一、计划时界总体介绍:
计划时界为当前日期距需求点的时间间隔(天数)。( 注 :视频讲解需编辑,下期发布 )
与MRP类型配置一起配合使用,下图为PRESS中 不同MRP类型针对“确定的类型”进行讲解:
Firming methods of existing procurement proposals (withi-n the planning time fence)
针对在计划时界内、现有的计划订单或PR,锁定方式:
-
No firming of procurement proposals within the planning time fence.
计划时界内的计划订单或PR,不锁定;
-
Automatic firming of procurement proposals within t he planning time fence.
计划时界内的计划订单或PR,自动锁定;
-
Manual firming of procurement proposals within the planning time fence (no automatic firming of procurement proposals).
计划时界内的计划订单或PR,需手工锁定;
Firming methods of new order proposals (within the planning time fence)
针对在计划时界内、新产生的计划订单或PR,锁定方式:
-
Automatic creation of new procurement proposals to cover the shortages within the planning time fence. However, the system pushes the dates of these new procurement proposals outside the planning time fence.
自动创建新的计划订单或PR,系统将这些新的计划订单或PR的日期推到计划时界日期之外;
-
No new procurement proposals created to cover the material shortages within the planning time fence.
在计划时界内,不产生新的计划订单或PR。
配置截图:MRP类型中的 确定的类型有4个可配选项。分别进