MC-4/11/22/400安全、正确地使用PacDrive伺服放大器的功能

本文介绍了在初次使用PacDrive伺服放大器前,必须进行的预操作检查和系统质量要求,包括环境条件、设备连接、电源和信号线检查等,以确保安全、降低维护成本和提升系统可靠性。

摘要生成于 C知道 ,由 DeepSeek-R1 满血版支持, 前往体验 >

在第一次使用PacDrive伺服放大器之前,请阅读并理解本手册中包含的材料。特别注意安全信息(见2.3剩余风险)。只有符合“员工的选择和资格”的人员才能在PacDrive伺服放大器上工作。本手册的副本必须提供给PacDrive伺服放大器的工作人员。本手册旨在帮助您安全、正确地使用PacDrive伺服放大器的功能。按照本手册中的说明:

•避免风险

•降低维修成本和PacDrive伺服放大器的停机时间

•延长PacDrive伺服电路的使用寿命

•提高PacDrive伺服系统的可靠性。

Pre operation inspection and quality requirements of the system
(1) Appearance inspection and requirements
Before putting into operation, check the temperature, humidity, and cleanliness of the environment where the equipment is located, check that the cable holes in the electronic equipment room are sealed properly, and also check that each power supply fuse meets the requirements. The cabinet numbers and names of each control station cabinet, I/O cabinet, and on-site transition terminal cabinet are clearly marked, and terminal block wiring diagrams are attached. The common power lines, grounding wires, and lighting wires of each control station cabinet, I/O cabinet, and on-site transition terminal cabinet should be connected properly, correctly, and firmly; The attachments are complete and intact. The lighting inside the cabinet is normal. The various signal wires, signal shielding wires, protective wires, and power wires entering the intermediate transition terminal cabinet and on-site control station cabinet from the site should be connected in good condition, correctly, firmly, and aesthetically pleasing; The cable brand and wiring number are complete and clear.


(2) Inspection and quality requirements for each workstation
1) For the on-site control station, various signal wires, power lines, and grounding wires that enter the on-site control station cabinet from the site should be checked and connected to ensure the integrity of the system and reduce defects.
2) Check all power modules, main controller modules, functional modules, and other equipment in the on-site control station cabinet, and ensure that they are fully restored and installed correctly and firmly. All connecting cables and wiring should be connected in good, correct, firm, and aesthetically pleasing condition; The redundant communication cables of each workstation should be connected properly, correctly, firmly, and aesthetically pleasing.
3) Check the data communication lines inside the on-site control station and between each on-site control station. The connections should be intact, correct, and firm, and the connecting cables and wiring should be intact, correct, and firm.
4) For functional service stations such as operator stations and engineer stations, it is necessary to check the power supply of computers, CRTs, printers, etc. at each station and ensure that they are properly connected; Also, check the connection between the dedicated keyboard, mouse or trackball, CRT signal line, and printer signal line to each computer for completeness and correctness; The redundant data communication lines between various functional service control stations and the communication lines between workstations should be connected in good, correct, and firm condition; Finally, check that the power supply of the large screen monitor and its connection to the computer are intact.

评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值