题目及答案
1) For what type of work is Scrum MOST suitable?
A) Complex
B) Simple
C) Pre-defined
D) Low-risk
选A
2) Which of the following is a MAIN purpose of a Sprint Backlog?
A) For the Development Team to organize themselves during the Sprint
B) For the Product Owner to understand what the Development Team has committed to for a Sprint
C) For the ScrumMaster to manage the Development Team’s progress during the Sprint
D) For the Development Team to manage the number of hours spent on tasks in the Sprint
选A
3) What is the main purpose of a Sprint Review?
A) For the Scrum Team and stakeholders to review what the Scrum Team has built, and to collaborate on what could be done next to create value.
B) For the Scrum Team to review their work and to determine what is needed to complete the next set of backlog items
C) For the Product Manager to be able to show progress to the Stakeholders
D) For Stakeholders to “hold the Scrum Team’s feet to the fire” - to make sure something is produced during the Sprint
选A
4) What is the ScrumMaster’s role in the Sprint Retrospective?
A) To provide answers to the challenges that the Scrum Team identifies
B) To facilitate the Scrum Team’s search for improvements
C) To lead the Scrum Team in the evaluation of each individual Scrum Team member
D) To determine the re-composition of the Scrum Team
选B
5) Considering the Agile Manifesto, which of the following statements best describes Scrum Teams and planning?
A) Planning is not important in Scrum.
B) Scrum Teams place value in following a plan, but they value responding to change even more.
C) Scrum is intended to be an efficient way to carry out plans that have already been made.
D) Traditional planning is replaced by the Sprint Burndown chart.
选B
6) During a Daily Scrum meeting, Olivia mentions she has found an available solution and she thinks that will solve one of the problems she has been working on. She wants to implement it immediately. What is the best next step?
A) The ScrumMast