SAP PP 计划外发料与计划内发料在WM层面的差异初探

 

Process order header material: HR0072

BOM item materials:

  1. RR0078
  2. R0078A
  3. R0880A

 

Control cycle master data: they are all pick parts.

 

  1. create& release process order, M36040

 

 

 

 

Release process order, TR was created: 271122.

 

Convert TR to TO, TO 245032.

 

LT12 to confirm this TO,

 

Save it. The batch of components are updated into process order,

 

  1. MB1A to issue components to process order, this is planned goods issue,

 

 

 

Save it,

  1. We can find the stock in PSA storage type was consumed:

 

  1. If business team need consume more raw material than planned quantity, maybe need to consume another batch, for example, need to consume more quantity 1 KG for the raw material RR0078, another batch 2002000057.

4.1) Then LB01 to create TR by manually, with WM movement type 997(or SAP standard movement type 319),

 

 

 

TR 271123,

 

4.2)  Convert this TR to TO document,

 

At this moment, the new batch 2002000057 will NOT be updated into process order since it was unplanned.

 

 

4.3) Then MB1A + 261 , try to do planned goods issue.

 

 

Failed. We cannot do planned goods issue for this process order now.

 

Try to do unplanned goods issue,

 

Enter,

 

Save it, see the WM details data for this material document item,

 

The raw material was consumed from GI storage type, but not from PSA storage type.

That’s the difference of WM level effect between planned GI and unplanned GI to process order.

 

4.4) The WM stock status for this material/batch combination,

There is 1 KG in PSA storage type, but -1 KG in GI storage type.

 

We need to do bin to bin stock transfer (LT01+999) from PSA to GI area in order to adjust stock balance.

 

2017-03-06 写于苏州市吴中区

 

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值