BAC = Budget at Completion -----完工预算
AC = Actual Cost -------实际成本
EV = Earned Value. -----挣值
PV = Planned Value -----计划价值
CV = Cost Variance -----成本偏差
CV = EV- PV
SV = Schedule Variance -----进度偏差
SV = EV - PV
CPI = Cost performance Index -----成本绩效指数
CPI = EV/AV
SPI = Schedule performance Index —进度绩效指数
SPI = EV/PV
ETC = Estimate to Complete ----完工尚需估算
EAC = Estimate at Completion ----完工估算
典型ETC = BAC/CPI
非典型 EAV = AC+(BAC-EV)
进度成本同事作用EAC = AC+(BAC-EV)/(CPI*SPI)
TCPI = To-Complete Performance Index ----完工尚需绩效指数
TCPI = (BAC-EV)/(BAC-AC)
TCPI = (BAC-EV)/(EAC-AC).
VAC = Variance at Completion ----完工偏差