使用基于消耗的计划的前提
为了能全面使用基于消耗的计划,我们需要作一些最基本的配置:
如果物料需求计划在工厂层发生,系统将各个仓储地点的所有可用库存叠加在一起,来确定短缺量。如图中对plant进行计划时,工厂的可用库存应该是Storage loc. 1和Storage loc. 2中可用库存的总和。
为了对一个工厂执行需求计划,必须满足以下先决条件:
- Requirements planning for the corresponding plant must be activated in Customizing for Materials Management under Consumption-Based Planning → Planning → Activate Material Requirements Planning.
必须激活相应的工厂的需求计划。Tcode: OMDU
- The plant parameters for the corresponding plant must be activated in Customizing for Materials Management under Consumption-Based Planning → Plant Parameters → Carry Out Overall Maintenance of Plant Parameters.
必须激活相应工厂的工厂参数。Tcode: OMI8
- In the material master record, you have to maintain the MRP data of the materials that are subject to automatic planning.
在物料主记录中,你必须维护自动计划物料的MRP数据。Tcode: MM01