What is Fast Tracking and Crashing?

Fast tracking and crashing are techniques without which a project manager can’t survive. I know many of Project managers out there reading this blog will agree with me. Even though these are schedule compression techniques which are not supposed to be used commonly, it’s very common in real life. So for both practical usages as well as for clearing PMP®aspirant’s doubts around these techniques, I am penning down this blog. Let’s look in to the details of these techniques

Fast tracking – As per PMBOK® Guide fifth edition

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration

Important points which gets ignored about Fast Tracking

  • Fast tracking is not done blindly by changing schedule to have activities running in parallel.Rather activities are analysed to parallel work and extent of it.
  • There is reference to “at least a portion of their duration.” In definition. This means full activity/activities are not required to be done in parallel. Portions can be done and most of the time its portions only
  • In a situation where schedule compression is required, this technique is explored first
  • Any schedule compression technique is applied on the activities of critical path activities else we may end up owning risk without any tangible output of it
  • Fast tracking can only be done to some limits after which if continued may only add risk and rework and not schedule compression. Ultimately you have to wait for concrete to settle before start of painting
fast-tracking-activity

Crashing – As per PMBOK® Guide fifth edition

A technique used to shorten the schedule duration for the least incremental cost by adding resources

Important points which gets ignored about Crashing

  • Crashing is not done blindly by adding resources. First the additional cost and benefits with crashing are evaluated and then only this is taken forward. Cost and schedule trade-offs are analysed to explore least additional cost and maximum compression
  • Additional resources doesn’t only mean additional number of heads but it can be any of below
    • Approving overtime
    • Paying extra
    • Adding more resources
  • This option is always explored after exploring fast tracking for a obvious reason of additional cost
  • Any schedule compression technique is applied on the activities of critical path activities else we may end up owning risk without any tangible output of it
  • Crashing can be done to some limits, after which if continued may only consume money without schedule compression. Ultimately you can’t deliver a baby in one month if resources increased from 1 to 9
crash-resource

Comparison of these two techniques

 

Sno Fast Tracking Crashing
1 Activities or phases are performed in parallel to compress the schedule More resources are added to the activities or phases to compress the schedule
2 Increases rework and risk Increases cost and can result in increased risk/cost too
3 Works only when activities/phases can be overlapped to shorten the project duration Works only for activities where additional resources will shorten the activity’s duration
4 Always tried first Always tried when fast tracking hasn’t given required compression in schedule
5 Applied on critical path activities. If not it will only add to float Applied on critical path activities. If not it will only add to float

Frequently asked questions

Q: What is fast tracking? Is it same as lead?
A: Fast tracking is schedule compression technique in which activities are done in parallel to achieve compression. Lead is a type of dependency which helps in doing so.

Q: What is crashing? Is it same as fast tracking?
A: In crashing schedule compression technique additional resources are added to bring the timelines in. Fast tracking and crashing is different.

Q: What is the difference between fast tracking & crashing?
A: Refer above table for comparison of both

Q: Which technique is better?
A: Depends on needs. If you can manage enough with fast tracking that’s the best because it doesn’t involve additional cost however crashing helps in bringing timelines in considerably in some scenarios. E.g. construction projects, more workers can build the wall earlier

Q: Why we apply schedule compression on Critical path activities?
A: What comprises project length? It’s the critical path. If we apply compression on activities not on critical path, we are just increasing the float. Schedule compression is not as easy as it appears. Sometimes while doing compression you may end up getting more than one critical paths which will make project riskier. There is always lot of analysis at the back ground to do schedule vs cost trade-off to achieve an optimized schedule after compression

This is all I want to say about fast tracking and crashing. I hope this helps in resolving some long pending confusions. If not, please feel free to put your follow up questions here or on our Forum

  • 0
    点赞
  • 1
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
本课程详细讲解了以下内容:    1.jsp环境搭建及入门、虚拟路径和虚拟主机、JSP执行流程    2.使用Eclipse快速开发JSP、编码问题、JSP页面元素以及request对象、使用request对象实现注册示例    3.请求方式的编码问题、response、请求转发和重定向、cookie、session执行机制、session共享问题     4.session与cookie问题及application、cookie补充说明及四种范围对象作用域     5.JDBC原理及使用Statement访问数据库、使用JDBC切换数据库以及PreparedStatement的使用、Statement与PreparedStatement的区别     6.JDBC调用存储过程和存储函数、JDBC处理大文本CLOB及二进制BLOB类型数据     7.JSP访问数据库、JavaBean(封装数据和封装业务逻辑)     8.MVC模式与Servlet执行流程、Servlet25与Servlet30的使用、ServletAPI详解与源码分析     9.MVC案例、三层架构详解、乱码问题以及三层代码流程解析、完善Service和Dao、完善View、优化用户体验、优化三层(加入接口和DBUtil)    1 0.Web调试及bug修复、分页SQL(Oracle、MySQL、SQLSERVER)     11.分页业务逻辑层和数据访问层Service、Dao、分页表示层Jsp、Servlet     12.文件上传及注意问题、控制文件上传类型和大小、下载、各浏览器下载乱码问题     13.EL表达式语法、点操作符和中括号操作符、EL运算、隐式对象、JSTL基础及set、out、remove     14.过滤器、过滤器通配符、过滤器链、监听器     15.session绑定解绑、钝化活化     16.以及Ajax的各种应用     17. Idea环境下的Java Web开发
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值