SPT: 50---- Phantom assembly (MRP2 -- > special procurement type)
BOM list ( ASM -- the component in this item has its own BOM )
这个phantom 的料号 体现在工单里面的效果; (它是一个组装的线终端)
http://scn.sap.com/docs/DOC-46110
Phantom Assemblies:
Phantom assemblies are ‘logical groupings’ of components, and they are ‘fictitious assemblies’ that never get produced. Their components are integrated with the higher level product. The basic reasons of the popular use of phantom assemblies are:
- Grouping by a logical process and creation of a ‘nomenclature’
- Simplicity in the BOM structure for a complex in-house product containing thousands of materials as BOM components.
Configuration setting for the special procurement type ‘Phantom Assemblies’:
Regarding master data difference of a phantom assembly and a real assembly is: a phantom assembly does not need a Routing, since it is not going to be produced. This derives the following consequences:
- There are no planned orders/ production orders for the phantom assemblies.
- There are no stocks of the phantom assemblies.
Indicator: assembly
Indicator: the component in this item has its own BOM.