频点集标识配置错误,修正后测试正常。 5G网络优化与策略: CCE映射方式优化:针对诺基亚站点覆盖农村区域,通过优化CCE资源映射方式(交织、非交织),提升RRC连接建立成功率和无线接通率。非交织方式相比交织方式有显著提升。 5G AAU两扇区组网:与三扇区组网相比,AAU两扇区组网在RSRP、SINR、下载速率和上传速率上表现不同,需根据具体场景选择适合的组网方式。 5G语音解决方案:包括沿用4G语音解决方案、EPS Fallback方案和VoNR方案。不同方案适用于不同的5G组网策略,如NSA和SA,并影响语音连续性和网络覆盖。 4G网络优化与资源利用: 4G室分设备利旧:面对4G网络投资压减与资源需求矛盾,提出利旧多维度调优策略,包括资源整合、统筹调配既有资源,以满足新增需求和提质增效。 宏站RRU设备1托N射灯:针对5G深度覆盖需求,研究使用宏站AAU结合1托N射灯方案,快速便捷地开通5G站点,提升深度覆盖能力。 基站与流程管理: 爱立信LTE基站邻区添加流程:未提供具体内容,但通常涉及邻区规划、参数配置、测试验证等步骤,以确保基站间顺畅切换和覆盖连续性。 网络规划与策略: 新高铁跨海大桥覆盖方案试点:虽未提供详细内容,但可推测涉及高铁跨海大桥区域的4G/5G网络覆盖规划,需考虑信号穿透、移动性管理、网络容量等因素。 总结: 提供的参考资料涵盖了4G/5G无线网络优化、网规案例分析、网络优化策略、资源利用、基站管理等多个方面。 通过具体案例分析,展示了无线网络优化中的常见问题及解决方案,如NSA终端掉4G、RSSI识别天馈遮挡、CA不生效等。 强调了5G网络优化与策略的重要性,包括CCE映射方式优化、5G语音解决方案、AAU扇区组网选择等。 提出了4G网络优化与资源利用的策略,如室分设备利旧、宏站RRU设备1托N射灯等。 基站与流程管理方面,提到了爱立信LTE基站邻区添加流程,但未给出具体细节。 新高铁跨海大桥覆盖方案试点展示了特殊场景下的网络规划需求。
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值