2020.4.16每日一题:
You and and your team have just created a schedule network diagram.You have come up with the estimates and have defined the durations and subsequently have identified the Critical Path.You now decide to do a ‘Backward Pass’ through the Schedule Network Diagram - what would you be calculating ?
A. The Early Start and Early Finish for each activity
B. The Late Start and Late Finish for each activity
C.The duration of the other paths
D. The duration of the critical path
-
22、你和你的团队刚刚创建了一个进度网络图。你已经提出了估算并定义了持续时间,随后确定了关键路径。你现在决定通过进度网络图执行“逆推法”,下面那些是正确的算法?
A 每项活动的最早开始和最早完成
B 每项活动的最晚开始和最晚完成
C 其他路径的持续时间
D 关键路径的持续时间 -
知识点:进度网络图的顺推、逆推
-
解析:选B。顺推法:关键路径法中的一种技术,在进度模型中,从项目开始日期或给定时点出发,正向推导,计算出最早开始和最早结束日期。
顺推法:关键路径法中的一种技术,在进度模型中,从项目开完工日期出发,反向推导,计算出最晚开始和最晚结束日期。