【Planning】PL order convertion to Production order

Purpose

对于SFC PP, 一般有Planned order与Production order。当planning run出PL后,如果accept那么需要convert成Production order,这一个conversion主要有:MD04、CO40 single、CO41 collective、COHV Mass、CO46 order progress report、CO48 Partial convert、及PPBICO40;


Content


MD04

Machine generated alternative text:
Stock/Requirements List as of 07:42 his
Show Overview Tree L Q 3 e 
Material
Plant
EDI FC 2
Fool
MRP type
edison test FG 2 - PP
k Material Type
?FERT Unit
1 11
MRP el... MRP element data Reschedulin... E.. Receipt/Reqmt Available Qty
1
100
100?
[
A.. Date
01. 2017 Stock
13. 01. 2017 PrdOrd
000001000020/FFO1
l6. 01. 2017 IndReq
VSF
17. 01. 2017 IndReq
VSF
l8.0l.20l7 >
End of Planning Tim...
l8. 01. 2017 PIdOrd
0000005160/STCK
64
99
01. 2017 PIdOrd
0000005161/STCK
il
100
18. 01. 2017 PIdOrd
0000005162/STCK
100
18. 01. 2017 IndReq
VSF
100?
ijl9. 01. 2017 PidOrd
0000005163/STCK
100
19. 01. 2017 IndReq
20. 01. 2017 PIdOrd
20. 01. 2017 IndReq
VSF
鑙000005164/STCK
VSF
100?
100
100?
23. 01. 2017 PidOrd
0000005165/STCK
100
ij23. 01. 2017 IndReq
VSF
100?
24. 01. 2017 PIdOrd
0000005166/STCK
100
24. 01. 2017 IndReq
VSF
100?
Pro...
o
1 0001
99?
199?
100? 0001
0 0001
100 0001
o
100 0001
o
100 0001
o
100 0001
o
100 0001
o


Partial convert,直接在MD04上伏

Machine generated alternative text:
100?001
0 0001
100 0001
00000051 60/STCK
0000005161 /ST?C
00000051 62/STCi
64
l8.
[l8.
l8.
l8.
l9.
l9.
20.
[2o.
23.
23.
I24.
64
01. 2017 PIdOrd
01. 2017 PIdOrd
01. 2017 PIdOrd
01. 20
01. 20:
01. 20:
01. 20:
01. 20:
01. 20:
01. 20:
01. 20:
01. 2ui r iriurieq wr
99
100
100
Ec? Additional Data for MRP Elemei 靦 X
PInd order rr? ke-to-stock Order finish 18. 01. 2017 GR ProcTme
09 01 2017 Proc. type
Scrap O Planned opening
Order qty Order start 01 2?17 Order type LA
Exception 64 Production fi h after order finish
1 vv?
L_j ?

  • 这一个无法做convert, 因为capacity已做DSPT 


Machine generated alternative text:
JJ.O. vi. ?vi I ritic靑u
jis. 01. 2017 PIdOrd
ji8. 01. 2017 PIdOrd
PInd order
Order qty
Scrap
Exception
VVVVVV._I.L LIV! OLLsfl
0000005. 61 /STCK
000000542/STCK
Order finish
Order start
Planned opening
18. 01. 2017 GR ProcTme
09. 01. 2017 Proc. type
09. 01. 2017 Order type
lO
E
LA
ai
:,;,
E4
100
j ?
Cc? Additional Data for MRP Element
100
100 P
o
64 = Production finish after o r finish
j
j
El [-> Prod.Ord. ][ -> PartconvProdOrder [ -> Proc,Ord. j[ -> SubProcOrd ][Pur.Req. ][慮X
j
:1
:1

2个日期的partial:

Machine generated alternative text:
Query Subset/Order Correction
S Generate
General Data
Planned order ?161 慏elete Planned Ord.
Material EDI_FC_2 edison test FG 2 - PP
Sales Order Project
Quantities Scheduling
Total 100, 000 BscStart 09. 01. 2017
Open 70,000 BscFin. 18. 01. 2017?
Type 2 Backwards w?
Subsets
Target quantity ... sic artDate Basic Star... a asic Fin.... Order G... Pro... Scheduling
r PC 00:00:00 18.01.2017 00: 0 0001 2 Backwz
2OPC 00:00:00 19. 01. 2017 00:00 0 2 Backw
_____

Generate -> save

Machine generated alternative text:
J 2 orders are created


MD04:

Machine generated alternative text:
Stock/Requirements List as of 07:49 his
Show Overview Tree  Si 3 1 
[J Material EDI FC 2 edison test frS 2 - PP
Plant F001 MRP type Jill Material Type FEET Unit 慒C
A.. Date MRP el... MRP element data Reschedulin... E.. Receipt/Reqmt Available Qty Pro...
j08. 01. 2017 Stock U
Ji3. 01. 2017 PrdOrd 000001000020/FF01 1 1 0001
01. 2017 IndReq VSF loo? 99?
Jl7. 01. 2017 IndReq VSF 100? 199?
18. 01.2
jl8.Ol.rdOOOOOOlOOOOFFOr 10 189?001
99 90? 0001
01. 2017 PIdOr ____
ijl8. 01. 2017 PIdOrd 0000005161/SC 70 20? 0001
J18. 01. 2017 PIdOrd 0000005162/STCK 100 80 0001
jis. 01. 2017 IndReq
100? 20?
20 0 0001
19.01.2017PrdC??0001000022/FFr16.01.T7T, 100 100 0001
iji9. 01. 2017 PIdOrd ____
[]i. 01. 2017 IndReq VSF 100? 0
ij20. 01. 2017 PIdOrd 0000005164/STCK 100 100 0001
ij20. 01. 2017 IndReq VSF 100? 0
ij23. 01. 2017 PIdOrd 00000051 65/STCK 100 100 0001
j23. 01. 2017 IndReq VSF 100? 0
JLJ


 


Collective convert:

Machine generated alternative text:
Collective Con version of Planned Orders: Initial Screen
Planning plant o鮮 Wh guanggu
MRP Area
MRP Controller
Production Plant
Prodn Supervisor
Material
Sales Order
WBS element
BOM explosion number
Opening Date 10. 01. 2017梚9L 01. 2017i1
Select According to Status Select According to Availability
Firmed Planned Orders ! Fully Confirmed Not Confirmed
Plan, Orders with Plan. Capacity D Partly Confirmed Not Checked
Order Type FF01 Standard production order


Machine generated alternative text:
Collective Conversion of Planned Orders: List
? Planned Orders
Planned Ords
Opening Capacity ...
10. 01. 2017 fl
18. 01. 2017 EJ
9. 01. 2017 lEI
Start End ! Material
10. 01. 2017 18. 01. 2017 EDI_FC_2
18. 01. 2017 18. 01. 2017 EDI_FG_2
19. 01. 2017 19. 01. 2017 EDI_FC_2
De.ion
edison test FG 2 - PP
edison test FG 2 - PP
edison test FG 2 - pp
Order Quantity
70
100
100
. ________
. ________
.
.
Convert  [ Fields St./Reqmts [$
MRP


Machine generated alternative text:
Collective Con version of Planned Orders: List
? Planned Orders
Planned Ords
R.. Opening Capacity ...
918.01.2017 b
j19. 01. 2017 
Start End Material
10. 01. 2017 18. 01. 2017 EDI_FG_2
18. 01. 2017 18. 01. 2017 EDI_FC_2
19. 01. 2017 19. 01. 2017 EDI_FG_2
Order Quantity
70
100
100
B... Type Planned order
PC FF01 5161
PC FF01 5162
PC FF01 5163
Order
1000023
1000024
1000025
Convert J   Fields  1I  St./Reqmts fiS
ed orders have been convert? 7
MRP
De.ion
edison test FG 2 - PP
edison test FG 2 - PP
edison test FG 2 - PP
u
a
ECC (5) 001 SAPECC? INS

 


然后CO46查看Order progress

Machine generated alternative text:
Order Progress Report: Selection Screen
? ? Profile
4 Sales Order Project WBS Element Production/Process Order Network Planned Order
Sales Order Number to
Sales Order Item to
Material edi_fg_21
Plant 慞OOl
Profile Selection
Overall Profile 000000000001
Display Format
1 List-Based Progress Report


  • 主要用来看SO对应的order history


这里我们看ProOrd:

Machine generated alternative text:
Order Progress Report: Selection Screen
? 6? Profile
Sales Order Project WBS Element Production/Process Order Network Planned Order
r_________
Production/Process Order i! 000025
L
Profile Selection
Overall Profile 000000000001
Display Format
Rl List-Based Progress Report


Machine generated alternative text:
Sto ck/Requfrements List as of 07:57 his
Hide Overview Tree L 
w  
ProdOrder De.ion Require.., Requi... Reqmt El Rec./reqd qty B Receipt ... Rec... Recei 
w 000001000025
O EDI_FG_2 edison test FG 2 - pp PrdOrd 1000025 1 100,000 Pc 20.01.2017 PrdOrd 1000025 1
O EDI_RW_1 edison test rw 2 09.01.2017 OrdRes 20 1 200,000- c Stock
O EDI_RW_2 edison test rw 2 09.01.2017 OrdRes 20 2 400,000- c Stock
Material
Plant
r
L
Pool
DI FC 2
[ A.. Date MRP el... MRP element data
01. 2017 Stock
II13. 01. 2017 PrdOrd 000001000020/PPO1
盠L
憀 edison test FG 2 - PP
MRP type Jill Material Type FERT Unit
Reschedulin... E.. Receipt/Reqmt Available Qty Pro...
o
1 1 0001


来自 “ ITPUB博客 ” ,链接:http://blog.itpub.net/17144169/viewspace-2134249/,如需转载,请注明出处,否则将追究法律责任。

转载于:http://blog.itpub.net/17144169/viewspace-2134249/

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值