【PMP】Daily practice 1115

本文探讨了在项目执行过程中遇到的突发情况,如关键测试人员缺席,以及如何有效管理项目全生命周期的风险。项目经理面对测试人员缺失时,应遵循升级流程获取授权签署同意。同时,为了管理不确定性,项目经理应创建风险登记册并定义应对策略。
摘要由CSDN通过智能技术生成

1、 一个项目团队在周末对一个项目升级进行测试。客户指定的质量保证测试人员未能出席调试测试以及进行签署同意,测试人员和直线经理都联系不上,团队经常完成这些项目,并且经过大量测试后,确信该设施将在周一上午完美运行。项目经理应该怎么做?
A project team is commissioning a project upgrade over the weekenThe client-appointed quality assurance tester fails to be present for commissioning testing and sign-off. Neither the tester nor the line manager can be contacte The team, frequently engaged in similar projects with extensive testing experience,is confident that the facility will perform flawlessly on Monday morning. What should the project mananger do?
A、 指示团队中止升级,并安排周一上午与项目发起人进行紧急评审会
Instruct the team to suspend the upgrade,and schedule an emergency review meeting with the project sponsor for Monday morning.
B、 让团队保持待命状态,以防万一在周一上午之前可以联系到测试人员
Keep the team on standby in case the tester can be reached before Monday morning.
C、 指示客户团队的一位成员代替指定的测试人员进行验收测试以及签署同意
Instruct a member of the client team to conduct the acce

  • 0
    点赞
  • 1
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值