【PMP 每日一题】2020.3.25

[PMP 每日一题]

2020.3.25每日一题:
A software project is undergoing testing during the final user acceptance stage, and
acceptance is anticipated by the next day. A user unexpectedly realizes that a new feature is
required to run the current software. The user tells the developer that it must be completed by
the next day or it will not be approved. The developer believes that two days are required to
complete this feature. What should the project manager do?
A. Refuse to develop the feature, as it is out of scope.
B. Ask the user to submit a written change request, and obtain permission from the customer’s
project manager.
C. Work overtime and revise the software in order to ensure timely project approval.
D. Perform an analysis with the developer to determine a workaround.

  • 8、一个软件项目已在最后的用户阶段测试中,按照计划明天就要验收。用户突然发现必须要有一个新功能才能使目前的软件往下运行,用户告诉开发人员,必须要明天完成,否则拒绝验收这个软件项目。软件开发人员觉得需要2天时间才能开发完这个功能。项目经理应该怎么做?
    A 拒绝开发,因为这是新功能要求,不在项目范围之内
    B 要求用户书面提交变更请求,并得到客户方项目经理的批准
    C 加班修改软件来保证明天的项目验收
    D 和开发人员一起分析,找变通方案来解决当前问题

  • 知识点:变更

  • 解析:选B。按照正常的变更程序。用户提交正式的书面变更请求给到项目团队,并得到客户方项目经理PM的批准。

  • 实施整体变更控制的流程图如下:
    在这里插入图片描述
    PS:欢迎留言指出错误之处与交流~

评论 1
添加红包

请填写红包祝福语或标题

红包个数最小为10个

红包金额最低5元

当前余额3.43前往充值 >
需支付:10.00
成就一亿技术人!
领取后你会自动成为博主和红包主的粉丝 规则
hope_wisdom
发出的红包
实付
使用余额支付
点击重新获取
扫码支付
钱包余额 0

抵扣说明:

1.余额是钱包充值的虚拟货币,按照1:1的比例进行支付金额的抵扣。
2.余额无法直接购买下载,可以购买VIP、付费专栏及课程。

余额充值