软考高项学习记录

第一周练习题

  1. D

  2. D

  3. A

  4. A

  5. A

  6. A D

  7. C

  8. D

  9. C

  10. B

  11. C

  12. B

  13. B

  14. C

  15. C A

  16. A

  17. A

  18. A D

  19. B

  20. A

  21. C D

  22. B

  23. C

  24. C

  25. B

  26. A

  27. D

  28. D

  29. B

  30. B

  31. A

  32. C

  33. A

  34. C

  35. B C

  36. B

  37. C A

  38. B

  39. D C

  40. D

  41. C

  42. B

  43. D

  44. B

  45. B D

  46. D A

  47. A D

  48. C

  49. B

  50. B

  51. C B

  52. C

  53. B

  54. A B

  55. D

  56. B

  57. C

  58. D A

  59. A C

  60. B A

得分45分,错误15题,正确率75%

第二周练习题

题号回答纠错
1B
2A
3A
4C
5D
6A
7C
8DA
9B
10AB
11DB
12C
13D
14DA
15C
16DC
17CD
18C
19D
20D
21B
22B
23B
24AB
25BC
26A
27BD 离谱
28C
29D
30BC
31C
32D
33C
34C
35B
36DB
37D
38A
39C
40A
41B
42DA
43B
44CA
45AB
46DB
47B
48DA
49B
50D
51A
52D
53C
54CB
55B
56D
57B
58DA
59C
60DB

21.计算过程

M = (8+38+20*4)/6 = 21

σ = (38 - 8) / 6 = 5

26天以后就是 M±1σ

50% - 68.26%/2 = 15.87%

24.画图

image-20240527153812697

项目关键路径C - D -E 9天

B晚1天开始 并且延期2天,总耗时 4 +3 +1+2 =10天,超出工期要赶工选A

晚一天开始不加4啊,3+1+2 = 6 天,不需要采取措施,选B

33.计算

BAC = 1230

AC = 900

PV = 850

EV = 1230 * 60% = 738

CPI = EV / AC =738/900 = 0.82

ETC = (BAC - EV)/CPI = (1230 - 738)/0.82 = 600

选C

33.计算分析

时间1年2年3年4年
BAC800800800800
PV200400600800
AC200400
EV100200

第2年末完成的实际进度为 100/200/4 = 12.5%

EV = 800 * 12.5% = 100

CPI = 100 / 200 = 0.5

39.计算

EAC = 47750 + 167500 - 38410 = 176840

CV = 38410-47750=-9340

SPI = 38410 / 44100 = 0.87

选C

40.计算分析

BAC = 13 + 23 +8 =44

AC = 20

EV = BAC * 30% = 44*0.3 = 13.2

CPI = 13.2 / 20 = 0.66

ETC = (44-13.2)/0.66 = 46.67

选A

正确答案

BAC = 13 + 23 +8 +2+2+2 =50

AC = 20

BAC = EV = BAC * 30% = 50*0.3 = 15

CPI = 15 / 20 = 0.75

ETC = (50-15)/0.75 = 46.67

答题时间

总耗时1小时55分钟

得分41分,错误19题,正确率68%

开始时间:2024年4月18日14:35:59

暂停:2024年4月18日16:03:47

开始2024年4月18日18:15:09

暂停:2024年4月18日18:20:47

开始2024年4月18日19:12:15

结束时间2024年4月18日19:34:27

第三周练习题

题号回答纠错
1C
2D
3BC
4B
5A
6AC
7A
8C
9DA
10DC
11D
12C
13C
14C
15A
16D
17A
18C
19BC
20A
21C
22B
23D
24C
25B
26CA
27CD
28D
29AD
30B
31C
32D
33B
34BC
35C
36A
37CD
38CB
39DC
40B
41CA
42BA
43A
44D
45CA
46DC
47C
48AD
49A
50C
51BD
52C
53DA
54B
55D
56DA
57AC
58CB
59DA
60C

43题计算

  1. 100000 * 0.6 + 30000+0.4 =- 72000

  2. 50000*0.9+10000*0.1 = 46000

  3. 10000 * 0.99 + 1000 * 0.01 = 9910

  4. 20000 * 0.8 + 10000*0.2 =18000

49题计算

  1. 35 *0.9 + 90 *0.1 = 40.5

  2. 20 * 0.3 + 60*0.7 = 48

54题计算

  1. (200-100) *0.7 + (90 - 100) *0.3 = 67

  2. (120 - 60) * 0.7 + (60 - 60 ) *0.3 = 42

答题时间

开始时间:2024年4月28日10:29:23

结束时间2024年4月28日11:16:42

总耗时47分钟

得分37分,错误23题,正确率61.67%

第四周练习题

题号回答纠错
1A
2C
3AB
4CA
5B
6CB
7C
8C
9CD
10CB
11C
12B
13A
14B
15DC
16A
17B
18AC
19CB
20A
21CD
22D
23C
24B
25DB
26AB
27C
28DA
29A
30CD
31DC
32A
33DC
34A
35D
36DB
37D
38B
39C
40AB
41A
42AC
43D
44AB
45D
46DC
47DC
48AB
49BC
50AC
51A
52B
53BA
54A
55DB
56C
57DC
58D
59B
60BC

答题时间

开始时间2024年5月9日17:31:28

结束时间2024年5月9日18:10:31

总耗时29分钟

得分32分,错误28题,正确率53%

第五周练习题

题号回答纠错
1BC
2AD
3C
4A
5B
6D
7D
8D
9A
10C
11A
12C
13D
14C
15A
16A
17D
18B
19A
20C
21B
22D
23B
24A
25A
26B
27B
28B
29C
30D
31B
32B
33A
34C
35C
36D
37C
38C
39C
40B
41B
42C
43B
44B
45D
46D
47B
48D
49D
50B
51C
52D
53A
54D
55B
56D
57A
58A
59B
60C

第六周练习题

题号回答纠错
1CB
2DB
3BA
4C
5C
6C
7BA
8D
9A
10B
11D
12D
13B
14AB
15A
16D
17C
18A
19A
20D
21A
22AB
23A
24A
25B
26B
27D
28D
29C
30D
31C
32A
33BD
34B
35CA
36D
37B
38A
39B
40B
41D
42B
43D
44D
45A
46A
47D
48D
49B
50A
51A
52A
53C
54B
55D
56D
57A
58B
59C
60C

课后作业

第十章回家作业(一)

回家作业1

image-20240419113832491

活动A : 12345,活动B: 456 6天

活动A : 12345,活动B: 123 5天

活动A : 12345,活动B:-101 7天

活动A : 12345,活动B: -4-3-2 10天

回家作业2

image-20240527154152355

回家作业3

image-20240419113726115

问题一

公司到山顶

最差要300分钟,最好要180分钟,最可能是220分钟

M = (300+180 + 220*4) / 6 = 226.67分钟

σa = (160-100)/6 = 10

σb = (140-80)/6 = 10

标准差 10*10 + 10*10 = 根号200 ≈ 14.14

问题二

从公司到山脚

活动A

M = (160+100+120*4)/6 = 123.33

σ = (160-100)/6 = 10

活动B

133分钟就是M±1

133分钟内 到达山脚的概率就是 50+68.26%/2 =84.13%

回家作业4

image-20240419141947924

问题一

路径 1-2-3-4- 6-8-10-13 = 2+4+10+ 6+6+7+2 = 16 + 21 = 37

1-2-3-4- 5-8-10-13 = 4+7+2 =13

5-7-9-11-12-13 = 4+5+8+4+6 = 27

5-7-9-12-13 = 4+5+8+5+6 = 28 关键路径

7-9-11-12-13 = 7+8+4+6 = 25

7-9-12-13 = 7+8+5+6 = 26

关键路径是1-2-3-4-5-7-9-12-13 同ABCDGJMN

问题二

总工期天数就是关键路径的天数 为 16 + 28 = 44天

回家作业5

image-20240419143119979

画图结果:

image-20240527153935470

image-20240509105713236

总时差:A:0,B:3,C:0,D:6,E:0,F:3,G:4,H:0

自由时差:A:0,B:3,C:0,D:0,E:0,F:3,G:4,H:无

回家作业6

image-20240419171315609

1.关键路径 BGI 120天

2.

活动持续时间自由时差总时差
A20010
B5000
C62424
D50010
E101020
G4000
H401010
I3000

回家作业7

image-20240419174748492

A工期 (1+7+4*4)/6 = 4

B工期(12+22+14*4)/6 = 15

C工期 (13+21+14*4)/6 = 15

D工期(8+16+9*4)/6 = 10

E工期(10+18+17*4)/6 = 16

F工期(6+8+7*4)/6 = 7

G工期(5+11+8*4)/6 = 8

H工期(9+17+16*4)/6 = 15

I工期(3+7+5*4)/6 = 5

image-20240527154001530

第十一章回家作业

回家作业1

image-20240422152458492

BAC = 4+10+12+4+8+6+10 = 54 万元

AC = 3+8+16+5+4 = 36 万元

EV = 4 +10 + 12 + 4 +2 = 32万元 出错了,活动C只完成了75%,活动F看错了预计是6万元; EV = 4 +10 + 12*75% + 4 +6/2 = 30万元  

PV = 4+10+12+4+4 = 34万元

回家作业2

image-20240422152518320

已完工50%,已铺8000,总项目就是16000平方码

BAC = 16000 * 2 = 32000美元

EV = 32000 * 50% = 16000美元 EV = 8000 * 2 = 16000美元

PV = 4000 *2 = 8000美元

AC = 8000美元

回家作业3

image-20240422135700230

①进度落后,SV 进度偏差SV

②成本超出 , CV 成本偏差CV

③PV 完工预算BAC

④超出计划完 工费用就是CV 完工预算:VAC = EAC - BAC

⑤超出计划完工日期,EV-PV = SV 估算的项目将整体延期的天数

⑥落后进度的天数 项目当前已延期的天数

回家作业4

image-20240422141143225

image-20240422141646680

问题一

(1) 关键路径BDEG,工期 24 周

(2)时序网络图, 紧前关系图(单代号图),双代号图,7格图

双代号时标网络图,         还有里程碑图,甘特图,逻辑横道图

(3)A的 总时差 (5-3) + (12-11) = 3 自由时差 5-3 = 2

D的 总时差 0 自由时差 0

F的 总时差 22 - 15 = 7 自由时差 22-15 = 7

(4)无影响 因为C的总时差是12-11 = 1,可以拖延1周

(4)若任务C拖延1周,对项目的进度无影响。 因为任务C的总时差是:1;延期1周,不会产生新的关键路径,因此不会影响工期。

image-20240422143101017

问题二

PV: 4 + 10 +12 +4 +8/2 = 34

EV: 4 + 10 + 12*0.75 +4 +6*0.5 = 30

AC: 3 +8 +16 + 5 +4 = 36

CV: 30 - 36 = -6

SV: 30-34 = -4

CPI: 30/36 ≈ 0.83

SPI: 30 / 34 ≈ 0.88

image-20240422145050398

问题三

进度绩效SPI<1 ,进度落后,要赶工或快速跟进,

成本绩效CPI<1,成本超支,要节约成本

image-20240422145104230

<span style="background-color:#f8f8f8"><span style="color:#333333">由于在监控点时的CPI=0.83<1,所以成本超支;SPI=0.88<1,因此进度落后:(2分)
​
​
进度绩效改进的措施有:
​
1、快速跟进----并行施工,以缩短关键路径的长度。
​
2、使用高素质的资源或经验更丰富的人员。
​
3、甲方同意前提下减小活动范围或降低活动要求。 
​
4、改进方法或技术,以提高生产效率。
​
5、加强质量管理,及时发现问题,减少返工,从而缩短工期。
​
6、成本可控情况下适当赶工。
​
成本绩效改进的措施有:
​
1、关注成本超支较严重的工作;
​
2、对成本的支出进行细化分析,找出成本超支的原因;
​
3、针对不同的原因,采取对应的措施。例如:
​
<span style="color:red">•</span>   (a)减少不必要的工作;
​
<span style="color:red">•</span>   (b)优化工作流程,提高效率;
​
<span style="color:red">•</span>   (c)削减不必要的资源;
​
4、定期对项目的成本绩效进行评估,及时按情况进行调整。</span></span>

问题四

image-20240422150223464

(1)BAC = 4 +10+12+4+8+6+10 = 54万元

(2)ETC = (BAC-EV)/1 = 54 - 30 = 24万元

EAC = AC + ETC = 36 +24 = 60万元

image-20240422150834428

计算题综合(一)

1.C

image-20240506153752387

计算: 200 * 0.75 + -40 * 0.25 = 140,选C

2.A 选D,投资回报 按照收入算最后减去成本

image-20240506154505689

疑问: 收入是盈利吗?我觉得应该减去成本

计算:

先算算要减去成本

0.5*(100-50) + 0.2*(200-50) + 0.15*(250-50) + 0.1*(50-50) + 0.05 * -500

25 + 30+ 30 + 0 - 25 = 60 ,实测结果不符合预期,那么题目中的收入应该就是净收入

0.5*(100) + 0.2*(200) + 0.15*(250) + 0.1*(50-50) + 0.05 * -500

50 + 40 + 37.5 + 0 - 25 = 102.5,选A

纠错

0.5*100+0.2*200+0.15*250+0+0.05*-500 -50 = 50 +40 +37.5-25 -50 = 102.5 -50 = 52.5选D

3.C

image-20240506155601896

500* 4% = 20

预计有20个不合格,480个合格

500 * (10000) + 480 * 2000= 5960000

20 * 23000 = 460000

596+46 = 642选C

4.D 选C

image-20240506160242505

一件赚50元,卖不完一件亏50元

1件赚50

2件, 0.1 的概率赚0 , 0.9 的概率赚100 0.1*0+0.9*100 = 90

3件 , 0.1的概率赚-50,0.2的概率赚50,0.7的概率赚150 0.1*-50 + 0.2*50+0.7*150 = 65.1 为什么会算错啊110

4件,0.1的概率赚-100,0.2的概率赚0,0.3 的概率赚100,0.4的概率赚200 0.1*-100 + 0.2*0 + 0.3*100 + 0.4*200 = -10+30+80=100

选D  应该选C

5.D

image-20240506161730657

8*0.2 = 1.6选D

6.C

image-20240506161856118

A: 0.4*90+0.4*80+0.2*80 = 36 +32 +16 = 84

B:0.4*80+0.4*85+0.2*90 = 32 + 34 + 18 = 84

选C

7.C 选A,选最大

image-20240506162150323

自己研发:

45*0.15+20*0.25+-5*0.4+-15*0.2 = 6.75 + 5 - 2 -3 = 6.75

采购代销

6.5*1 = 6.5

有条件购买

25*0.15 + 10*0.25 +0 +0 = 3.75+2.5 = 6.25

选C

8.(1)A (2)B

image-20240506162653926

设产品用量为P

自制成本

12*P + 4000

采购成本

P小于3000件,成本14*P

P大于3000件,成本13*P

当小于3000件时,12*P + 4000 = 14*P,P = 2000,成本相同

当大于3000件时,12*P + 4000 = 13*P,P = 4000,成本相同

结论,小于2000件外购,2000-3000自制,3000-4000外购,大于4000自制

(1)A,(2)B

9.C

image-20240506163839924

总共12人

1,2,6,10,规律就是(n-1)n/2 11*12/2=66

10.D

image-20240506164605598

11.C 选D

image-20240506164835445

4*(5000 - 250) = 19000行/人月

20000 / 19000 = 1.05 选C

纠错

要两年沟通 ,沟通路径就是4*3/2 = 6

每月工作量就是 4*5000 - 6*250 = 18500

20000/18500 = 1.08 选D

12.A 选B

image-20240506170733949

13.C

image-20240506170835049

两个骰子,点数和2的概率就是都为1,1/36 , 点数和为7的概率(1+6,2+5,3+4,4+3,5+2,6+1),为6/36, 点数和为11的概率(5+6,6+5),为2/36

赢X元的概率为8/36,输9元的概率1/36,输一元的概率就是27/36

EMV = 8/36 * X + 1/36 * -9 + 27/36 * -1 = 8/36 * X - 1

当EMV>0,即 8/36 * X - 1> 0 , 8/36 * X > 1, 8X>36,X>4.5 选C

14.C

image-20240506172513109

期数012
净现金流量-630330440
净现值流量-630300363.64
净现值累计-630-33033.64

330/(1+0.1)^1 = 300 , 440 / (1+0.1)^2 ≈ 363.64

33.64最接近34选C

15.B

image-20240506173016281

A: 14000 / 1.1 + 19000 / 1.21 ≈ 28429.75

B: 23000 / 1.1 + 20000 / 1.21 ≈ 37438.02

C: 18000 / 1.1 + 24000 / 1.21 ≈ 36198.35

D: 21000 / 1.1 + 22000 / 1.21 ≈ 37272.73

选B

16.A

image-20240506173546565

2011年2012年2013年2014年2015年
-2000600700800500
-2000-1400-700100600

PP = 3-1 + |-700| / 800 = 2.875,选A

17.(1)A (2)B

image-20240506174057549

01234
净现金-2000990121011981277
净现金累计-2000-101020013982675
净现值-20009001000900.08872.21
净现值累计-2000-1100-100800.081672.29

990/1.1 = 900, 1210/1.21 = 1000, 1198/1.1^3 ≈ 900.08, 1277/1.1^4 ≈ 872.21

PP = 2-1 + |-1010|/1210 ≈ 1.83

Pt = 3-1 + |-100|/900.08 ≈ 2.11

18.D

image-20240506174959839

012345678
净收益-1000200200200200200200200200
净收益累计-1000-800-600-400-2000
净现值-1000181.82165.29150.26136.60124.18112.89102.6393.30
净现值累计-1000-818.18-652.89-502.63-366.03-241.85-128.96-26.3366.97

Pt = 8-1 + |-26.33|/93.30 ≈7.28

19.(1)C (2)B

image-20240506175828632

012345
净现金-35000190008500100001400018000
净现金累计-35000-16000-75002500
净现值-3500017,29070557500952011160
净现值累计-35000-17710-10655-31556365

(1) PP = 3-1 + |-7500|/10000 = 2.75≈2.8

(2) Pt = 4-1 + |-3155|/9520 ≈3.33 ≈ 3.4

20.A

image-20240506180751701

甲项目:

投资10,收益2+23+7 = 32

ROI = 32/10 = 3.2

乙项目:

投资100,收益190

ROI = 190/100=1.9

丙项目:

投资20,收益15+18+30 = 63

ROI = 63/20 = 3.15

丁项目:

投资150,收益300

ROI = 300/150 = 2

纠错,要减去成本

image-20240507143638883

21.(1)D (2)B

image-20240506181321386

012342021年
支出-120-1.1-0.35-0.05=-1.5-1.5-1.5-1.5
收益06666
净现金-1204.54.54.54.5
净现金累计-12-12-7.5-31.56

PP = 4-1 + |-3|/4.5 ≈ 3.67

ROI = 6 / (1.5*4 + 12)≈ 0.33

22.无法选择没有选项10.8 选D

image-20240506182212048

路径距离
1-21.3
2-3 1-30.9 2.1
3-4 2-4 1-42.6 1.8 0.9
4-50.7

规律是每列最短路径,最小生成树1-2-3,1-4-5-6-7-8

最短长度就是 1.3+0.9+0.9+0.7+0.9+0.6+0.5= 5.8

1号离海岸还有5海里,总共就是10.8海里

纠错

image-20240507144210391

23.B

image-20240507095307141

后悔值需求量大需求量中需求量小大中取小
00350350
20020300300
50017050500
400700400

24.(1)A (2)D

image-20240507100132299

设甲为X万个,乙为Y万个

2X+3Y = 20

3X+Y=15

2Y ≤ 12 => Y≤6

3X≤ 15 => X≤5

利润
1626
2524
3422
4320
5010

纠错

image-20240507144537622

image-20240507144630360

25.B

image-20240507101820364

A17202326
B21252420
C2819√1821
D21211919

17+20+19+19 = 75选B

image-20240507144916738

26.B

image-20240507102359425

任务1任务2任务3任务4任务5
2525
252028
27
2323

甲做任务1,丙做任务2,丁做任务4,乙做任务3和任务5

纠错

image-20240507150423933

27.B

image-20240507102754048

1.中部运到甲8*2 = 16,剩余产量2,,甲满

2.中部运到丙2*3 = 6,剩余0,丙还能接收10

3.东部运到丙10*4 = 40,剩余6,丙满

4.西部运到乙14*5 = 70,剩余8,乙满

5.东部运到丁6*11 = 66,西部运到丁8*6 = 48,剩余0,丁满

最小运费为 16+6+40+70+66+48 = 246,方法错误还是画图吧

Y产量
东部412411016
中部21039110
西部85116122
X2513
需求量8141214

1.西部给到乙5*14=70,西部剩余8,乙满

Y产量
东部4411016
中部239110
西部811628
X213
需求量81214

2.西部给到丁6*8 = 48,西部空,丁还能接收6

Y产量
东部4411016
中部239110
X212
需求量8126

3.中部给到甲2*8=16,中部剩余2,甲满

Y产量
东部411716
中部3962
X12
需求量126

4.东部给到丙4*12=48,东部剩余4,丙满

产量
东部114
中部92
需求量6

5.东部给到丁4*11 = 44 ,中部给到丁2*9 = 18 ,给完

最小运费为 70+48+16+48+44+18 = 244 选B

计算题综合(二)

1.B

image-20240508172634124

σ = (36 - 6) / 6 = 5

求0 到+1σ以内的概率

68.26%/2 = 34.13%

2.(1)B (2)B

image-20240508173622425

M = (38 + 8 + 20 * 4) / 6 = 21天

σ = (38 - 8 ) / 6 = 5

求大于+1σ的概率

50% - 68.26%/2 = 15.87%

选B,B

3.C

image-20240508174424997

(最悲观+ 105 + 最可能) / 3 = 94 (最悲观+ 105 + 最可能) = 282

(最悲观+ 105 + 最可能 * 4 ) / 6 = 94.5 最悲观+ 105 + 最可能 * 4 = 567

3*最可能 = 567 - 282 = 285

最可能 = 285 / 3 = 95

最悲观 = 282 - 105 - 95 = 82选C

4.A

image-20240508175527364

M = (36 + 12 + 21 *4) / 6 = 22

22-18 = 4

5.C

image-20240508175711882

先计算各个项目的期望完工时间

A:(10*4+8+12) / 6 = 10

B:(12*4+11+14 ) / 6= 12.17

C:4

D:8

E:18

F:8

G:12

C紧前B , C:4+12.17 = 16.17

D紧前A, D:10+8 = 18

E紧前A, E:10+18 = 28

F紧前CD,取最大18 , F: 18+8 = 26

G紧前EF,取最大28 , G:28 + 12 = 40 , 选C

6.A

image-20240508181400753

A: 12 , B:19 , C:7 , D: 12.83 , E: 6 , F: 12

B预计在 12 + 19 = 31 天完成

D预计在 7+12.83 = 19.83 天完成

E预计在 31 + 6 = 37 天完成

F预计在37 + 12 = 49 天完成

所以项目预期完工时间为49天

σ = 3.2

±1σ : 45.8 - 52.2

±2σ : 42.6 - 55.4

±3σ : 39.4 - 58.6

95%就是±2σ , 95.46% , 选A

7.C

image-20240509104417104

M的最早结束时间16+5 = 21

25-21 = 4,自由时差

M的最迟结束时间28

28-21 = 7总时差

8.B

image-20240509110048647

22-16-4 = 2

9.AB 结论选A

image-20240509110134266

自由时差: 16-(6+9) = 1

总时差: 9- 6 = 3

不是说单选吗?

解析:

image-20240514170114960

10.D

image-20240509110546772

路径

A-B-C = 3+5+3 = 11

D-H-C =9 +0 +3 = 12 关键路径

D-E = 9+2 = 11

F-G = 5+3 = 8

12-8 = 4

解题思路

image-20240514170929880

11.A

image-20240509110904304

先找关键路径

A-B-D-H-J = 3+4+7+2+2 = 18

A-B-E-H-J = 3+4+7+2+2 = 18

A-C-D-H-J = 3+5+7+2+2 = 19 关键

A-C-E-H-J = 3+5+7+2+2 = 19 关键

A-C-F-J = 3+5+8+2 =18

A-C-G-I-J = 3+5+4+3+2 =17

17+2 = 19不延期

解题思路

image-20240514171052518

12.B

image-20240509111233131

1-4-5-8-9-e =4+7+6+8+1+3 = 29

1-4-5-8-10-e =4+7+6+8+4+3 = 32 -1 =31

2-7-5-8-9-e = 3+14+2+8+1+3 = 31 -2 = 29

2-7-5-8-10 = 3+14+2+8+4+3 = 34 -2 =32 -1 = 31

3-6-7-5-8-9-e = 6+9+5+2+8+1+3 = 34 +3 = 37

3-6-7-5-8-10-e = 6+9+5+2+8+4+3 = 37 关键路径 -1 =36 +3 = 39

增加了39-37 = 2天

解题思路

image-20240514171141721

13.C 选D

image-20240509111830441

先找关键路径

A-C-F =4+8+8 =20 关键路径 -3

B-E-F 5+0+8 = 13

B-D-G =5+5+8 = 18

解析

image-20240514171459911

14.B

image-20240509112120643

4-6总时差17-15 = 2 - 3 = -1

解题思路

image-20240514171627021

15.(1)C (2)A

image-20240509112257374

先算最晚结束时间

A:5

B:9

C:10

D:12

E:14

F:5

G:15

一开始7人,B必C先做完1天4人,分给2人做D给2人做F,1天后C做完多出3人没地方分配,最少需要7人

解题思路

image-20240514172018784

16.(1)B (2)C 选(1)A (2)A

image-20240509113156695

正常进度时间3+4+5 =12 , 费用 10+15+12+8 = 45万

赶工时间2+6 = 8, 费用15+17+13+11 = 56万

还要加上间接费用

45+12 = 57

56+9 =65,超预算,不 赶工A

3+6=9 65-5=60

解析

image-20240514172836768

17.B

image-20240509113548222

最早完成时间本月14日晚

总时差8

最晚完成时间本月22日晚

解题思路

image-20240514175724140

18.(1)B (2)D 选(2)C

image-20240509114006995

image-20240509114227523

活动B自由时差0,总时差1

最晚第6天,5月7号晚就是5月8号早前

解析

image-20240514175930516

19.C

image-20240509114444238

5天到7天,有3人空余刚好给C再加1人就够跟B同时完成,3+6+1 = 10人

解题思路

image-20240514175959925

20.C

image-20240509114700753

因为甲施工时间长,2+4>5设备先给甲用,3+2+4 = 9 天

解题思路

image-20240514180049421

21.

image-20240509133926921

问题1

image-20240509134052331

先画图

image-20240527154021479

image-20240514180455070

(1)

B的自由浮动时间 = 11 - 8 =3

C的自由浮动时间 = 11-11 = 0

F的自由浮动时间 = 19 - 16 = 3

(2)不知道怎么写公式啊

D的最迟开始时间 = 9

G的最迟开始时间 = 13

结论:不写公式

问题2

image-20240509134109013

如果活动B拖延了4天,则该项目的工期会拖延1天。

因为B活动的总时差是3天,拖延4天会比当前的关键路径多1天,所以工期会拖延1天。

问题3

image-20240509134124085

实际完成了定义活动,排列活动顺序,估算活动持续时间的过程。

还要完成规划进度管理,制定进度计划,控制进度的过程。

解题思路

image-20240514180813264

22.

image-20240509142920241

问题1

image-20240509142953168

先列出所有路径

1-2-3-4-6-8-10-13 =2+4+10+6+6+7+2 = 37

1-2-3-4-5-8-10-13 =2+4+10+4+7+2 =29

1-2-3-4-5-7-9-11-13 =2+4+10+4+5+8+4+6 =43

1-2-3-4-5-7-9-12-13 =2+4+10+4+5+8+5+6 =44

1-2-3-4-7-9-11-13 =2+4+10+7+8+4+6 =41

1-2-3-4-7-9-12-13 =2+4+10+7+8+5+6 =42

关键路径是1-2-3-4-5-7-9-12-13,即ABCDGJMN

image-20240514180850920

问题2

image-20240509143814108

1-2-3-4-5-7-9-12-13 =2+4+10+4+5+8+5+6 =44天

image-20240514180906954

问题3

image-20240509143918637

image-20240509143937549

(1)

image-20240509144924216

image-20240509145011571

(2)

总工期44天,要缩短到38天,就是赶工6天

活动J赶工2天,活动N赶工3天,活动G或者活动M赶工1天,增加的费用最少为710元

200+360+150 = 710元

解题思路

image-20240514182007867

image-20240514182031507

23.

image-20240509145415330

画图最直观

image-20240527154055059

问题1

image-20240509145441861

关键路径是ABDFHI

工期 = 10 +20+10+20+20+15 = 95天

问题2

image-20240509150700483

活动C的总时差 = 30天

活动C的自由时差 = 0天

活动E的总时差 = 30天

活动E的自由时差 = 30天

活动G的总时差 = 30天

活动G的自由时差 = 30天

image-20240514182343982

问题3

image-20240509151452643

(1)

因为12人会冗余,所以没有统一该项目经理的要求。

若不考虑人员能力差异,该项目所需人数最少是10人

因为C的总时差是30天,而活动B和活动D总耗时30天,所以人员先分配给活动B,之后做活动D,需要8人

活动D完成后,从8人中分配4人做活动C,分配4人做活动F

活动E和活动F能同一天完成,这时候活动G总时差是30天,已经拖延了20天

分配7人做活动H,分配3人做活动G,活动G和活动H都完成后,活动I只需要8人

所以最少需要10人

最佳情况,活动B完成后开始做活动C,

活动D需要5人,活动C需要4人,因为活动B只需要8人,所以还要加1人,总人数是9人

活动D完成时活动C也完成,继续做活动E需要4人,活动F需要4人 , 空闲1人

活动F做10天后,活动E完成,分配3人做活动G , 空闲2人

活动F完成时活动G也完成,分配7人做活动H ,空闲2人

最后做活动I只需要8人

所以最少需要9人

image-20240514182625374

image-20240509153122475

(2)资源平滑

image-20240509160255913

(3)

活动C最迟从第31天开始

活动E最迟从第41天开始

活动G最迟从第51天开始

image-20240514182749650

问题4

image-20240509160942161

(1)D 选C
(2)G 选D
(3)C 选G
(4)A
(5)F
(6)E

以下是对提供的参考资料的总结,按照要求结构化多个要点分条输出: 4G/5G无线网络优化与网规案例分析: NSA站点下终端掉4G问题:部分用户反馈NSA终端频繁掉4G,主要因终端主动发起SCGfail导致。分析显示,在信号较好的环境下,终端可能因节能、过热保护等原因主动释放连接。解决方案建议终端侧进行分析处理,尝试关闭节电开关等。 RSSI算法识别天馈遮挡:通过计算RSSI平均值及差值识别天馈遮挡,差值大于3dB则认定有遮挡。不同设备分组规则不同,如64T和32T。此方法可有效帮助现场人员识别因环境变化引起的网络问题。 5G 160M组网小区CA不生效:某5G站点开启100M+60M CA功能后,测试发现UE无法正常使用CA功能。问题原因在于CA频点集标识配置错误,修正后测试正常。 5G网络优化与策略: CCE映射方式优化:针对诺基亚站点覆盖农村区域,通过优化CCE资源映射方式(交织、非交织),提升RRC连接建立成功率和无线接通率。非交织方式相比交织方式有显著提升。 5G AAU两扇区组网:与三扇区组网相比,AAU两扇区组网在RSRP、SINR、下载速率和上传速率上表现不同,需根据具体场景选择适合的组网方式。 5G语音解决方案:包括沿用4G语音解决方案、EPS Fallback方案和VoNR方案。不同方案适用于不同的5G组网策略,如NSA和SA,并影响语音连续性和网络覆盖。 4G网络优化与资源利用: 4G室分设备利旧:面对4G网络投资压减与资源需求矛盾,提出利旧多维度调优策略,包括资源整合、统筹调配既有资源,以满足新增需求和提质增效。 宏站RRU设备1托N射灯:针对5G深度覆盖需求,研究使用宏站AAU结合1托N射灯方案,快速便捷地开通5G站点,提升深度覆盖能力。 基站与流程管理: 爱立信LTE基站邻区添加流程:未提供具体内容,但通常涉及邻区规划、参数配置、测试验证等步骤,以确保基站间顺畅切换和覆盖连续性。 网络规划与策略: 新高铁跨海大桥覆盖方案试点:虽未提供详细内容,但可推测涉及高铁跨海大桥区域的4G/5G网络覆盖规划,需考虑信号穿透、移动性管理、网络容量等因素。 总结: 提供的参考资料涵盖了4G/5G无线网络优化、网规案例分析、网络优化策略、资源利用、基站管理等多个方面。 通过具体案例分析,展示了无线网络优化中的常见问题及解决方案,如NSA终端掉4G、RSSI识别天馈遮挡、CA不生效等。 强调了5G网络优化与策略的重要性,包括CCE映射方式优化、5G语音解决方案、AAU扇区组网选择等。 提出了4G网络优化与资源利用的策略,如室分设备利旧、宏站RRU设备1托N射灯等。 基站与流程管理方面,提到了爱立信LTE基站邻区添加流程,但未给出具体细节。 新高铁跨海大桥覆盖方案试点展示了特殊场景下的网络规划需求。
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值