知识点滴 - Jira中的工作量录入和跟踪

在项目管理软件Jira中,在任务的属性中,包含了工作量的管理。

主要分为录入和跟踪两种。

录入工作量选项:

- 已花费的时间

- 开始的日期

- 还需要的时间

跟踪工作量选项:

- 花费时间的初步估计

- 还需要的时间

时间的表示法:

周w,日d,小时d。

1w = 5d 

1d = 8h

Logging Work and Time Tracking

The following points explain how to use Jira's logging work and time tracking options and what values these options can accept.

Note that in the single edit, if you leave one of the estimate fields empty, it automatically assumes the value specified in the other field. For example, if you specify the Original Estimate to be 4h, and leave the Remaining Estimate field empty, then it will be automatically populated with the value of 4h. The values can be changed whenever needed. In bulk edit, this behavior is only there if you select to change both fields. This rule does not apply to the Legacy Mode, where you can only update the Original Estimate until you start logging work.

  • Logging Work options

    • Time Spent - the amount of time logged working on the issue so far or while performing this Jira operation.

    • Date Started - the date and time when you started this unit of work.

    • Remaining Estimate - the amount of time anticipated to resolve the issue after completing this unit of work. You can adjust this value using the following options:

      • Adjust Automatically - adjusts the Remaining Estimate value by subtracting the amount of work logged in the Time Spent field from the Remaining Estimate's current value.

      • Leave Estimate Unset - does not specify any time estimates for the issue. This option is displayed only if no time estimates have been specified on the issue.

      • Use Existing Estimate of ... - does not adjust the Remaining Estimate value, leaving its current value 'as is'.

      • Set to ... - adjust the Remaining Estimate value to the amount of time you specify in this field.

      • Reduce by ... - adjusts the Remaining Estimate value by subtracting the amount of time you specify in this field.

  • If the Work Description text box is not available when logging work, then any text entered into the Comment text box will be copied across to the Work Description.

  • Time Tracking options

    • Original Estimate - the amount of time you originally believe is required to resolve the issue.

    • Remaining Estimate - the amount of time you believe is required to resolve the issue in its current state.

  • Field Values

    • You can specify a time unit after a time value 'X', such as Xw, Xd, Xh or Xm, to represent weeks (w), days (d), hours (h) and minutes (m), respectively.

    • If you do not specify a time unit, hour will be assumed.

    • Your current conversion rates are 1w = 5d and 1d = 8h.

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包

打赏作者

夜流冰

你的鼓励将是我创作的最大动力

¥1 ¥2 ¥4 ¥6 ¥10 ¥20
扫码支付:¥1
获取中
扫码支付

您的余额不足,请更换扫码支付或充值

打赏作者

实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值