PZ_Jun11/05 (cXXXX)_v163_Implement New Guided Navigators

                         PZ_Jun11/05 (cXXXX)_v163_Implement New Guided Navigators

Project Start:
Project Finish:
2011/7/18
2011/11/23

Project Schedule


标识号 
Task_Name
BaseStartBaseEndBaseDurActualStartActualEndDurVarDoneStatus前置任务资源名称
1 
PZ_Jun11/05 (cXXXX)_v163_Implement New Guided Navigators
NANA0 days2011/7/18NA87 days24%   
2 
Project Initiation & Preparation
2011/7/182011/7/192 days2011/7/182011/7/190 days100%   
3 
Project Announcement
2011/7/182011/7/181 day2011/7/182011/7/180 days100%  TLMS
4 
Kick-off meeting
2011/7/192011/7/191 day2011/7/192011/7/190 days100%  Claud
5            
6 
FTBRD Preparation
2011/7/212011/8/1720 days2011/7/212011/8/16-2 days100%   
7 
First draft requirements
2011/7/212011/7/264 days2011/7/212011/7/22-2 days100% 2Lana,Si
8 
Business Requirements Iteration
2011/7/272011/7/293 days2011/7/252011/7/25-2 days100% 7Lana,Si,He
9 
Technical Solution First Draft
2011/8/12011/8/33 days2011/7/262011/8/34 days100% 8He
10 
Business Objective Preparation
2011/8/12011/8/55 days2011/7/282011/8/52 days100%  Lana,Si
11 
Prepare Business Objectives/Justification
2011/8/12011/8/11 day2011/7/282011/8/12 days100% 8 
12 
Review Business Objectives/Justification
2011/8/22011/8/32 days2011/8/12011/8/1-2 days100% 11 
13 
Finalize Business Objectives/Justification
2011/8/42011/8/52 days2011/8/12011/8/1-2 days100% 12 
14 
Complete ROI
2011/8/52011/8/51 day2011/8/12011/8/1-1 day100% 13 
15 
Send draft BRD to BS
2011/8/52011/8/51 day2011/8/52011/8/50 days100% 14Lana
16 
Finalize the requirements & technical solutions
2011/8/42011/8/94 days2011/8/42011/8/101 day100% 9 
17 
Cutoff date for requirement changes
2011/8/52011/8/51 day2011/8/52011/8/50 days100% 18 
18 
Finalize Requirements
2011/8/42011/8/94 days2011/8/42011/8/101 day100%  Lana,Si
19 
Finalize Technical Solutions and effort estimate
2011/8/42011/8/94 days2011/8/42011/8/90 days100%  He,Lee
20 
UI Mockup Discussion & Effort Estimation
2011/8/12011/8/55 days2011/8/12011/8/50 days100%   
21 
Prepare draft mockup list
2011/8/12011/8/11 day2011/8/12011/8/10 days100% 8Lana,Si,He
22 
Revise & Finalize mockup list
2011/8/22011/8/32 days2011/8/12011/8/41 day100% 21Lana,Si,He
23 
Confirm UI effort estimation
2011/8/42011/8/52 days2011/8/42011/8/50 days100% 22UI Manager
24 
Finalize project costing
2011/8/102011/8/112 days2011/8/42011/8/114 days100% 16Claud,He
25 
Final Review of BRD
2011/8/122011/8/121 day2011/8/112011/8/162 days100% 24 
26 
Final review by PDM & TM
2011/8/122011/8/121 day2011/8/112011/8/11-1 day100%  Si,He
27 
Final review by Stakeholders
2011/8/122011/8/121 day2011/8/112011/8/162 days100%  Stakeholder
28 
Sign-off by BS & TS
2011/8/152011/8/162 days2011/8/152011/8/16-2 days100% 25 
29 
Sign-off by Primary Stakeholders
2011/8/152011/8/162 days2011/8/152011/8/15-2 days100%  Primary Stakeholder
30 
Sign-off by Business Sponsor
2011/8/152011/8/162 days2011/8/162011/8/16-2 days100%  Peter
31 
Sign-off by Technical Sponsor
2011/8/152011/8/162 days2011/8/162011/8/16-2 days100%  Lee
32 
Submit to PRB
2011/8/172011/8/171 day2011/8/162011/8/16-1 day100% 28Claud
33            
34 
Project Approved to development
2011/8/312011/8/311 dayNANA0 days0%   
35 
Project Briefing
2011/9/12011/9/11 dayNANA0 days0% 34 
36            
37 
UI Design and Mockup Development
2011/9/12011/9/149 daysNANA0 days0%   
38 
HTML Mockup Development
2011/9/12011/9/22 daysNANA0 days0%  Zhang
39 
Review mockups & feedback
2011/9/52011/9/51 dayNANA0 days0% 38Zhang,He,Si,Primary Stakeholder
40 
Revise mockups
2011/9/62011/9/61 dayNANA0 days0% 39Zhang,He,Si,Primary Stakeholder
41 
Final Review & Revision
2011/9/72011/9/71 dayNANA0 days0% 40Zhang,He,Si,Primary Stakeholder
42 
Sign off HTML Mockup
2011/9/82011/9/81 dayNANA0 days0% 41He,Si,Primary Stakeholder
43 
UI Summary Preparation
2011/9/92011/9/91 dayNANA0 days0% 42Zhang
44 
Review UI Summary
2011/9/132011/9/131 dayNANA0 days0% 43He
45 
Sign-off UI Summary
2011/9/142011/9/141 dayNANA0 days0% 44He
46            
47 
Development & Unit Testing
2011/9/92011/9/2914 daysNANA0 days0%   
48 
Technical walkthrough session
2011/9/92011/9/91 dayNANA0 days0%  He,Dev
49 
Coding & Unit Testing
2011/9/132011/9/2812 daysNANA0 days0% 48Dev
50 
Sign-off development
2011/9/292011/9/291 dayNANA0 days0% 49He
51            
52 
System Test Preparation & Testing
2011/9/92011/10/1723 daysNANA0 days0%   
53 
System Test Plan
2011/9/92011/9/165 daysNANA0 days0%   
54 
Prepare system test plan
2011/9/92011/9/132 daysNANA0 days0% 42Lana
55 
Review & revise system test plan
2011/9/142011/9/152 daysNANA0 days0% 54He,Lana
56 
Sign off system test plan
2011/9/162011/9/161 dayNANA0 days0% 55He,Lana
57 
System Test Cases
2011/9/192011/9/288 daysNANA0 days0%   
58 
Prepare UI test cases
2011/9/192011/9/213 daysNANA0 days0% 56Zhang
59 
Prepare system test cases
2011/9/192011/9/213 daysNANA0 days0% 58He
60 
Review & revise system test cases
2011/9/222011/9/232 daysNANA0 days0% 59He,Lana
61 
Final Review & revise system test cases
2011/9/262011/9/272 daysNANA0 days0% 60He,Lana
62 
Sign-off system test cases
2011/9/282011/9/281 dayNANA0 days0% 61He,Lana
63 
Pre-SIT Preparation
2011/9/262011/10/35 daysNANA0 days0%   
64 
Setup Test Environment & Data
2011/9/262011/10/35 daysNANA0 days0% 65He,Lana,Claud
65 
Pre-SIT code merge
2011/10/32011/10/30 daysNANA0 days0% 50He
66 
System Testing
2011/10/82011/10/178 daysNANA0 days0%   
67 
First round of SIT testing
2011/10/82011/10/125 daysNANA0 days0% 65He,Dev
68 
Bug Fix & Re-test
2011/10/132011/10/142 daysNANA0 days0% 67He,Dev
69 
Sign-off system testing
2011/10/172011/10/171 dayNANA0 days0% 68He,Lana
70            
71 
UAT Preparation & Testing
2011/9/212011/11/127 daysNANA0 days0%   
72 
UAT Test Plan
2011/9/212011/9/286 daysNANA0 days0%   
73 
Prepare UAT Test Plan
2011/9/212011/9/233 daysNANA0 days0%  Lana
74 
Review & revise UAT test plan
2011/9/262011/9/272 daysNANA0 days0% 73Lana,Si
75 
Sign off UAT Test Plan
2011/9/282011/9/281 dayNANA0 days0% 74Si,Lana
76 
UAT Test Cases
2011/10/82011/10/178 daysNANA0 days0%   
77 
Prepare UAT Test Cases
2011/10/82011/10/92 daysNANA0 days0% 75,62Si
78 
Review UAT Test Cases & feedback
2011/10/102011/10/112 daysNANA0 days0% 77Lana
79 
Revise UAT Test Cases
2011/10/122011/10/121 dayNANA0 days0% 78Si
80 
Final review UAT Test Cases & feedback
2011/10/132011/10/131 dayNANA0 days0% 79Lana
81 
Final Revise UAT Test Cases
2011/10/142011/10/141 dayNANA0 days0% 80Si
82 
Sign-off UAT Test Cases
2011/10/172011/10/171 dayNANA0 days0% 81Si,Lana
83 
Pre-UAT Preparation
2011/10/112011/10/186 daysNANA0 days0%   
84 
Setup QA Test Environment & Test Data
2011/10/112011/10/186 daysNANA0 days0% 86FFHe,Si,Lana,Claud
85 
Brief Testers on UAT
2011/10/182011/10/181 dayNANA0 days0% 86FFSi
86 
Pre-UAT code merge
2011/10/182011/10/181 dayNANA0 days0% 69He
87 
User Acceptance Testing
2011/10/192011/11/110 daysNANA0 days0%   
88 
First round of UAT testing
2011/10/192011/10/255 daysNANA0 days0% 86Si,UAT Tester
89 
Bug Fix & Re-test
2011/10/192011/10/319 daysNANA0 days0% 86Si,UAT Tester,He
90 
Signoff User Acceptance Testing
2011/11/12011/11/11 dayNANA0 days0% 89Si,Lana
91            
92 
Rollout
2011/11/22011/11/32 daysNANA0 days0%   
93 
Post-UAT code merge
2011/11/22011/11/21 dayNANA0 days0% 90He
94 
System launch
2011/11/32011/11/31 dayNANA0 days0% 93He
95 
Send internal announcement regarding launch
2011/11/42011/11/41 dayNANA0 days0% 94 
96            
97 
Project Closure Activities
2011/11/72011/11/2313 daysNANA0 days0%   
98 
Project Closure Meeting
2011/11/72011/11/168 daysNANA0 days0%   
99 
Confirm whether Project Closure Meeting required
2011/11/72011/11/115 daysNANA0 days0% 95Claud
100 
Conduct Project Closure meeting (if required)
2011/11/142011/11/163 daysNANA0 days0% 99Lana,Zhang,Si,Lana,He
101 
Change History Document
2011/11/72011/11/168 daysNANA0 days0%   
102 
Prepare Change History Document
2011/11/72011/11/93 daysNANA0 days0% 95He
103 
Review & revise Change History Document
2011/11/102011/11/143 daysNANA0 days0% 102Si,He
104 
Endorse Change History Document
2011/11/152011/11/151 dayNANA0 days0% 103Si
105 
Upload Change History Document to OWL
2011/11/162011/11/161 dayNANA0 days0% 104Claud
106 
Project Closure Review Checklist
2011/11/72011/11/2111 daysNANA0 days0%   
107 
Prepare Discrepancies & Quality Audit
2011/11/72011/11/115 daysNANA0 days0% 95Lana
108 
Prepare Closure Review Checklist
2011/11/72011/11/115 daysNANA0 days0% 95Lana
109 
Update Closure Review Checklist
2011/11/142011/11/152 daysNANA0 days0% 108Claud
110 
Review closure checklist
2011/11/162011/11/183 daysNANA0 days0% 109Lee,He,Lana
111 
Upload closure checklist to OWL
2011/11/212011/11/211 dayNANA0 days0% 110Claud
112 
Customer Satisfaction Survey
2011/11/172011/11/235 daysNANA0 days0%   
113 
Send Customer Satisfaction Survey
2011/11/172011/11/171 dayNANA0 days0% 100Claud
114 
Conduct discsussion with TM,QA, BRA on CSS
2011/11/182011/11/212 daysNANA0 days0% 113Claud,He,Lana,Lana
115 
Collate & Submit CSS results
2011/11/222011/11/232 daysNANA0 days0% 114He,Claud
116 
Check all documents are uploaded to OWL
2011/11/222011/11/221 dayNANA0 days0% 100Claud
117 
Send final progress report to announce project is closed
2011/11/232011/11/231 dayNANA0 days0% 116Claud
118 
Close the project sites
2011/11/232011/11/230 daysNANA0 days0% 117Claud
 
  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论

“相关推荐”对你有帮助么?

  • 非常没帮助
  • 没帮助
  • 一般
  • 有帮助
  • 非常有帮助
提交
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值