第9章章节试题

一 序

听完视频,觉得本章没有啥计算题,概念相对简单应该快速通过吧。12道题,答题用时:7分钟,还是翻车了

二  题目

1、 [单选] X项目团队中的部分团队成员同时还要承担Y项目的工作,X项目估算活动历时必须用到下面哪一项?
Some members of the project X team also undertake the work of project Y at the same time. Which of the following items should be used for estimating activities of project X?

  •  A:历时上其它项目中类似活动的历时;
    The duration of similar activities in other projects in the past;
  •  B:项目Y的进度计划;
    schedule of project Y;
  •  C:资源日历;
    resource calendar;
  •  D:成员所在职能部门经理的意见。
    comments from the functional managers of the members.

正确答案:C 你的答案:C

解析:资源日历是项目团队成员(资源)的工作日历,项目经理通过了解资源日历,才能够知道每个资源可用的时间,避开与其它项目工作的冲突。 见9.2.1.2。

2、 [单选] 下面都是项目经理职位带来的权力,除了:
All the following are forms of power derived from the project manager’s position EXCEPT:

  •  A:正式
    Formal
  •  B:奖励
    Reward
  •  C:惩罚
    Penalty
  •  D:专家
    Expert

正确答案:D 你的答案:D

解析:专家/权威的权力是项目经理自身的权力,非职位带来的权力。

5种权利,ABC是职位,专家、威望参照是自身的领导力。

3、 [单选] 项目团队的一位新成员因为看不懂网络图、也不知道关键路径、浮动时间这些术语很难与项目经理和其他团队成员交流。这个问题应该如何解决?
A new member of the project team is difficult to communicate with the project manager and other team members because he can't know the network diagram, the critical path and the floating time. How should the problem be solved?

  •  A:新成员所在的职能部门经理有责任提供针对性培训;
    The functional department manager of the new member is responsible for providing targeted training;
  •  B:项目经理有责任为新成员提供针对性培训;
    Project manager is responsible for providing targeted training to the new member;
  •  C:公司人力资源部有责任为新成员提供针对性培训;
    The human resources department of the company is responsible for providing targeted training to the new member;
  •  D:要求新成员自学项目管理以满足工作需要。
    The new member should be required to self-study project management to meet the needs of work.

正确答案:B 你的答案:B

解析:团队成员的培训由谁负责,要看需要培训的内容,如果是项目管理的知识和技能就应该由项目经理负责,业务技术和专业技能应该有他的职能经理负责,公司管理规章制度等是由人力资源部负责。当然,安排满足项目工作要求的资源是以上所有管理者的共同责任。

 视频上专门讲过了。“借用育还”

4、 [单选] 下面哪种冲突解决技术虽然不容易做到,但能做到的话总会带来最满意的效果?
Which of the following conflict resolution technologies is not easy to implement, but will always bring the most satisfying results?

  •  A:强制
    Forcing
  •  B:缓和
    Smoothing
  •  C:妥协
    Compromise
  •  D:解决
    Problem solving

正确答案:D 你的答案:D

解析:合作/解决是冲突解决技术中最好的,双赢 win-win,且副作用最少,效果最彻底,作用最持久。

除了合作/解决外其他都不是双赢。

5、 [单选] 项目绩效评估和团队绩效评估不同,项目绩效评估主要关注:
Project performance appraisals are different from team performance assessment in that project performance appraisals focus on:

  •  A:团队成员个人在项目中的绩效表现;
    How an individual team member is performing on the project.
  •  B:项目团队效率评价;
    An evaluation of the project team’s effectiveness.
  •  C:团队建设工作;
    A team-building effort.
  •  D:降低员工流动率。
    Reducing the staff turnover rate.

正确答案:A 你的答案:B

解析:团队绩效评估针对团队建设的有效性,侧重于团队整体而非个人,见 9.4.3.1。项目绩效评估是通过每个团队成员的工作绩效来评价项目绩效,绩效不好的成员应通过培训改善。见 9.4.2.6。

B应该归为团队绩效,老师在分析A的时候,书上没有直接标出来,而是通过培训侧面说的。

6、 [单选] 项目经理应该把项目团队开会的纪律和表决的规则写进:
Which document should the project manager write about meeting discipline and voting rules of the project team?

  •  A:项目章程
    project charter
  •  B:团队章程
    team charter
  •  C:沟通管理计划
    communication management plan
  •  D:相关方参与计划
    stakeholder engagement plan

正确答案:B 你的答案:B

解析:团队章程是为团队创建团队价值观、共识和工作指南的文件。见 9.1.3.2。

老师举例:3个章程

7、 [单选] 项目经理观察到有些项目团队成员开始调整工作习惯以配合其他成员。但是,他们彼此仍然缺乏信任。项目经理可以得出下列哪一项结论?
The project manager observed that some project team members began to adjust their work habits to accommodate other members. But they still lack trust. Which of the following conclusions can the project manager draw?

  •  A:团队处于规范阶段,很有可能进入到成熟阶段
    The team is in the norming stage and is likely to enter the mature stage.
  •  B:团队处于规范阶段,很有可能退回到震荡阶段
    The team is in the norming stage and is likely to return to the storming stage.
  •  C:团队处于震荡阶段,很有可能进入到规范阶段
    The team is in the storming stage and it is likely to enter the norming stage.
  •  D:团队处于震荡阶段,很有可能退回到形成阶段
    The team is in the storming stage and is likely to return to the forming stage.

正确答案:B 你的答案:B

解析:开始调整自己的工作习惯以配合其他成员,说明已经进入规范阶段,但是彼此仍然不信任,当前状态不稳定,如果遇到干扰因素或新的冲突可能会退回震荡阶段。

9.4 P338 塔克曼阶梯理论5个阶段。

8、 [单选] 在一个大型项目快结束时,紧张状态上升,团队成员之间冲突越来越频繁。冲突的焦点是因为两个有宿怨的成员彼此敌对,团队的注意力已经脱离了项目的目标。为了恢复秩序,项目经理打发掉两名团队成员,让其他人代替他们。项目经理使用的是哪种冲突解决策略?
At the end of a large project, tensions rise and conflicts between team members become more frequent. The focus of the conflict is because two feuding members are hostile to each other, and the team's attention has been distracted from the project's goals. To restore order, the project manager removed the work of the two members in advance and let others replace them. What kind of conflict resolution strategy does the project manager use?

  •  A:强制
    Forcing
  •  B:回避
    Avoiding
  •  C:妥协
    Compromising
  •  D:解决
    Solving

正确答案:A 你的答案:A

解析:被强制的一方虽然体验很差,但在情况紧急时,为顾全大局强制也是必要的、有效的正确选择。

人都开了,当然是强制。

9、 [单选] 项目范围已明确定义,且项目团队之前做过此类工作。进度绩效指数为0.7,在调查完差异之后,项目经理了解到,项目发起人要求在现场工作的一名团队成员去执行他认为对项目很重要的额外活动。若要避免这种情况,项目经理应该:
The project scope is well defined and the project team has performed this type of work before. The schedule performance index is 0.7. After investigating the deviation, the project manager realizes that one of the team members, working onsite is being asked by the project sponsor to perform extra activities believed important to the project. Which action should the project manager take to avoid situations?

  •  A:改进项目沟通,确保所有需求都得到满足;
    Improve project communications, making sure all needs are being satisfied.
  •  B:根据新的需求对项目范围进行变更;
    Make changes to the project’s scope based on the new demands.
  •  C:向这位同事明确说停止范围蔓延;
    Give a clear statement to the coworker do discontinue the scope creep.
  •  D:对于必须的变更,与变更控制委员会沟通。
    Communicate that changes must be done through the change control board.

正确答案:C 你的答案:D

解析:项目章程对项目经理有明确授权,项目上资源的调配和工作的分配这是项目经理的权力,发起人无权越俎代庖,直接指挥团队成员。

老师说D沟通跟CCB是不搭的,正确的是提变更。题目侧重点是额外活动。那就是范围蔓延了。正确额做法是发起人提变更请求,走整体变更控制流程。B相对于C来说,C更好。

10、 [单选] 下列哪一种方式有助于调动团队成员最大潜能和发挥他们的主观能动性?
Which of the following ways can help motivate team members to maximize their potential and leverage their initiative?

  •  A:集中办公
    War-room
  •  B:虚拟团队
    virtual team
  •  C:自组织团队
    self-organizing team
  •  D:强矩阵
    strong matrix

正确答案:C 你的答案:C

解析:自组织团队自己分工、自主决策、风险共担、利益共享。有利于发挥成员的潜能和主动性。见 9 资源管理的趋势和新兴实践。

P310 自组织。

11、 [单选] 在项目规划阶段,项目经理认识到一名项目相关方对项目可交付成果的理解存在分歧,从而造成与该项目相关方的关系紧张。要解决这个问题,项目经理应该怎么做?
During the project planning phase, the project manager realized that a project stakeholder had a disagreement about the understanding of the deliverables, resulting in a tension between the project manager and the stakeholder. What should the project manager do to solve this problem?

  •  A:忽略该项目相关方的意见,根据多数相关方的理解确定项目范围;
    ignore the opinions of this stakeholder and define the project scope according to the understanding of majority;
  •  B: 安排与这位相关方的会谈,了解造成分歧的原因并积极解决分歧;
    Arrange meeting with the stakeholder to get the reason of the understanding differences and actively address them; 
  •  C:将该问题上报给项目发起人,让他们解决这个问题;
    Escalate the issue to the project sponsor so that they can solve the problem;
  •  D:让权力更大的其他相关方出面说服这位相关方做出妥协。
    Ask other stakeholders with greater power to convince this stakeholder to compromise.

正确答案:B 你的答案:B

解析:遇到分歧,应首先考虑“合作/解决问题“的冲突解决策略,积极主动正面沟通永远是第一选择。

直觉吧。

12、 [单选] 交期临近但项目进度落后,马上面临圣诞节长假,项目经理需要在让所有团队成员放弃假期支付加班补偿和延期交付项目承担罚款之间做出选择,他需要用以下哪一个分析技术?
The delivery time is near but the project is behind schedule. Facing with the Christmas holidays, the project manager needs to choose between asking all team members to give up their holidays with overtime compensation and delay the delivery of the project and bear the penalty. Which of the following analytical techniques does he need?

  •  A:储备分析
    Reserve analysis
  •  B:挣值分析
    Earned value analysis
  •  C:备选方案分析
    Alternative analysis.
  •  D:成本效益分析
    Cost-benefit analysis.

正确答案:C 你的答案:C

解析:让团队成员加班和延期交付项目都是当前的备选方案,项目经理需要综合分析得失利弊做出选择,这个分析技术是备选方案分析。见 9.2.2.5。

AB是进度D项目一开始做不做。

 

 

  • 0
    点赞
  • 0
    收藏
    觉得还不错? 一键收藏
  • 0
    评论
评论
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值