pmp 第10章章节试题

本章题目少,就2道

1、 [单选] 沟通对项目成功非常关键,作为项目经理,你有3个相关方需要沟通。这时候又加进来一位新相关方也需要沟通,沟通渠道增加了几条?
Communication is key to the success of a project. As the project manager, you had three stakeholders with whom you needed to communicate. A new stakeholder has been added with whom you also need to communicate. How many communication channels have been added?

  •  A:3
    3
  •  B:4
    4
  •  C:6
    6
  •  D:10
    10

正确答案:B 你的答案:B

解析:原来 3 个相关方加上项目经理是 4 个人,沟通渠道 C 24=N*(N-1)/2=(4*3)/2=6 条;新增 1 人变成 5 个人沟通,C 25=N*(N-1)/2=(5*4)/2=10 条;沟通渠道新增:C 25- C 24=10-6=4 条。

2、 [单选] 项目实施过程中,开发阶段的工作已经外包给一支海外团队。执行项目期间,海外团队通知说有关于开发的重要信息有遗漏,但国内设计团队说已经提供了所有设计文档。造成这种情况最有可能的原因是什么?
In an implementation project, the development phase has been outsourced to an off-shore team. During the execution of the project, the off-shore team states that vital information to proceed in the development is missing. However, the on-shore design team has stated that all design documents have been provided. What could most likely be the cause of this situation?

  •  A:未正确创建沟通管理计划
    failed to create communication management plan correctly.
  •  B:未正确创建相关方参与计划
    failed to create stakeholders’ engagement plan correctly.
  •  C:项目经理缺乏沟通技巧
    the project manager lacks communication skills.
  •  D:未正确创建风险管理计划
    failed to create the risk management plan correctly.

正确答案:A 你的答案:A

解析:沟通管理计划应明确定义团队之间沟通的方式、频率,确认的方式和时限等,确保沟通的及时性和有效性。见 10.1.3.1。

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值