【PMP 每日一题】
2020.5.14每日一题:
A company is planning to develop a new product. Project stakeholders come from different
countries and regions, speak various languages, and have diverse political and cultural
backgrounds.What should be a priority for the project manager when developing the
communications management plan?
A. Information confidentiality and sensitivity
B. Project environment
C. The number of communication channels
D. Technological availability
-
某个公司计划进行一个产品开发项目。干系人来自不同的国家及地区,使用不同的母语语言,拥有不同的政治及文化背景。项目经理在制定沟通计划时应优先考虑下列哪项因素?
A 信息的保密和敏感度
B 项目环境
C 沟通渠道的数量
D 技术的可用性 -
选项:选B。根据题意描述的题意,项目环境将是项目比较大的沟通制约因素,做项目沟通计划需要考虑事业环境因素。