Production Planner Workbench
The Production Planner Workbench displays information about
material shortages物料短缺of selected jobs
in a dashboard format. This dashboard is valuable for viewing information about
multiple jobs at once. You cannot add or edit records in this tracker.
Although this information is already available in each job,
this overview provides the job planner with a tool to quickly gather information for multiple jobs at once.
In the Production Planner Workbench, select one or more jobs, parts, or product groups for material shortage review. For each job material from each selected job, the Epicor application compares the required quantity with the available quantity. If the available quantity is less than the required quantity, the application expects and displays a shortage of material. This information is useful for determining which jobs to reschedule and allows you to request materials to resolve the shortage. Note that the Consumed quantity field that displays the consumed quantity per component is the sum of the required quantities of all other job materials with the same part number.
![Production Planner Workbench - spectragem - 丝碧@翠音.spectragem](http://img2.ph.126.net/mXKJojJHzIquwcBqr3KWiA==/6597733871681094347.jpg)
Note: For more information on trackers, review the Tracker Overview topic in the Application Help. The overview topic explains the tracker interface, as well as how to best search for specific records. The topic also contains definitions of concepts and terms.
Note: For more information on dashboards and dashboard capabilities, review the Dashboard overview topic in the Application Help. This topic contains links to other dashboard topics that explain how to personalize and customize dashboards.
Menu Path
Navigate to this program from the Main Menu:
Production Management > Job Management > General Operations > Production Planner Workbench
Features
Review this list for information on key features in this program.
Parts
Use the sheets under the Parts tab to view part shortage quantities for jobs that meet the selection criteria specified in the Advanced Selection Criteria box in the Jobs sheet, or to view all parts associated with jobs that meet the specified search criteria.
Jobs
Use the sheets under the Jobs tab to view, for the specified search criteria, jobs with part shortage quantities, jobs with full availability (no part shortage quantities) or all jobs associated with the specified search criteria. The Advanced Selection Criteria box can be used to enter the plant, job, part, description and planner criteria for which production planning information is being selected and displayed.
Shortages For Job 工单所缺物料表
Use Shortage For Job sheet to view material shortage quantities for the jobs associated with the items selected in the sheets located under the Parts or Jobs tab.
Available For Job 工单可用物料表
Use the Available For Job sheet to view only parts with available quantities for the jobs associated with the items selected in the sheets located under the Parts or Jobs tab.
All Requirements For Job 工单所有需求
Use the All Requirements For Job sheet to view all material requirements for the jobs associated with the items selected in the sheets located under the Parts or Jobs tab.
Shortages For Part 短缺物资
Use Shortage For Part sheet to view material shortage quantities for the parts associated with the items selected in the sheets located under the Parts or Jobs tab.
All Requirements For Part 所有物料需求
Use the All Requirements For Part sheet to view all material requirements for the parts associated with the items selected in the sheets located under the Parts or Jobs tab.
Using the Production Planner Workbench
Tracker Searches
Tracker Navigation
Parent topic: Job Management Operation Programs