The concrete project with the largest single volume of Yongling Expressway was successfully poured

Red Net Moment News October 31st (Correspondent Yu Fangrui) From 7:00 on October 29th to 1:00 on October 30th, after 18 hours of hard work, the fourth contract section of Yongling Expressway YK39+155.5 Bird Pond Shop The concrete pouring of the right web bottom and web of the cast-in-place bridge on the main line of Heng-Zao Expressway was successfully completed. This pouring is the largest concrete project in Yongling Expressway with the largest single pouring volume, and the single pouring volume reaches 1122 square meters.


The bridge span of the Hengzao Expressway bridge span of the Yongling 4 standard birdtangpu intercommunication span is 35m+48m+35m cast-in-place prestressed concrete box girder. Among them, the 1st and 3rd spans are constructed by the method of full-house support, and the second span is constructed by the method of section steel + steel pipe column support. In order to ensure the smooth pouring of concrete this time, the leaders of Hengyong Company at all levels worked together to provide guidance, and the Transportation Guohe Company, the Project Department and the Second Director Office of Yongling attached great importance to it. Confidential meeting, mobilization and deployment meeting. Wu Chuping, deputy general manager and chief engineer of Transportation Guohe Company, Li Liujun, director of the second director's office, and Yu Jingchu, deputy director, came to the scene to supervise the battle and provided many valuable opinions and suggestions. Based on the actual situation on site, the project department has prepared a special construction plan for concrete pouring. It is estimated that the pouring time will be about 24 hours. Control, logistical support and other aspects have been carefully arranged, and we strive to be fully prepared and foolproof. The main equipment involved in this construction are: 3 sets of mixers, 12 sets of concrete tankers, 2 sets of sky pumps (1 spare), 2 sets of 25T truck cranes, 2 sets of PC220 excavators, and 1 set of 1000KVA box-type transformers (1 standby 300kW generator set, 2 on-site standby 50kw generators), etc. The personnel involved in the construction include 60 front desk personnel (including the project department) and 40 back office personnel.


The cast-in-place beam section of the box girder in this construction has a large pouring area, a large amount of concrete, a long continuous pouring time, high quality requirements, and an arduous and critical task. The on-site construction personnel strictly control, clarify the responsibilities and tasks of all parties, and cooperate closely with each team to complete the construction work in one go. At the same time, the safety production management policy of "safety first, prevention first" is strictly implemented to ensure the safety and smoothness of the pouring process.


The successful pouring of the box girder this time marks a major breakthrough in the key node projects of the Yongling Fourth Standard Project, and has accumulated valuable experience for the subsequent construction of cast-in-place beams. Next, all the construction personnel of Yongling Fourth Standard will work hard, seize the golden period of construction, work together to speed up the project construction, adhere to the "two-handed and correct" of epidemic prevention and control and safety production, and ensure that all projects are completed this year. Construction tasks for cast-in-place and precast beams.

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论

“相关推荐”对你有帮助么?

  • 非常没帮助
  • 没帮助
  • 一般
  • 有帮助
  • 非常有帮助
提交
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值