Activity Duration Estimating technique - PERT铪铪铪

在画出项目活动网络图,准备寻找关键路径之前,必须先将每个在活动用时(Duration)进行估算,PMBOK 中提到的几种估算方法(PMBOK 2004 3rd P141-P142)中有一种叫做Three-Point Estimates,这其实就是PERT方法 - Program Evaluation and Review Technique. 这一方法最早产生于美国海军在研发 Polaris系统时。当时人们想出这种方法是因为这是一项从来没有做过的事情,没有任何数据来估算项目的时间。由此可见PERT适用于不确定条件下的时间估算。

PERT assumes a beta probability distribution (beta分布) for the time estimates. For a beta distribution, the expected time for each activity can be approximated using the following weighted average:

Expected time (期望) =  ( Optimistic  +  4 x Most likely  +  Pessimistic ) / 6

This expected time may be displayed on the network diagram.

To calculate the variance for each activity completion time, if three standard deviation times were selected for the optimistic and pessimistic times, then there are six standard deviations between them, so the variance is given by:

[ ( Pessimistic  -  Optimistic ) / 6 ]2

SD(标准差) = ( Pessimistic  -  Optimistic ) / 6

(from http://www.netmba.com/operations/project/pert/)


  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值