1 [单选] 在每日站会期间,开发人员提出了一个影响产品质量并需要解决方案的问题,项目经理应该做什么?
During the daily stand-up, the developer raises a problem that affects product quality and needs a solution. What should the project manager do?
- A:延长冲刺
Extended sprint - B:召开一次回顾会议
Hold a retrospective meeting - C:与团队确定根本原因
Determine the root cause with the team - D:允许开发团队解决该问题
Allow the development team to solve the problem
正确答案:C 你的答案:C
解析:解析:每日站立会议提出的影响产品质量的问题,并需要解决方案,需进行根本原因分析,在明确原因的基础上,提出解决方案A:敏捷项目管理不能扩展冲刺。B:迭代没有完成,项目过程中出现问题,在解决问题,还不到回顾的时候。D:解决问题首先要弄清原因。
2
[单选] 作为敏捷管理从业人士,项目经理已接受某新公司提供的工作岗位。直到第三个迭代,项目一直进展的非常好,但从第四个迭代开始,项目团队开始注意到速率大幅下滑,项目现在已经进入了第七个迭代,但燃尽图仍未见好转的趋势。这种情况发生的原因是什么?
As an Agile management practitioner, the project manager has accepted a job offer from a new company. Until iteration 3, the project was doing very well, but from iteration 4, the project team began to notice a significant drop in the rate. The project is now in iteration 7, but the burndown chart shows no improvement. Why does this happen?
- A:每日站立会议要么未举行,要么效率低下
Daily stand-up meetings are either not held or inefficient - B:看板图未被用于组织和跟踪变更工作
Kanban diagrams are not used to organize and track change efforts - C:产品负责人未举行待办事项列表梳理会议
Product owner does not hold to-do list combing meeting - D:回顾会议要么未举行,要么效率低下
Retrospectives are either not held or inefficient
正确答案:D 你的答案:A
解析:解析:敏捷知识点-冲刺回顾会议。冲刺回顾会议的目的是就团队可以如何提高他们的工作方式,以及就未来的迭代改进计划达成一致。在冲刺回顾中,团队将认识到他们做得好的领域以及有待改进的领域。包括什么